London Borough of Southwark
Cabinet (decommissioned, for the Executive after, Thursday 28 May 2026 at 4.00pm

Gateway 1: Major Works Contractor Framework

Approved Executive 1 paper

AI summaryCabinet approved a four lot major works contractor procurement strategy, covering building work, district heating and communal electrical work, as the route to a restricted tender. The estimated value is up to £368m for four years from 1 September 2014 [D][P17][P39][P88].

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedFour lot housing works framework [P3][P17]
MoneyUp to £368m total [D]Up to £92m annually for four years [P90]
What happens nextRestricted tender planned [P39]Mini competitions award individual schemes [P70]
Who it affectsHousing and related services [D]Building, heating and communal electrics [P17]

What was decided

Cabinet approved the procurement strategy for a housing and related services major works contractor framework covering four lots [D][P3]. Report P3

The framework covers low value building work, high value building work, district heating, and communal or standalone electrical work [P17]. Report P17

Individual works contracts were not approved at this stage. Scheme awards would follow mini competitions, with Gateway 2 authority still to be sought [D][P22][P34][P70]. Report P22, P34, P70

Why

The council needed a more flexible approach to awarding future major works, with value for money, consistent quality and speedy delivery [P12]. Report P12

A framework would offer resilience and an easy procurement route if existing partnering contracts or contractors had problems [P13]. Report P13

The council judged its own framework with second stage mini tenders the best option. It would retain competition, support high quality firms and include community benefits such as local apprenticeships [P23][P34][P36][P70]. Report P23, P34, P36, P70

What happens next

Tender under a full EU restricted procedure. Use a pre qualification questionnaire to shortlist bidders, then invite shortlisted firms to tender [P39][P99]. Report P39, P99

Advertise the framework in OJEU and write to leaseholders before the notice for information [P34][P39][P63]. Report P34, P39, P63

Use mini competitions for individual schemes, with Gateway 2 authority sought for scheme awards. The report also proposes delegation of framework award authority to the Deputy Leader and cabinet member for housing management [P4][P5][P6][P22][P70]. Report P4, P5, P6, P22, P70

The money

  • up to £368m Total estimated contract value [P88] Report P88
  • up to £92m Total estimated annual cost [P90] Report P90
  • £30m Lot 1 estimated annual value for schemes up to the value of £3m [P17] Report P17
  • £50m Lot 2 estimated annual value for schemes above £3m [P17] Report P17
  • £10m Lot 3 estimated annual value for district mains, boilers and internal works [P17] Report P17
  • £2m Lot 4 estimated annual value for communal and standalone electrics [P17] Report P17
  • £15m Maximum individual order, with only Lot 2 reaching this size [P37] Report P37
  • £4.34m EU threshold above which a nominated contractor may require separate procurement [P106] Report P106

Options considered

  • Rejected: Tender each works contract as and when required. This was time consuming and bureaucratic, created a new process for every scheme, and could not build long term contractor relationships [P31] Report P29, P30, P31
  • Rejected: Bring major building works in house. Southwark Building Services only carried out day to day repairs [P32] Report P30, P32
  • Rejected: Use an existing internal or external framework. Existing external frameworks could not be used because there had been no specific consultation with leaseholders [P33] Report P30, P33
  • Chosen: Create a council framework with a second stage tender. It would use high quality firms, retain competition through individual mini tenders, and allow permitted leaseholder nominations [P34][P36] Report P34, P36

Implications

  • Financial: Capital costs would be met from the housing investment programme. Current funding is approved up to 31 March 2016, with further capital approval needed beyond that period [P89]. Report P89
  • Financial: There is no minimum contract value, and work would be commissioned only against confirmed funding. Lower separate tender prices could put leaseholder service charges under partnering contracts at risk [P90][P112][P119]. Report P90, P112, P119
  • Legal: The full EU restricted procedure and the additional rules for frameworks in regulation 19 would apply. Each work package would require statutory leaseholder consultation, although the framework itself would not be consulted on under section 20. A valid leaseholder contractor nomination above the OJEU limit may require a separate OJEU procurement [P92][P99][P106][P118]. Report P92, P99, P106, P118
  • Risk: Provider failures are mitigated through KPI monitoring, suspension or termination, default and no fault exit provisions, financial checks and, where appropriate, performance bonds [P23][P43][P85]. TUPE risk at call off is considered low, but bidders must take independent legal advice and the council will not give assurances or warranties [P54][P55]. Report P23, P43, P54, P55, P85
  • Equalities: The final tender evaluation panel would include one leaseholder and one tenant representative [P68]. The London Living Wage would apply to relevant staff working directly on contracts and relevant sub consultant staff [P80]. Report P68, P80
  • Climate: There are no specific environmental considerations at this stage. E tendering would be used where possible to reduce printing and paper, and contractors would meet requirements for timber, CO2 emissions and safer lorries [P82][P83]. Report P82, P83
  • Staffing: No specific staffing implications are identified. Procurement resources can come from existing housing and community services, supported by external and internal resources [P87][P100]. Report P87, P100
  • Other: The framework would initially supplement existing partnering contracts. A review of value for money and performance would decide whether those contracts were extended or work moved to the framework [P18][P19]. Report P18, P19

Who and where

  • Housing leaseholders Report P71, P92, P118, P119
  • Tenants and residents Report P68, P75, P76
  • The council's housing capital programme Report P48, P85
  • Housing and community services staff Report P87, P100
  • Framework providers and their subcontractors Report P70, P80
  • Local residents seeking jobs, training or apprenticeships Report P36, P73, P76
  • Local suppliers and subcontracting firms Report P76, P78
  • Existing housing works contractors Report P18, P19, P20

Timeline

  • 3 Jan 2014: Advertise the contract [P51] Report P51
  • 28 March 2014: Issue the invitation to tender [P51] Report P51
  • 12 May 2014: Closing date for the return of tenders [P51] Report P51
  • 16 June 2014: Complete tender evaluation, including project board approval [P51] Report P51
  • 28 July 2014: Approval of the Gateway 2 contract award report [P51] Report P51
  • 18 August 2014: Contract award [P52] Report P52
  • 1 Sept 2014: Contract start [P52] Report P52
  • 31 August 2018: Contract completion date [P52] Report P52

Plain English for the jargon

  • Framework agreement: A list of contractors covering defined work types, with individual schemes awarded after competition [P12][P16][P70].
  • Lot: A separate category of work within the framework [P16].
  • Mini competition: A tender among capable providers in the relevant lot for a specified scheme [P70].
  • OJEU: The Official Journal of the European Union, where the framework will be advertised [P63].
  • PQQ and ITT: The pre qualification questionnaire and Invitation to Tender stages used to shortlist bidders and invite bids [P39].
  • MEAT: Most Economically Advantageous Tender, using a 60:40 split of price and quality [P68].
  • KPI: Key Performance Indicator covering areas such as satisfaction, value, employment, training and efficiency [P23].
  • TUPE: A possible employment transfer issue at call off; the council assesses the risk as low [P54].
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item14

Resolved

That the procurement strategy outlined in the report for a housing and related services major works contractor framework covering 4 lots (for main building works, district heating works and communal electrics work as further detailed in paragraph 9 of the report at a total estimated annual cost of up to £92m for a period of four (4) years from 1 September 2014, making a total estimated contract value of up to £368m be approved.
Word for word from the decision Southwark published for this meeting. Source: moderngov.southwark.gov.uk

Follow this further

Built from Southwark's papers

What the report saysPro

Report to Cabinet (decommissioned, for the Executive after, 17 pages

Recommendations

Recommendation for the Cabinet

The cabinet approves

1. The procurement strategy outlined in this report for a housing and related services major works contractor framework covering 4 lots (for main building works, district heating works and communal electrics work as further detailed in paragraph 9 at a total estimated annual cost of up to £92m for a period of four (4) years from 1 September 2014, making a total estimated contract value of up to £368m. Recommendations for the Leader of the Council

That the Leader of the council delegates

2. Authority to the Deputy Leader and cabinet member for housing management to award and enter into the framework agreement with four lots.

3. Authority to the Deputy Leader and cabinet member for housing management to award and enter into the overarching agreement with all providers on the framework agreement to cover management and governance provisions and the delivery of soft benefits.

BACKGROUND INFORMATION

4. On 14 June 2010 the council awarded main housing building works partnering contracts to five contractors covering different geographical areas of the borough. The contracts awarded and the areas they cover are set out in the table below:

Contractor Area covered by the contract A & E Elkins Nunhead and Peckham Rye/Dulwich Breyers Borough and Bankside/Walworth Apollo/Keepmoat Camberwell/Peckham Saltash Street properties, TA halls, hostels, major voids Wates Rotherhithe/Bermondsey

5. The contracts with Wates Construction Limited (Wates) and Breyer Group PLC (Breyers) have since been mutually concluded leaving three in place with Apollo Property Services Group Limited/Keepmoat Limited (Keepmoat), A & E Elkins Limited (A & E Elkins) and Saltash Enterprises Limited (Saltash). Since the contracts with Wates and Breyers ended, Keepmoat have been providing back up for the Bermondsey/Rotherhithe areas and A & E Elkins for Borough and Bankside/Walworth.

6. These contracts expire in June 2015 but have options to extend for a further five years.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Report: Gateway 1: Major Works Contractor FrameworkReport 17 pages DownloadRead as text

At this meeting

Whole meeting

Who was there

8 of 11 attended
PJ
Councillor Peter JohnChair, present
IW
Councillor Ian WingfieldDeputy Chair, present
FC
Councillor Fiona ColleyCommittee Member, present
DD
Councillor Dora Dixon-FyleCommittee Member, present
BH
Councillor Barrie HargroveCommittee Member, apologies
RL
Councillor Richard LivingstoneCommittee Member, present
CM
Councillor Catherine McDonaldCommittee Member, present
VM
Councillor Victoria MillsCommittee Member, present
VW
Councillor Veronica WardCommittee Member, present
EK
Eleanor KellyOfficer, expected
DF
Doreen Forrester-BrownOfficer, expected

On this subject at Southwark

Search all
  1. Gateway 1: Major Works Contractor FrameworkThis decision
  2. Gateway 2 Major Works Framework ContractsApproved
  3. Gateway 3: Variation Decision - Housing Major Works ContractsApproved
  4. Gateway 1: Procurement Strategy Approval - Heating and Water Repairs, Maintenance, Refurbishment and Replacement Works and Communal Heating Major Works FrameworkApproved

More from Southwark Cabinet (decommissioned, for the Executive after

All decisions
MeetingDecisionOutcome
28 May 2026 Election of Chair for the meetingThat Councillor Maisie Anderson be elected chair for this meeting. Decided Open
28 May 2026 Notification of any items of business which the chair deems urgentIt was agreed that all the deputations would be heard so that consideration of these representations could be given p... Agreed Open
28 May 2026 Disclosure of Interests and DispensationsDecision Maker (IDM) report in respect of this issue. Councillor Peter John also declared a personal, non prejudicial... Decided Open
28 May 2026 Review of Void Disposal StrategyThat the progress of disposals of void housing properties since April 2009 be noted. 2. That the importance of void d... Noted Open
28 May 2026 Housing Revenue Account - Approval of Housing Revenue Budget Account 2011/12That the savings required to deliver a balanced housing revenue account (HRA) for 2011/12 be noted. 2. That the propo... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies