Investigation in to Asbestos Incident, Westonbirt Court

Noted Executive 3 papers

AI summaryCabinet noted two asbestos incident investigations and required a Special Cabinet report on the south borough repairs contract [D]. The Leader delegated monitoring of training recommendations, and all Council response costs will be reclaimed from Mears Ltd [D] [P37].

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedMonitoring delegated; further contract report requested [D] [P2] [P3]
MoneyCosts reclaimed from Mears Ltd [P37]Officer time stayed within existing budgets [P37]
What happens nextSpecial Cabinet report in July [P31]Further report on south borough repairs award [P31]
Who it affectsEight adults exposed [P8]At two leasehold properties in Peckham [P8]

What was decided

Cabinet noted the two investigation reports into the asbestos incident at Westonbirt Court, which were attached as appendices. Report P1, P56

Cabinet agreed to receive a further report at a Special Cabinet meeting about the award of the repairs and maintenance contract for the south of the borough. Report P2, P31

Cabinet noted the officers' recommendations in the internal investigation report at Appendix 1. The Leader delegated monitoring of their implementation to the Deputy Leader and Cabinet Member for Housing Management. Report P3, P25

Why

The internal investigation found that the Mears Ltd operative and supervisor failed to identify or consider the asbestos insulating board, despite warning flags and the right policies, procedures and systems being in place. Report P21, P22, P24

The investigation pointed to individual failings rather than corporate or structural failings at Mears Ltd. Officers were satisfied that the company had no systematic failings, after Mears Ltd agreed compensation, indemnity and further training. Report P24, P27, P28

Deferral allowed Cabinet to assess the findings and any service implications, but delay beyond July 2013 could jeopardise continuity and cause operational, financial and legal implications. Report P13, P36, P51

What happens next

A further report on the long term repairs and maintenance contract award will be received at a Special Cabinet meeting arranged for later in July. Report P31, P51

The Deputy Leader and Cabinet Member for Housing Management will monitor implementation of the four immediate and two medium/long term asbestos awareness training recommendations. Report P3, P25

Mears Ltd said further asbestos awareness training would start shortly. Further investigations into the reporting delay are under way, with recommendations to follow for the Strategic Director and Cabinet Member. Report P27, P29

Options considered

  • Chosen: Note both investigation reports Report P1, P17, P19
  • Chosen: Defer the repairs and maintenance contract award. Officers needed to establish whether the incident affected the recommendation to award the contract to Mears Ltd. Report P13, P36
  • Chosen: Receive a further report at a Special Cabinet meeting. This would allow Cabinet time to consider the investigation findings and any implications for service delivery. Report P2, P31
  • Chosen: Delegate monitoring of the training recommendations. The report sought approval for the Deputy Leader and Cabinet Member for Housing Management to monitor implementation. Report P3, P25

Implications

  • Risk: The interim contract expires on 2 October 2013, so delay beyond July 2013 could jeopardise the smooth transition and continuity of service. Report P50, P51
  • Financial: Council response costs will be reclaimed from Mears Ltd, and the overall impact on HRA Repairs and Maintenance will be neutral. Report P37, P48
  • Legal: Mears Ltd agreed to fully compensate and fully indemnify the Council against claims from residents. Report P27
  • Risk: The six day gap between exposure and confirmation resulted from delays in T Brown and Southwark Council reporting and responding to the incident correctly. Report P29
  • Staffing: Recommendations require Mears Ltd to ensure that all operatives, supervisors and managers are fully trained in asbestos awareness and complete annual refresher training. Report P23
  • Legal: The Council reserved all rights under the contract, including the indemnity for all loss and damage caused by Mears' negligence or breach of contract. Report P46
  • Financial: Any claim would be redirected to Mears in line with normal practice. The Council's liability insurance is subject to an excess. Report P38
  • Other: Protective measures included temporary accommodation, sealing two bedrooms, remedial work and satisfactory air tests. Report P12

Who and where

  • Eight adults living in two leasehold properties in Peckham Report P8
  • Residents elsewhere in Westonbirt Court Report P12, P35
  • Two Mears Ltd staff involved in the incident Report P19
  • Tenants and residents receiving repairs and maintenance services in the south of the borough Report P50, P51

Timeline

  • 19 June 2013: A Mears Ltd operative displaced asbestos at two leasehold properties in Peckham, exposing eight adults. Report P8
  • 25 June: Pennington Choices completed a management survey and confirmed the incident. Report P11
  • 26 June 2013: The internal investigation commenced, and Cabinet deferred the long term contract award. Report P13, P17
  • Friday 5 July: Residents returned after remedial work and satisfactory air test results. Report P12
  • Monday 8 July 2013: Council officers met Mears Ltd, which agreed compensation, indemnity and further asbestos awareness training. Report P27
  • Tuesday 9 July: The Compliance Operations Team investigation was completed. Report P17, P53
  • later in July: A Special Cabinet meeting was arranged to receive a further report on the contract award. Report P31
  • 2 October 2013: The interim repairs and maintenance contract was due to expire. Report P50

