Quarterly Capital Monitoring Outturn Report 2012/13

Noted Executive 5 papers

AI summarySouthwark Cabinet noted the 2012/13 capital outturns and approved virements, funded variations and 2013/14 reprofiling. General Fund and housing investment budget differences were £63m and £7m [D] [P14]

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedOutturns noted, variations and 2013/14 reprofiling approved [D]
Money£63m and £7m budget differencesGeneral Fund and Housing Investment Programme variations [P14]
What happens nextFurther reprofiling during 2013/14Service managers to review forecasts using current information [P5] [P173]
Who it affectsCapital programme and borough residentsSchools, housing, public realm and offices affected [P27] [P89] [P103] [P134]

What was decided

Cabinet noted the 2012/13 General Fund capital outturn and overall programme through 2021/22. It also noted the 2012/13 Housing Investment Programme outturn and overall programme through 2015/16. Report P2, P3

Cabinet approved the virements and funded variations for both capital programmes. Report P4

Cabinet approved reprofiling expenditure and resources into 2013/14. Further reprofiling during 2013/14 was noted as necessary. Report P5

Why

General Fund expenditure varied from budget by £63m, while Housing Investment Programme expenditure varied by £7m. The differences largely came from budget reprofiling across schemes, driven by complexities in procuring contracts and works, contract management and monitoring. Report P14

General Fund expenditure included £178.1m for the 160 Tooley Street freehold acquisition. Excluding that cost, revised spend was £80.9m, slightly lower than £84.2m in 2011/12. Report P17

Housing Investment Programme expenditure increased by 60% from £53.5m. Budget variation fell from 49% to 7%, showing increased and accelerated Warm, Dry and Safe investment. Report P19

What happens next

Further forecasts will be reprofiled during 2013/14 using more up to date information on procurement and contract management. Report P5, P173

Housing Investment Programme schemes will be reviewed for reprofiling in 2013/14. Report P135

Cabinet will receive a further paper on the emerging primary strategy for school places and available funding. Report P28

The money

  • £63m General Fund expenditure variation against budget Report P14
  • £7m Housing Investment Programme expenditure variation against budget Report P14, P19
  • nearly £1billion Total forecast spend across the capital programme Report P9
  • £403.7m Overall Housing Investment Programme budget for 2012/13 to 2015/16 Report P134
  • £259.0m Total General Fund departmental expenditure in 2012/13 Report P17
  • £85.6m Housing Investment Programme expenditure in 2012/13 Report P19, P134
  • £178.1m 160 Tooley Street freehold acquisition included in General Fund expenditure Report P17, P43
  • £128m Accumulated cash balance committed to existing capital projects Report P161, P164

Options considered

  • Chosen: Note the General Fund outturn and programme position Report P2
  • Chosen: Note the Housing Investment Programme outturn and programme position Report P3
  • Chosen: Approve virements and funded variations. Updates budgets to the position available at 1 April 2013. Report P174
  • Chosen: Approve 2013/14 reprofiling. Responds to the outturn and favourable variances. Report P5, P172

Implications

  • Financial: The 2012/13 outturns produced a general favourable variance for reprofiling in 2013/14. Further changes are expected during the year. Report P5, P172, P173
  • Financial: The capital programme had forecast spending of nearly £1billion. It was a major part of the Council's financial activities. Report P9
  • Financial: General Fund expenditure included £178.1m for 160 Tooley Street. Excluding it, revised spend was £80.9m compared with £84.2m in 2011/12. Report P17
  • Legal: The Council must maintain a balanced budget and monitor its finances throughout the year under section 28 of the Local Government Act 2003. The capital programme must support continuous improvement under the Local Government Act 1999. Report P185, P186
  • Risk: Delivery is exposed to programme slippage, management capacity, funding uncertainty and changes to funding regimes. Controls include scheme level tracking, dedicated finance teams, monthly monitoring, regular programme refreshes, reserves and forward planning. Report P177
  • Financial: Disabled Facilities Grant demand is likely to create significant pressure from 2013/14. Assistance levels and the mix of grants and loans are proposed to change. Report P125, P126, P127
  • Risk: Some lower moderate risk high rise blocks still need work. Further surveys may lead to approval of additional resources. Report P142
  • Other: The report was considered to have no or very limited direct impact on local people. The wider capital programme is expected to improve borough amenities and infrastructure. Report P179

Who and where

  • People who live, learn, visit or do business in the borough Report P9
  • Children using primary school places Report P27
  • Adults using Southwark Resource Centre and Stones End Report P30
  • Residents benefiting from Warm, Dry and Safe works Report P140, P143
  • Disabled residents needing housing adaptations Report P126
  • Council staff and customers using Queens Road offices Report P103, P108
  • Residents benefiting from transport and public realm schemes Report P89, P99
  • Residents benefiting from waste, park and cemetery improvements Report P53, P64, P67

Timeline

  • 17 July 2012: The 2011/12 capital outturn was presented to Cabinet. Report P7
  • 25 September 2012: Cabinet noted the refreshed General Fund and housing investment programmes. Report P8
  • 11 December 2012: Cabinet approved the 160 Tooley Street freehold acquisition. Report P17, P43
  • 31 March 2013: Capital balances were unapplied but committed to existing projects. Report P164
  • during 2013/14: Further reprofiling will follow review of procurement and contract management information. Report P173
  • summer of 2013/14: The Willow Walk hostel was scheduled to start on site. Report P151
  • by 31 March 2014: The Housing CCTV Refresh was expected to be completed. Report P78
  • by the end of 2015/16: The Warm, Dry and Safe programme was expected to be fully committed. Report P137

Plain English for the jargon

  • General Fund capital programme: Capital programme reported separately from housing investment. [P2] [P11]
  • Housing Investment Programme: Housing capital programme for 2012/13 to 2015/16. [P3] [P134]
  • Outturn: Final 2012/13 expenditure compared with the relevant budget. [P14]
  • Virement: Reallocation of resources within programme budgets. [P177]
  • Funded variation: Agreed budget change included at 1 April 2013. [P174]
  • Reprofiling: Movement of expenditure and resources between financial years. [P172]
  • Warm, Dry and Safe: Housing works for efficiency, heating and fire safety. [P137] [P140] [P142]
  • Capital receipts: Property disposal income used to finance capital work. [P160] [P168]
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item16

Resolved

That the outturn position for 2012/13 for the general fund capital programme including the overall position of the programme for the period 2012/13 to 2021/22 as detailed in Appendix A and D of the report be noted. 2. That the outturn position for 2012/13 for the housing investment programme, including the overall position of the programme for the period 2012/13 to 2015/16, as detailed in Appendix B of the report be noted. 3. That the virements and funded variations to the general fund and housing investment capital programme as detailed in Appendix C of the report be approved. 4. That the re-profiling of the expenditure and resources in the new financial year 2013/14 in light of the 2012/13 outturn position for both the general fund and housing investment programmes as detailed in Appendix A, B and D of the report be approved and it be noted that further re-profiling will be required during 2013/14 based on more up to date information available at that time.
Word for word from the decision Southwark published for this meeting. Source: moderngov.southwark.gov.uk

Follow this further

Built from Southwark's papers

What the report saysPro

Report to Cabinet (decommissioned, for the Executive after, 20 pages

Recommendations

That cabinet:

1. Notes the outturn position for 2012/13 for the general fund capital programme including the overall position of the programme for the period 2012/13 to 2021/22 as detailed in Appendix A and D.

2. Notes the outturn position for 2012/13 for the housing investment programme, including the overall position of the programme for the period 2012/13 to 2015/16, as detailed in Appendix B

1 3. Approves the virements and funded variations to the general fund and housing investment capital programme as detailed in Appendix C.

4. Approves the re-profiling of the expenditure and resources in the new financial year 2013/14 in light of the 2012/13 outturn position for both the general fund and housing investment programmes as detailed in Appendix A, B and D and note further re-profiling will be required during 2013/14 based on more up to date information available at that time.

BACKGROUND INFORMATION

5. On 17 July 2012, the 2011/12 capital outturn report was presented to the cabinet. This reported the capital outturn position at the end of 2011/12 and approved the continued expenditure and resources, including new bids up the period 2020/21. At that time, the total value of the general fund programme stood at £383.8m including the Southwark Schools for the Future programme and the housing investment programme stood at £432.9m.

6. On 25 September 2012, cabinet noted the refreshed general fund capital programme of £387m for the period 2012/13 to 2021/22 including the agreed new capital bids of £59.8m. Cabinet also noted the housing investment programme of £397.5m for the period 2012/13 to 2015/16.

7. With a total forecast spend of nearly £1billion the capital programme represents a major element of the Council’s financial activities. It has a significant and very visible impact on the borough and hence on the lives of those who live, learn, visit and or do business in the borough.

8. Due to the size and scale of the capital programme and the number of projects involved, it is inevitable that unforeseeable delays can occur which lead to some variations against planned spend. Historically the capital programme has been over programmed in year to compensate for these variations, whilst retaining a balanced programme overall.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
General fund capital programme summary 2012/13 at OutturnAppendix A 1 pages Download
PDF
Housing revenue account capital programme summary: 2012/13 at OutturnAppendix B 2 pages Download
PDF
Funded virements and variations for approvalAppendix C 6 pages Download
PDF
General fund capital programme detailsAppendix D 5 pages Download
PDF
Report: Quarterly Capital Monitoring Outturn Report 2012/13Report 20 pages DownloadRead as text

At this meeting

Whole meeting

Who was there

8 of 11 attended
PJ
Councillor Peter JohnChair, present
IW
Councillor Ian WingfieldDeputy Chair, present
FC
Councillor Fiona ColleyCommittee Member, present
DD
Councillor Dora Dixon-FyleCommittee Member, present
BH
Councillor Barrie HargroveCommittee Member, apologies
RL
Councillor Richard LivingstoneCommittee Member, present
CM
Councillor Catherine McDonaldCommittee Member, present
VM
Councillor Victoria MillsCommittee Member, present
VW
Councillor Veronica WardCommittee Member, present
EK
Eleanor KellyOfficer, expected
DF
Doreen Forrester-BrownOfficer, expected

On this subject at Southwark

Search all
  1. Quarterly Capital Monitoring Outturn Report 2012/13This decision
  2. Quarterly Capital Monitoring Report Quarter 1Approved
  3. Quarterly Capital Monitoring Report Quarter 2Approved
  4. Quarterly Capital Monitoring Report Quarter 3Approved
  5. Quarterly Capital Monitoring Report Outturn and Capital Programme Refresh 2012-2022Noted
  6. Quarterly Capital Monitoring Report Quarter 3Noted

More from Southwark Cabinet (decommissioned, for the Executive after

All decisions
MeetingDecisionOutcome
28 May 2026 Election of Chair for the meetingThat Councillor Maisie Anderson be elected chair for this meeting. Decided Open
28 May 2026 Notification of any items of business which the chair deems urgentIt was agreed that all the deputations would be heard so that consideration of these representations could be given p... Agreed Open
28 May 2026 Disclosure of Interests and DispensationsDecision Maker (IDM) report in respect of this issue. Councillor Peter John also declared a personal, non prejudicial... Decided Open
28 May 2026 Review of Void Disposal StrategyThat the progress of disposals of void housing properties since April 2009 be noted. 2. That the importance of void d... Noted Open
28 May 2026 Housing Revenue Account - Approval of Housing Revenue Budget Account 2011/12That the savings required to deliver a balanced housing revenue account (HRA) for 2011/12 be noted. 2. That the propo... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies