What was decided
Cabinet approved a consultancy framework for phase 2b, estimated at £4.2m, and a construction framework for phases 2a and 2b, estimated at £64m. Both run for four years.
The OJEU notice may list extra consultancy and construction options for future direct delivery phases, estimated at £290m, and wider council requirements, estimated at £30m. Any use for those additions requires a separate report.
Gateway 2 decisions for phase 2 framework establishment and later call offs are delegated to the chief executive. If sites or phase scope change, authority moves to the relevant cabinet member.
Why
Phase 2 needs lead, design, engineering, surveying, cost and construction services to move sites from design to completion. Report P28, P29, P30
External frameworks used in phase 1 were limited by supplier availability and suitability, and were not designed for Southwark's requirements. Tailor made four year frameworks would provide broader access and more assurance. Report P38, P39, P40
The proposed design led structure would put design and coordination first and could allow novation of the initial architect to the contractor. The construction framework is intended to include companies of different sizes and give local firms access to smaller schemes. Report P42, P43, P55
What happens next
The Project Board will settle framework lots, structure and evaluation methods before expressions of interest are sought. A project team will prepare tender documents and operating guidance, with the Board approving both. Report P45, P46, P52, P88
The council will advertise through OJEU and, where applicable, local publications. It will assess expressions of interest, shortlist providers, invite tenders and take Gateway 2 award decisions. Report P90, P92, P93, P97, P98, P105
Funding must be confirmed before contract awards and commitments. Tenant, resident and neighbouring stakeholder consultation will precede final design proposals, with capital programme progress reported regularly to Cabinet. Report P133, P135, P149
The money
- £4.2m Estimated consultancy framework value for phase 2b
- £64m Estimated construction framework value for phases 2a and 2b
- £290m Possible future direct delivery programme scope
- £30m Possible wider council requirements scope
- £2.1m Estimated phase 2a consultancy fees, delivered separately Report P22, P23
- £21.0m Estimated phase 2a construction works Report P22
- £43.3m Estimated phase 2b construction works Report P22
- £320m Further tranches and requirements beyond the programme Report P41
Options considered
- Chosen: Separate new consultancy and construction frameworks. External frameworks had availability and suitability limits and were not tailored to Southwark's requirements. Report P39, P40, P140, P141
- Chosen: Phase 2a consultancy through an existing arrangement or approved list. This route enables an early start on the projects. Report P18
- Chosen: European Union Restricted Procedure for both frameworks. The services and works require full tendering, and four years is the maximum framework period. Report P45, P146
- Chosen: Construction framework split into at least two lots. Separate larger and smaller packages would let smaller local companies compete for smaller schemes. Report P45, P52, P55
- Chosen: Anticipated two list structure for each framework. The Project Board will finalise the structure and evaluation method before expressions of interest are sought. Report P46, P52
- Chosen: One Gateway 2 for providers, then later Gateway 2 award reports. This provides for framework approval and subsequent contract awards while allowing early scheme development. Report P57
- Chosen: Include future phases and wider council needs in the OJEU notice. Possible additions must be fully detailed to avoid procurement challenge, although their use remains subject to separate reports. Report P59
- Chosen: Design led consultant team with possible architect novation. This would put design and coordination first and could support quality assurance during construction. Report P42
Implications
- Financial: Most costs are expected from S106 funding, capital receipts and grants. All funding must be confirmed before contract awards and commitments. Report P133
- Financial: Framework use will have no minimum contract levels, reducing financial exposure. Resource costs to implement it stay within current budgets. Report P150
- Legal: The works and services must follow full European Union tendering rules and regulation 19 of the Public Contract Regulations 2006. The four year period is the maximum allowed. Report P146
- Legal: Any use of the frameworks for future phases or wider council requirements needs a separate report. Listing possible additions in the OJEU notice helps avoid procurement challenge. Report P59
- Equalities: More affordable, good quality homes would benefit households needing accommodation, including older people and disabled people. Decision makers must consider the Public Sector Equality Duty. Report P109, P111, P117
- Climate: The Code for Sustainable Homes will cover design, specification and construction. Low energy design is intended to reduce environmental effects and running costs. Report P122, P124
- Risk: The procurement risks are rated low: insufficient expertise, weak market interest, procurement delays and weak tender outcomes. The report lists training, market analysis, expert advice and clear value for money criteria as mitigations. Report P61, P62, P63, P64, P65, P66, P67, P69
- Staffing: Existing staff within existing budgets will resource the project. Officer time comes from existing revenue budget resources. Report P132
Who and where
- Households on Southwark's housing register Report P117
- Older people and disabled people living in Southwark Report P109
- Black and ethnic minority communities Report P107
- Residents near new development sites Report P110
- Tenants, resident associations and neighbouring stakeholders Report P135
- Local construction companies, including smaller firms Report P43, P55
- Consultancies and technical advisers Report P47, P48
- Employees and subcontractors of appointed contractors Report P119
Timeline
- 18/03/2014: Gateway 1 procurement strategy approval Report P80
- 02/04/2014: Scrutiny call in period and notification of Gateway 1 implementation Report P80
- 28/07/2014, 01/08/2014, 02/09/2014, 03/10/2014, 16/10/2014, 25/11/2014: Tender documentation completion, advertising, expressions of interest closing, shortlisting, tender invitation and tender closing Report P81
- 02/02/2015, 26/02/2015: Interviews and tender evaluation completed Report P81
- 09/03/2015, 26/03/2015, 16/04/2015: Gateway 2 reviews and Cabinet approval Report P82, P83
- 08/05/2015, 11/05/2015: Standstill period and contract award Report P84
- 18/05/2015: Award notice placed in OJEU Report P84
- 11/06/2015, 10/06/2019: Contract start and contract completion Report P84
Plain English for the jargon
- Framework arrangement: An arrangement providing access to services or works from a range of organisations [P39]
- Call off: Selection of a provider for an individual commission under a framework [P105]
- OJEU: Official Journal of European Union, where the frameworks will be advertised [P90]
- Gateway 1: Approval of the procurement strategy for the frameworks [P1]
- Gateway 2: Approval of framework providers and later awards under the frameworks [P57]
- European Union Restricted Procedure: The proposed full tender route for both frameworks [P45]
- RIBA Plan of Work: The framework used to break consultancy fees into work stages [P51]
- CDM coordination: A consultancy service included in the scope [P29]