Plain English for the jargon

  • Compliance Operations Team: Council specialist team that completed the internal investigation [P17]
  • Gateway 2 report: Report recommending the long term repairs and maintenance contract award [P7]
  • interim contract: 12 month service arrangement from 3 October 2012 [P5]
  • indemnity: Mears Ltd undertaking to cover claims against the Council [P27]
  • asbestos awareness training: Training for operatives, supervisors and managers, with annual refreshers [P23]
  • Special Cabinet: Cabinet meeting arranged to receive the contract award report [P31]
  • HRA Repairs and Maintenance: Repairs and maintenance service with a neutral overall incident impact [P48]
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item24

Resolved

Decisions of the Cabinet 1. That the contents of the two investigation reports into the asbestos incident at Westonbirt Court included as appendices to the report be noted. 2. That a further report be received at a special cabinet meeting regarding the award of the repairs and maintenance contract for the south of the borough. 3. That officers' recommendations in the internal investigation report at Appendix 1 of the report be noted. Decision of the Leader of the Council 4. That the monitoring of the implementation of the recommendations (referred to in 3 above) be delegated to the deputy leader and cabinet member for housing management.
Word for word from the decision Southwark published for this meeting. Source: moderngov.southwark.gov.uk

Follow this further

Built from Southwark's papers

What the report saysPro

Report to Cabinet (decommissioned, for the Executive after, 7 pages

Recommendations

1. That the Cabinet note the contents of the two investigation reports into the asbestos incident at Westonbirt Court included as appendices to this report.

2. That the Cabinet agree to receive a further report at a Special Cabinet meeting regarding the award of the repairs and maintenance contract for the south of the borough.

3. That the Cabinet note officers' recommendations in the internal investigation report at Appendix 1 and the Leader of the Council delegate the monitoring of the implementation of these to the Deputy Leader and Cabinet Member for Housing Management

BACKGROUND INFORMATION

4. Following the termination of the repairs and maintenance contract with Morrison Facilities Services Limited on 2 October 2012, the council put in place interim arrangements to deliver the service for 12 months from 3 October 2012. Following competition, Mears Ltd were appointed from the Watford Community Housing Trust repairs and maintenance framework.

1 5. Putting in place this 12 month interim contract provided the council with the space and time it required to work through the options available for the long-term delivery of the repairs service. The procurement strategy for the long-term repairs and maintenance contract was approved by Cabinet on 17 July 2012.

6. The Gateway 2 report recommending the award of the long term contract for Repairs and Maintenance was due to be considered by Cabinet at their meeting on 14 May and subsequently on 26 June 2013. This report was to recommend the contract be awarded to Mears Ltd.

7. On 19 June 2013, a Mears Ltd operative (working under the interim contract) displaced some asbestos at two leasehold properties in Peckham while trying to trace the source of a leak. This meant that eight adults living in the two properties were exposed to asbestos, although the exposure in one of the properties was limited to one unoccupied bedroom.

8. Although the incident occurred on 19 June, it took six days for the asbestos exposure to be confirmed, initially because the Mears Ltd operative did not identify the material as asbestos. The council’s heating contractor, T. Brown, attended on 20 June to remedy the cause of the water penetration and did correctly identify the damaged panel as being asbestos. However, the T. Brown operative advised the resident and his own back-office, who failed to notify the council immediately.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Compliance Operations Team investigation reportAppendix 1 38 pages Download
PDF
Mears Ltd investigation reportAppendix 2 4 pages Download
PDF
Report: Investigation into Asbestos Incident, Westonbirt CourtReport 7 pages DownloadRead as text

At this meeting

Whole meeting

Who was there

8 of 11 attended
PJ
Councillor Peter JohnChair, present
IW
Councillor Ian WingfieldDeputy Chair, present
FC
Councillor Fiona ColleyCommittee Member, present
DD
Councillor Dora Dixon-FyleCommittee Member, present
BH
Councillor Barrie HargroveCommittee Member, apologies
RL
Councillor Richard LivingstoneCommittee Member, present
CM
Councillor Catherine McDonaldCommittee Member, present
VM
Councillor Victoria MillsCommittee Member, present
VW
Councillor Veronica WardCommittee Member, present
EK
Eleanor KellyOfficer, expected
DF
Doreen Forrester-BrownOfficer, expected

More from Southwark Cabinet (decommissioned, for the Executive after

All decisions
MeetingDecisionOutcome
28 May 2026 Election of Chair for the meetingThat Councillor Maisie Anderson be elected chair for this meeting. Decided Open
28 May 2026 Notification of any items of business which the chair deems urgentIt was agreed that all the deputations would be heard so that consideration of these representations could be given p... Agreed Open
28 May 2026 Disclosure of Interests and DispensationsDecision Maker (IDM) report in respect of this issue. Councillor Peter John also declared a personal, non prejudicial... Decided Open
28 May 2026 Review of Void Disposal StrategyThat the progress of disposals of void housing properties since April 2009 be noted. 2. That the importance of void d... Noted Open
28 May 2026 Housing Revenue Account - Approval of Housing Revenue Budget Account 2011/12That the savings required to deliver a balanced housing revenue account (HRA) for 2011/12 be noted. 2. That the propo... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies