Gateway 1: Procurement Strategy Approval - Directly Funded Housing Delivery (Phase 2) - Procurement of Professional Services and Construction Works for Various Sites

Approved Executive 2 papers

AI summaryCabinet approved two four year consultancy and construction frameworks for directly funded housing phases 2a and 2b, with estimated values of £4.2m and £64m. [D] Future programme and wider council use requires separate reports. [D]

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedConsultancy covers phase 2b; construction covers phases 2a and 2b [D]
Money£4.2m consultancy, £64m construction [D]Both estimated over four years [D]
What happens nextGateway 2 approvals delegated [D]Chief executive handles phase 2 framework and call off decisions [D]
Who it affectsHousing delivery, wider council work [D]Further use requires separate reports [D]

What was decided

Cabinet approved a consultancy framework for phase 2b, estimated at £4.2m, and a construction framework for phases 2a and 2b, estimated at £64m. Both run for four years.

The OJEU notice may list extra consultancy and construction options for future direct delivery phases, estimated at £290m, and wider council requirements, estimated at £30m. Any use for those additions requires a separate report.

Gateway 2 decisions for phase 2 framework establishment and later call offs are delegated to the chief executive. If sites or phase scope change, authority moves to the relevant cabinet member.

Why

Phase 2 needs lead, design, engineering, surveying, cost and construction services to move sites from design to completion. Report P28, P29, P30

External frameworks used in phase 1 were limited by supplier availability and suitability, and were not designed for Southwark's requirements. Tailor made four year frameworks would provide broader access and more assurance. Report P38, P39, P40

The proposed design led structure would put design and coordination first and could allow novation of the initial architect to the contractor. The construction framework is intended to include companies of different sizes and give local firms access to smaller schemes. Report P42, P43, P55

What happens next

The Project Board will settle framework lots, structure and evaluation methods before expressions of interest are sought. A project team will prepare tender documents and operating guidance, with the Board approving both. Report P45, P46, P52, P88

The council will advertise through OJEU and, where applicable, local publications. It will assess expressions of interest, shortlist providers, invite tenders and take Gateway 2 award decisions. Report P90, P92, P93, P97, P98, P105

Funding must be confirmed before contract awards and commitments. Tenant, resident and neighbouring stakeholder consultation will precede final design proposals, with capital programme progress reported regularly to Cabinet. Report P133, P135, P149

The money

  • £4.2m Estimated consultancy framework value for phase 2b
  • £64m Estimated construction framework value for phases 2a and 2b
  • £290m Possible future direct delivery programme scope
  • £30m Possible wider council requirements scope
  • £2.1m Estimated phase 2a consultancy fees, delivered separately Report P22, P23
  • £21.0m Estimated phase 2a construction works Report P22
  • £43.3m Estimated phase 2b construction works Report P22
  • £320m Further tranches and requirements beyond the programme Report P41

Options considered

  • Chosen: Separate new consultancy and construction frameworks. External frameworks had availability and suitability limits and were not tailored to Southwark's requirements. Report P39, P40, P140, P141
  • Chosen: Phase 2a consultancy through an existing arrangement or approved list. This route enables an early start on the projects. Report P18
  • Chosen: European Union Restricted Procedure for both frameworks. The services and works require full tendering, and four years is the maximum framework period. Report P45, P146
  • Chosen: Construction framework split into at least two lots. Separate larger and smaller packages would let smaller local companies compete for smaller schemes. Report P45, P52, P55
  • Chosen: Anticipated two list structure for each framework. The Project Board will finalise the structure and evaluation method before expressions of interest are sought. Report P46, P52
  • Chosen: One Gateway 2 for providers, then later Gateway 2 award reports. This provides for framework approval and subsequent contract awards while allowing early scheme development. Report P57
  • Chosen: Include future phases and wider council needs in the OJEU notice. Possible additions must be fully detailed to avoid procurement challenge, although their use remains subject to separate reports. Report P59
  • Chosen: Design led consultant team with possible architect novation. This would put design and coordination first and could support quality assurance during construction. Report P42

Implications

  • Financial: Most costs are expected from S106 funding, capital receipts and grants. All funding must be confirmed before contract awards and commitments. Report P133
  • Financial: Framework use will have no minimum contract levels, reducing financial exposure. Resource costs to implement it stay within current budgets. Report P150
  • Legal: The works and services must follow full European Union tendering rules and regulation 19 of the Public Contract Regulations 2006. The four year period is the maximum allowed. Report P146
  • Legal: Any use of the frameworks for future phases or wider council requirements needs a separate report. Listing possible additions in the OJEU notice helps avoid procurement challenge. Report P59
  • Equalities: More affordable, good quality homes would benefit households needing accommodation, including older people and disabled people. Decision makers must consider the Public Sector Equality Duty. Report P109, P111, P117
  • Climate: The Code for Sustainable Homes will cover design, specification and construction. Low energy design is intended to reduce environmental effects and running costs. Report P122, P124
  • Risk: The procurement risks are rated low: insufficient expertise, weak market interest, procurement delays and weak tender outcomes. The report lists training, market analysis, expert advice and clear value for money criteria as mitigations. Report P61, P62, P63, P64, P65, P66, P67, P69
  • Staffing: Existing staff within existing budgets will resource the project. Officer time comes from existing revenue budget resources. Report P132

Who and where

  • Households on Southwark's housing register Report P117
  • Older people and disabled people living in Southwark Report P109
  • Black and ethnic minority communities Report P107
  • Residents near new development sites Report P110
  • Tenants, resident associations and neighbouring stakeholders Report P135
  • Local construction companies, including smaller firms Report P43, P55
  • Consultancies and technical advisers Report P47, P48
  • Employees and subcontractors of appointed contractors Report P119

Timeline

  • 18/03/2014: Gateway 1 procurement strategy approval Report P80
  • 02/04/2014: Scrutiny call in period and notification of Gateway 1 implementation Report P80
  • 28/07/2014, 01/08/2014, 02/09/2014, 03/10/2014, 16/10/2014, 25/11/2014: Tender documentation completion, advertising, expressions of interest closing, shortlisting, tender invitation and tender closing Report P81
  • 02/02/2015, 26/02/2015: Interviews and tender evaluation completed Report P81
  • 09/03/2015, 26/03/2015, 16/04/2015: Gateway 2 reviews and Cabinet approval Report P82, P83
  • 08/05/2015, 11/05/2015: Standstill period and contract award Report P84
  • 18/05/2015: Award notice placed in OJEU Report P84
  • 11/06/2015, 10/06/2019: Contract start and contract completion Report P84

Plain English for the jargon

  • Framework arrangement: An arrangement providing access to services or works from a range of organisations [P39]
  • Call off: Selection of a provider for an individual commission under a framework [P105]
  • OJEU: Official Journal of European Union, where the frameworks will be advertised [P90]
  • Gateway 1: Approval of the procurement strategy for the frameworks [P1]
  • Gateway 2: Approval of framework providers and later awards under the frameworks [P57]
  • European Union Restricted Procedure: The proposed full tender route for both frameworks [P45]
  • RIBA Plan of Work: The framework used to break consultancy fees into work stages [P51]
  • CDM coordination: A consultancy service included in the scope [P29]
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item18

Resolved

Decisions of the Cabinet 1. That the procurement strategy contained in the report i.e. to set up a framework arrangement for consultancy services to support the delivery of phase 2b of the directly funded programme at an estimated value of £4.2m for a period of 4 years be approved. 2. That the procurement strategy contained in the report i.e. to set up a framework arrangement for construction works to support the delivery of phase 2a and phase 2b of the directly funded housing programme at an estimated value of £64m for a period of 4 years be approved. 3. That the inclusion of additional consultancy services and construction works as possible options in OJEU notice for these 2 frameworks to cover future phases of the Direct Delivery programme (with a estimated value of £290m) and wider council requirements (with an estimated value of £30m) as detailed in paragraph 26 of the report be approved but noting that any use of the frameworks for these additional services/works will be subject to separate reports. 4. That gateway 2 decisions to set up frameworks and later call offs for consultancy services and construction works relating to phase 2 due to be considered by cabinet be delegated to the chief executive. Decision of the Leader of the Council 5. That if the scope of work changes i.e. the sites within the phases are altered, that these decisions are delegated to the cabinet member for regeneration and corporate strategy or another relevant cabinet member.
Word for word from the decision Southwark published for this meeting. Source: moderngov.southwark.gov.uk

Follow this further

Built from Southwark's papers

What the report saysPro

Report to Cabinet (decommissioned, for the Executive after, 16 pages

Recommendations

Recommendations for the Cabinet

1. That cabinet approve the procurement strategy contained in this report i.e. to set up a framework arrangement for consultancy services to support the delivery of phase 2b of the directly funded programme at an estimated value of £4.2m for a period of 4 years.

2. That the cabinet approve the procurement strategy contained in this report i.e. to set up a framework arrangement for construction works to support the delivery of phase 2a and phase 2b of the directly funded housing programme at an estimated value of £64m for a period of 4 years. 3. That the cabinet approve the inclusion of additional consultancy services and construction works as possible options in OJEU notice for these 2 frameworks to cover future phases of the Direct Delivery programme (with a estimated value of £290m) and wider council requirements (with an estimated value of £30m) as detailed in paragraph 26 but noting that any use of the frameworks for these additional services/works will be subject to separate reports.

4. That the cabinet agrees that Gateway 2 decisions to set up frameworks and later call offs for consultancy services and construction works relating to phase 2 due to be considered by cabinet are delegated to the chief executive.

Recommendation for the Leader of the Council

That the Leader

5. Agrees that if the scope of work changes i.e. the sites within the phases are altered, that these decisions are delegated to the cabinet member for regeneration and corporate strategy or another relevant cabinet member.

BACKGROUND INFORMATION

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Proposed phase 2 site listAppendix 1 1 pages Download
PDF
Report: Gateway 1- Procurement Strategy Approval: Directly Funded Housing Delivery (Phase 2): Procurement of Professional Services and Construction Works for Various SitesReport 16 pages DownloadRead as text

At this meeting

Whole meeting
3Notice of Intention to conduct business in a closed meeting, and any representations receivedOn the agenda 6MinutesApproved 8Quarter 3 Capital Monitoring Report for 2013/14 and Capital Programme Refresh for 2013/14 - 2023/24Noted 9Revenue Monitoring Report for Quarter 3, 2013/14, including Treasury ManagementNoted 10Response to the Education and Children's Services Scrutiny Sub-Committee's Review of BullyingAgreed 11School Places Strategy UpdateNoted 12Permanent Enlargement of Albion, Bessemer Grange, Charles Dickens, Crawford, Grange and Keyworth Primary SchoolsNoted 13Joint Carers Strategy and Action PlanApproved 14Better Care Fund - Draft Plan for SouthwarkNoted 15Home Ownership, Voluntary Disposals and Non-statutory AcquisitionsNoted 16Shared Equity - An Additional Rehousing Assistance Route for Homeowners Affected by RegenerationApproved 16aThe Impact of Regeneration on Leaseholders (Report of Overview and Scrutiny Committee)Noted 17Phase 1b and 1c Aylesbury RegenerationAgreed
18Gateway 1: Procurement Strategy Approval - Directly Funded Housing Delivery (Phase 2) - Procurement of Professional Services and Construction Works for Various SitesThis decision
19Gateway 1: Procurement Strategy Approval - Consolidated Repairs and Maintenance Contract for the Council's Operational EstateApproved 20Walworth Town Hall - Agreeing the Way ForwardApproved 21Disposal of 23 Harper Road, London SE1Decided 22Motions Referred from Council AssemblyNoted 24Exclusion of Press and PublicDecided

Who was there

9 of 11 attended
PJ
Councillor Peter JohnChair, present
IW
Councillor Ian WingfieldDeputy Chair, present
FC
Councillor Fiona ColleyCommittee Member, present
DD
Councillor Dora Dixon-FyleCommittee Member, present
BH
Councillor Barrie HargroveCommittee Member, present
RL
Councillor Richard LivingstoneCommittee Member, present
CM
Councillor Catherine McDonaldCommittee Member, present
VM
Councillor Victoria MillsCommittee Member, present
VW
Councillor Veronica WardCommittee Member, present
EK
Eleanor KellyOfficer, expected
DF
Doreen Forrester-BrownOfficer, expected

On this subject at Southwark

Search all
  1. Gateway 1: Procurement Strategy Approval - Directly Funded Housing Delivery (Phase 2) - Procurement of Professional Services and Construction Works for Various SitesThis decision
  2. Gateway 1 – Procurement Strategy Approval -The NestApproved
  3. Gateway 1 - Procurement Strategy Approval - Southwark and Lambeth Barristers FrameworkApproved
  4. Gateway 1 - Procurement Strategy Approval - Framework contracts to provide bailiff services to the Revenues & Benefits and Parking ServicesApproved
  5. Gateway 2: Contract Award Approval - Corporate Insurance Procurement (excluding Property Insurance)Approved
  6. Gateway 1 - Initial Procurement Strategy, Parking and Traffic Enforcement Services ContractAgreed

More from Southwark Cabinet (decommissioned, for the Executive after

All decisions
MeetingDecisionOutcome
28 May 2026 Election of Chair for the meetingThat Councillor Maisie Anderson be elected chair for this meeting. Decided Open
28 May 2026 Notification of any items of business which the chair deems urgentIt was agreed that all the deputations would be heard so that consideration of these representations could be given p... Agreed Open
28 May 2026 Disclosure of Interests and DispensationsDecision Maker (IDM) report in respect of this issue. Councillor Peter John also declared a personal, non prejudicial... Decided Open
28 May 2026 Review of Void Disposal StrategyThat the progress of disposals of void housing properties since April 2009 be noted. 2. That the importance of void d... Noted Open
28 May 2026 Housing Revenue Account - Approval of Housing Revenue Budget Account 2011/12That the savings required to deliver a balanced housing revenue account (HRA) for 2011/12 be noted. 2. That the propo... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies