Directly Funded Housing Delivery: Phase 2

Noted Executive 3 papers

AI summarySouthwark Cabinet agreed in principle to Phase 2 council housing on listed sites, with expected costs of £55.6m, and approved resident consultation and key procurement delegations. [D] [P159]

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedListed sites proceed to scheme development [P4]
Money£55.6m expected cost [P159]Estimated Phase 2 development costs [P159]
What happens nextConsultation strategies to be agreed [P6]Required separately for each Phase 2 scheme [P6] [P99]
Who it affectsResidents needing council housing [P144] [P147]Older people, disabled people and nearby residents [P145] [P146] [P149]

What was decided

Cabinet agreed in principle that the listed schemes would be worked up as Phase 2 of direct council housing delivery on council owned sites. The schedule covers Joseph Lancaster Nursery Annex, Canada Estate, Daniels Road Car Park, Albion Street Civic Centre, Commercial Way, Castle Resource Centre, Weston Street Garages, 95A Meeting House Lane, Welsford Street Garages, Colombo Street, Goschen Estate, Lugard Rd, Fenham Road, Tenda Road, Nunhead Lane at numbers 35 and 41, Kinglake Street and Pelier St. [D] [P4] [P90] [P91] Report P4, P90, P91

Cabinet agreed a specific resident consultation strategy for each Phase 2 scheme with the relevant representative body. Officers will explore a Joseph Lancaster Nursery annexe partnership with Leathermarket Gardens Joint Management Board. Old Kent Road / St James Road and Castle Resource Centre will enter Phase 1 procurement. [D] [P6] [P7] [P8] Report P6, P7, P8

Cabinet noted the Phase 2 procurement proposals and Greater London Authority funding bid position, including the need for a formal grant agreement for all awarded funding. It also noted preparations for 10,000 further homes and approved delegations for Phase 2B procurement approvals, Phase 1 gateway 2 decisions and necessary scheme substitutions. [D] [P9] [P10] [P11] [P14] [P15] [P16] Report P9, P10, P11, P14, P15, P16

Why

Phase 2 was intended to build on Phase 1 momentum and provide short term continuity while long term framework arrangements were procured. Initial capacity assessments estimated 327 homes, with 241 social rented homes, 36 Shared Ownership homes and 50 homes for private sale. [P94] [P105] Report P94, P105

The programme would increase good quality affordable housing in a borough with high housing need, including shortages of larger homes and extra care provision. [P137] [P144] [P145] [P146] Report P137, P144, P145, P146

Resident consultation was intended to shape designs, identify local issues and ease disruption from construction. The financial schedule showed sufficient funding for intended works, but funding conditions required monitoring and programme cost review if funding was not secured. [P99] [P149] [P150] [P151] [P166] [P167] Report P99, P149, P150, P151, P166, P167

What happens next

Officers and relevant representative bodies would agree a consultation strategy for each Phase 2 scheme, hold drop ins with outline designs, adjust designs as appropriate, complete formal planning consultation and continue engagement through detailed design and delivery. [P99] Report P99

Prepare a gateway 1 report on Phase 2B professional services and construction for decision in December 2013, and a separate Phase 2A professional services report for decision in November 2013 if a negotiated extension is feasible. The Leader delegated Phase 2B procurement approvals and Phase 1 gateway 2 decisions to the chief executive, and necessary scheme substitution decisions to the cabinet member for regeneration and corporate strategy. [P14] [P15] [P16] [P114] [P121] Report P14, P15, P16, P114, P121

Work would continue on proposals for 10,000 further homes, including a housing investment plan, delivery model, financial viability testing and site delivery strategy. The outcome would be reported to Cabinet in November. [P123] [P126] [P127] [P129] [P130] Report P123, P126, P127, P129, P130

The money

  • £55.6m Estimated Phase 2 development costs Report P159, P165
  • £44.5million Budget identified for Phase 1 Report P156, P157
  • £228k GLA grant for 10 Hidden Homes Report P78
  • £158k GLA funding for remodelling homes Report P78
  • £65m Minimum developer in lieu payment, with receipt uncertain Report P73
  • £3.4m Usable Right to Buy receipts realised in 2012/13 Report P75
  • £11.2m Estimated usable Right to Buy receipts in 2013/14 Report P75
  • £170,000 per unit Phase 2 modelling average, above £160,000 used for Phase 1 Report P94

Options considered

  • Chosen: Include Old Kent Road / St James Road in Phase 1. The site was previously identified for Home Office Approved Premises and a feasibility study had been commissioned. [D] [P44] Report P44
  • Chosen: Include Castle Resource Centre in Phase 1 procurement. The scheme was already more advanced and included church relocation and six homes. [D] [P90] Report P90
  • Chosen: Explore a Joseph Lancaster Nursery annexe partnership. A capacity study had been commissioned for the site beside estate managed by Leathermarket JMB. [D] [P90] Report P90
  • Rejected: Include Salisbury Estate Car Park in Phase 2. There was no resident support for a new council development, although an outline scheme and capacity assessment were proposed. [P93] Report P93
  • Rejected: Include Styles House in Phase 2. A joint proposal with a private developer depended on resident support, although future affordable homes would need to enter the programme. [P93] Report P93
  • Rejected: Include Braganza Street Workshops in Phase 2. A negotiated disposal for a mixed scheme already proposed council affordable homes and a possible model for other disposals. [P93] Report P93
  • Chosen: Substitute schemes when individual projects become undesirable. Suitable replacements would support the programme's overall momentum and balance. [D] [P97] Report P97

Implications

  • Financial: Phase 2 is estimated to cost £55.6m and deliver 327 homes. Rental income from 241 social rented homes is expected to contribute positively to the Housing Revenue Account. [P94] [P159] Report P94, P159
  • Financial: Funding sources carry conditions. If funding is not secured, the programme cost must be reviewed to remain affordable and alternative funding sources sought. [P166] Report P166
  • Legal: Any Greater London Authority grant award requires a formal agreement whose terms must not conflict with council objectives. Developer in lieu payments require Planning Committee approval, and possible housing appropriation must be explored for Nunhead Lane, Commercial Way, Cator Street and Albion Civic Suite. [P10] [P45] [P79] [P158] Report P10, P45, P79, P158
  • Risk: Construction prices are likely to rise with demand, particularly in the residential sector. The housing investment plan will also test rent policy, business plan assumptions and financial viability. [P120] [P126] [P127] Report P120, P126, P127
  • Staffing: Officer time can be contained within existing revenue resources, but team capacity and skills for the longer term programme will be assessed. [P133] [P169] Report P133, P169
  • Equalities: The programme is expected to increase housing options for households in need, older people and disabled people. Officers will keep monitoring equalities impact assessments. [P144] [P145] [P146] [P147] Report P144, P145, P146, P147
  • Financial: Extra care assets and ongoing maintenance will be charged to the Housing Revenue Account, with detailed budgets needed for each scheme. [P160] Report P160
  • Other: Residents near new developments may experience short term inconvenience and disruption, with longer term community benefits expected. [P149] [P150] Report P149, P150

Who and where

  • Southwark households in housing need Report P144, P147
  • Older people needing extra care housing Report P140, P145
  • People with disabilities needing housing options Report P146, P147
  • Existing tenants on nearby estates Report P150
  • Residents of proposed Phase 2 sites Report P90, P91, P98
  • Neighbouring residents during construction Report P149, P150
  • Council housing management and extra care services Report P147, P160
  • Local employment and training candidates Report P141

Timeline

  • 11 October 2013: Final officer report completed Report P174
  • November 2013: Gateway 1 decision due on Phase 2A professional services Report P114
  • November: Work on proposals for 10,000 further homes due to be reported to Cabinet Report P130
  • December 2013: Gateway 1 decision due on Phase 2B and later procurement Report P121
  • 2014/15 to 2017/18: Projected sequence of Phase 2 construction stages Report P95
  • Jun 2014 to Dec 2016: Phase 2A construction window Report P111
  • Jul 2015 to Jun 2017: Phase 2B construction window Report P111
  • by 2050: Viable delivery model sought for 10,000 additional homes Report P126

Plain English for the jargon

  • AHF: Pooled developer in lieu payments and usable Right to Buy receipts, restricted to new affordable housing. [P68] [P157] [P158]
  • RTB receipts: Right to Buy receipts usable for new housing, subject to DCLG guidance. [P75]
  • GLA: Greater London Authority, the grant funder for Building the Pipeline awards. [P76] [P77] [P79]
  • T&RA: Tenants and residents association involved in each Phase 2 consultation strategy. [P6] [P99]
  • JMB: Leathermarket Joint Management Board. [D] [P90]
  • Gateway 1 and Gateway 2: Gateway 1 sets procurement strategy. Gateway 2 covers work package and contractor decisions. [P15] [P66] [P114] [P121]
  • HRA: Housing Revenue Account, receiving rental income and meeting ongoing maintenance costs. [P159] [P160]
  • S106: Planning agreement that can generate developer in lieu payments for affordable housing. [P69] [P158]
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item15

Resolved

Decisions of the Cabinet 1. That progress to date of phase 1 of the directly delivered housing delivery programme be noted. 2. That it be agreed in principle that the schemes listed in paragraph 45 of the report are worked up in accordance with the individually identified recommendations as Phase 2 of an overall programme for direct delivery of new council housing on council owned sites. 3. That the consultation undertaken on some schemes in paragraph 45 of the report to date be noted. 4. That a specific strategy for consulting with residents is agreed with the relevant tenants and residents association / other relevant representative body for each of the Phase 2 schemes. 5. That officers explore opportunities to develop the Joseph Lancaster Nursery annexe site in partnership with the Leathermarket Gardens Joint Management Board. 6. That agreement be given to the inclusion of the Old Kent Road / St James Road site referred to in paragraph 24 of the report and the Castle Resource Centre, referred to in paragraph 45 of the report) within the Phase 1 Programme, and therefore to be delivered as part of the Phase 1 procurement arrangements. 7. That the procurement approaches and proposals for phase 2 outlined in paragraphs 57 to 63 of the report be noted. 8. That the position in respect of funding bids to the Greater London Authority for grant funding as outlined in paragraph 40 of the report be noted and that it be further noted that the council will be required to enter into a formal agreement with the Greater London Authority in relation to all funding awarded. 9. That the ongoing preparation of proposals to develop 10,000 further homes, as outlined in paragraphs to 64 to 70 of the report be noted. Recommendations for the Leader of the Council 10. That the approval for the procurement approaches for phase 2B, both professional services and construction be delegated to the chief executive. 11. That gateway 2 decisions for work packages in Phase 1 be delegated to the chief executive. 12. That decisions on scheme substitution that prove necessary because of unforeseen circumstances in Phase 1 and Phase 2 be delegated to the cabinet member for regeneration and corporate strategy.
Word for word from the decision Southwark published for this meeting. Source: moderngov.southwark.gov.uk

Follow this further

Built from Southwark's papers

What the report saysPro

Report to Cabinet (decommissioned, for the Executive after, 22 pages

Recommendations

Recommendations for the Cabinet

That the cabinet

1. Notes progress to date of Phase 1 of the directly delivered housing delivery programme.

2. Agrees in principle that the schemes listed in paragraph 45 are worked up in accordance with the individually identified recommendations as Phase 2 of an overall programme for direct delivery of new council housing on council owned sites.

3. Notes the consultation undertaken on some schemes in paragraph 45 to date.

4. Agrees that a specific strategy for consulting with residents is agreed with the relevant T&RA / other relevant representative body for each of the Phase 2 schemes.

5. Agrees the inclusion of the Old Kent Road / St James Road site referred to in paragraph 24, and the Castle Resource Centre, referred to in paragraph 45 f) within the Phase 1 Programme, and therefore to be delivered as part of the Phase 1

1 procurement arrangements.

6. Notes the procurement approaches and proposals for Phase 2 outlined in paragraphs 57 to 63.

7. Notes the position in respect of funding bids to the Greater London Authority for grant funding as outlined in paragraph 40 and notes that the council will be required to enter into a formal agreement with the Greater London Authority in relation to all funding awarded.

8. Notes the ongoing preparation of proposals to develop 10,000 further homes, as outlined in paragraphs to 64 to 70.

Recommendations for the Leader of the Council

That the Leader

9. Agrees to delegate the approval for the procurement approaches for Phase 2B, both professional services and construction, to the chief executive.

10. Agrees to delegate gateway 2 decisions for work packages in Phase 1 to the chief executive.

11. Agrees to delegate decisions on scheme substitution that prove necessary because of unforeseen circumstances in Phase 1 and Phase 2 to the cabinet member for regeneration and corporate strategy.

BACKGROUND INFORMATION

12. In October 2012, in considering a report on the direct delivery of new council housing, the cabinet resolved :

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Proposed phase 2Appendix 1 1 pages Download
PDF
Overall programmeAppendix 2 1 pages Download
PDF
Report: Direct Housing Delivery Phase 2Report 22 pages DownloadRead as text

At this meeting

Whole meeting

Who was there

8 of 11 attended
PJ
Councillor Peter JohnChair, present
IW
Councillor Ian WingfieldDeputy Chair, present
FC
Councillor Fiona ColleyCommittee Member, present
DD
Councillor Dora Dixon-FyleCommittee Member, present
BH
Councillor Barrie HargroveCommittee Member, apologies
RL
Councillor Richard LivingstoneCommittee Member, present
CM
Councillor Catherine McDonaldCommittee Member, present
VM
Councillor Victoria MillsCommittee Member, present
VW
Councillor Veronica WardCommittee Member, present
EK
Eleanor KellyOfficer, expected
DF
Doreen Forrester-BrownOfficer, expected

On this subject at Southwark

Search all
  1. Directly Funded Housing Delivery: Phase 2This decision
  2. Directly Funded Housing DeliveryNoted
  3. Directly Funded Housing DeliveryAgreed
  4. Gateway 1: Procurement Strategy Approval - Directly Funded Housing Delivery (Phase 2) - Procurement of Professional Services and Construction Works for Various SitesApproved

More from Southwark Cabinet (decommissioned, for the Executive after

All decisions
MeetingDecisionOutcome
28 May 2026 Election of Chair for the meetingThat Councillor Maisie Anderson be elected chair for this meeting. Decided Open
28 May 2026 Notification of any items of business which the chair deems urgentIt was agreed that all the deputations would be heard so that consideration of these representations could be given p... Agreed Open
28 May 2026 Disclosure of Interests and DispensationsDecision Maker (IDM) report in respect of this issue. Councillor Peter John also declared a personal, non prejudicial... Decided Open
28 May 2026 Review of Void Disposal StrategyThat the progress of disposals of void housing properties since April 2009 be noted. 2. That the importance of void d... Noted Open
28 May 2026 Housing Revenue Account - Approval of Housing Revenue Budget Account 2011/12That the savings required to deliver a balanced housing revenue account (HRA) for 2011/12 be noted. 2. That the propo... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies