Gateway 2: Contract Award Approval - Communal Lighting and Lightning Protection Contract
ApprovedExecutive1 paper
AI summaryCabinet approved the award of the communal lighting and lightning protection contract to Spokemead Maintenance Ltd [D]. The estimate is £896,000 per annum for 3 years, with 2 optional years taking the total to £4,480,000 [D].
Written from the decision and the officer reportPDF Pro
OutcomeApproved3 years, with an option for 2 more years [D]
Money£896,000 per annum [D]3 years: £2,688,000 [D]. 2 optional years: £4,480,000 total [D].
What happens nextStart on 01 Oct 2013 [P8]Minimum 10 calendar days standstill before award [P105]
Who it affectsCouncil housing and leaseholders [P12] [P57]Housing blocks, sheltered units, hostels and tenant halls [P12]
What was decided
Spokemead Maintenance Ltd was selected for the communal lighting and lightning protection contract at £896,000 per annum for 3 years from 1 October 2013 [D]. The estimated 3 year value is £2,688,000, with an option for 2 further years in 12 monthly increments, taking the estimated total to £4,480,000 [D].
The contract covers responsive repairs to communal lighting and landlord supplies, annual lightning protection tests, lightning protection repairs, stock condition surveys, emergency lighting tests and builders work [P4] [P5]. It includes housing blocks, sheltered housing units, temporary accommodation hostels and tenant halls [P12]. Report P4, P5, P12
Spokemead achieved the highest overall score under the Most Economically Advantageous Tender [P36]. Price carried 70% of the evaluation and quality carried 30% [P29] [P31]. Report P29, P31, P36
Why
Procurement advice confirms that the recommended provider scored highest on both quality and price [P98]. Spokemead therefore achieved the highest overall score in the Most Economically Advantageous Tender [P36]. Report P36, P98
The services maintain Housing's existing assets and provide regular inspections and maintenance to comply with current legislation [P12]. Communal lighting also supports community safety, helps reduce fear of crime and deters vandalism of property [P17]. Report P12, P17
The two services were combined into one contract to obtain efficient and cost effective services [P13]. The award produces a 3.5% (£31,360) saving on existing rates, allowing more work to be completed [P64]. Report P13, P64
What happens next
After award, weekly mobilisation meetings and lightning protection site visits will begin with Spokemead Maintenance Ltd, the current lighting contractor, and Central High Rise Ltd [P40]. Report P40
Officers will complete handover preparations, arrange stakeholder meetings and monitor works, quality, commercial performance and the contract through monthly reviews [P38] [P40] [P42] [P43]. Report P38, P40, P42, P43
The council must allow a minimum 10 calendar day standstill, post the award notice in OJEU within 48 days and start the contract on 01 Oct 2013 [P104] [P105] [P8]. Report P8, P104, P105
The money
£896,000 per annum Estimated annual contract sum
£2,688,000 Estimated value of the 3 year contract
£4,480,000 Estimated total if 2 optional years are used
3.5% (£31,360) Saving on the existing schedule of rates Report P64
£896,171 Combined annual budget after the budget transfer Report P82
£746,171 per annum Current HRA budget, with £150,000 identified in Repairs and Maintenance for lightning protection Report P82
£2,688,513 Budget allowance for the three years Report P82
£4,480,855 Budget allowance for the five year period Report P82
Options considered
Chosen: Award to Spokemead Maintenance Ltd. It achieved the highest overall score in the Most Economically Advantageous Tender. Report P36
Chosen: Combine the two service contracts into one. This followed the approved Gateway 1 procurement strategy. Report P3
Chosen: Include an option for 2 further years in 12 monthly increments. The extension option forms part of the approved award.
Implications
Financial: The £150,000 identified in the Repairs and Maintenance budget will transfer to Engineering. The resulting annual budget is £896,171, sufficient for the £896,000 estimate, with £2,688,513 allowed for 3 years and £4,480,855 for 5 years [P82]. Report P82
Financial: The award gives a 3.5% (£31,360) saving, allowing more work within the retained budget. Future Building Maintenance Index increases must be contained within the available budget [P64] [P83] [P109] [P110]. Report P64, P83, P109, P110
Legal: The Schedule 2 consultation under the Landlord and Tenant Act 1985 is complete, with 18 observations from 17,130 notices and none affecting progress [P89] [P90]. Work is service chargeable to leaseholders, and further Schedule 3 consultation is required for individual work exceeding £250 for a leaseholder [P91] [P113] [P114]. Report P89, P90, P91, P113, P114
Legal: The council must allow a minimum 10 calendar day standstill between notifying the successful tenderer and making the award, then post the award notice in OJEU within 48 days of the award [P104] [P105]. The contract includes a break clause allowing termination without consideration of loss or expense [P53]. Report P53, P104, P105
Risk: Spokemead Maintenance Ltd will provide a Performance Bond and was assessed as a below average risk contractor [P52] [P87]. No Parent Company Guarantee will be obtained because it has no parent company [P52]. Report P52, P87
Equalities: The contractor confirmed compliance with the council's Equal Opportunity Policy and London Living Wage requirements [P67] [P68]. The report also identifies local jobs and apprenticeship opportunities, including for young people [P60] [P61]. Report P60, P61, P67, P68
Other: All replaced lamps, light fittings and equipment must be disposed of under the latest Waste Electrical and Electronic Equipment Regulations (WEEE). Recyclable packaging must go to a recycling centre, no hazardous materials may be used, and the contractor will receive the council's asbestos register to avoid exposure [P71] [P72] [P73] [P74]. Report P71, P72, P73, P74
Staffing: There is no impact on council staff. Officers already perform the ordering and monitoring roles, and these functions will continue under the new contract [P78] [P79]. Report P78, P79
Who and where
Council housing leaseholders Report P12, P57, P89
Residents of housing blocks, sheltered housing units, temporary accommodation hostels and tenant halls Report P12
Local residents employed by Spokemead Maintenance Ltd Report P65
Young people taking up local apprenticeships Report P60, P61
Local schools offered workplace experience Report P62
Council staff responsible for ordering and monitoring Report P42, P78, P79
Spokemead Maintenance Ltd and Central High Rise Ltd during contract transition Report P40
Timeline
15 May 2012: Gateway 1 procurement strategy approved Report P8
20.7.12: Notices of Intention served on all council leaseholders Report P89
23 Jan 2013, 04 March 2013 and 19 March 2013: Invitation to tender issued, tender return deadline reached and tender evaluation completed Report P8
5.4.13 and 9.5.13: Notices of Proposal served on all leaseholders and the consultation period ended Report P89, P90
26 June 2013: Gateway 2 contract award approval Report P8
11 July 2013, 21 July 2013, 22 July 2013 and 25 July 2013: Implementation notification, standstill end, contract award and contract register entry, then OJEU publication Report P8
30 Sept 2016 and 30 Sept 2018: Initial contract completion, then completion if extension options are exercised Report P8, P9
Plain English for the jargon
Most Economically Advantageous Tender: The evaluation approach used for this tender. Spokemead achieved the highest overall score [P36] [P98].
PQQ and ITT: The PQQ is the prequalification questionnaire used to assess bidders. The ITT is the Invitation to Tender sent to shortlisted bidders [P19] [P20] [P22].
OJEU: The official journal where the contract award notice is to be published [P8] [P104].
Gateway 2: The contract award approval stage for this procurement [P6] [P8].
Standstill period: A minimum of 10 calendar days after the successful tenderer is notified, allowing unsuccessful tenderers to challenge [P105].
DCRB and CCRB: The Departmental and Corporate Contract Review Boards, which reviewed this Gateway 2 decision [P8] [P106] [P131] [P132].
TUPE: The consultation referred to in the report. It is not required for Spokemead because it is the incumbent contractor, and there are no implications for Central High Rise Ltd [P40].
London Living Wage (LLW): The minimum pay equivalent introduced for contractors where appropriate. Spokemead confirmed it met the requirements, with quality and cost monitored at annual review [P68].
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item17
Resolved
That the award of the communal lighting and lightning protection contract to Spokemead Maintenance Ltd for the estimated sum of £896,000 per annum for the period of 3 years from 1 October 2013 to the value of £2,688,000; with the option to extend by a further 2 years in 12 monthly increments making the total estimated contract value £4,480,000 be approved.
Word for word from the decision Southwark published for this meeting.Source: moderngov.southwark.gov.uk
Report to Cabinet (decommissioned, for the Executive after, 13 pages
Recommendation
1. That the cabinet approves the award of the Communal Lighting and Lightning Protection contract to Spokemead Maintenance Ltd for the estimated sum of £896,000 per annum for the period of 3 years from 1 October 2013 to the value of £2,688,000; with the option to extend by a further 2 years in 12 monthly increments making the total estimated contract value £4,480,000.
1 BACKGROUND INFORMATION
2. A Gateway 1 report setting out the strategy for the procurement of Communal Lighting and Lightning Protection contract was approved on 15 May 2012. The strategy set out that the services being supplied by two (2) separate contractors would be combined to tender for one (1) contract through the tendering process. This strategy was adhered to.
3. The scope of the proposed contract encompasses the following work streams;
• Responsive repairs to communal lighting and landlords supplies • Annual tests to lightning protection systems • Responsive repairs to lightning protection systems • Stock condition surveys of all communal lighting covered in this contract • Emergency lighting tests; and • Builders work in connection with services.
Procurement project plan (Key Decision)
4. See table below:
Activity Completed by: Forward Plan for Gateway 2 decision 01 March 2013 Approval of Gateway 1: Procurement Strategy Report 15 May 2012 Issue Notice of Intention 12 Sept 2012 Invitation to tender 23 Jan 2013 Closing date for return of tenders 04 March 2013 Completion of evaluation of tenders 19 March 2013 Issue Notice of Proposal 09 April 2013 DCRB Review: Gateway 2 02 May 2013 CCRB Review: Gateway 2 16 May 2013 Notification of forthcoming decision – despatch of Cabinet 28 May 2013 agenda papers Approval of Gateway 2: Contract Award Report 26 June 2013 Scrutiny Call-in period and notification of implementation of 11 July 2013 Gateway 2 decision Alcatel Standstill Period (end date) 21 July 2013 Contract award 22 July 2013 Add to Contract Register 22 July 2013 Publication of award notice in Official journal of European 25 July 2013 (OJEU) TUPE Consultation period 30 Sept 2013 Contract start 01 Oct 2013 Contract completion date 30 Sept 2016
2 Activity Completed by: Contract completion date – if extension(s) exercised 30 Sept 2018
KEY ISSUES FOR CONSIDERATION
Description of procurement outcomes
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Cabinet (decommissioned, for the Executive after at Southwark and we tell you when its next papers are published, before the meeting rather than after it.
Review of Void Disposal StrategyThat the progress of disposals of void housing properties since April 2009 be noted. 2. That the importance of void d...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.