Revenue Monitoring Report Quarter 2, 2013/14, including Treasury Management

Noted Executive 2 papers

AI summaryCabinet noted Southwark’s 2013/14 revenue forecasts, council tax and business rates collection performance, and treasury management for the first six months. [D] It approved general fund movements above £250,000. [D][P5]

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedGeneral fund, housing, collections and treasury were covered. [P2][P3][P4]
MoneyMovements above £250,000 [D]General fund movements in Appendix A require approval. [P5][P112]
What happens nextQuarter three council tax forecast [P89]Nine months’ experience should provide a better estimate. [P89]
Who it affectsCouncil services and collections [D]The report covers spending, housing, tax and rates. [P2][P3][P4]

What was decided

Cabinet noted the 2013/14 general fund and housing revenue account forecasts, forecast reserve movements, and treasury management for the first six months. [D][P2] Report P2

Cabinet noted forecast council tax collection performance. [D][P3] Report P3

Cabinet noted business rates collection performance and Business Rate Retention Scheme risks, and approved general fund budget movements exceeding £250,000. [D][P4][P5] Report P4, P5

Why

The report used experience to the end of quarter two to forecast the end of financial year 2013/14, while work continued to achieve a balanced position. [P7] Report P7

Within services, the forecast showed a favourable variance of £208k, based on limited information. [P17] Report P17

Agreed savings were still forecast to be achieved, despite a £1.1m shortfall offset by compensating savings. [P71][P73][P74] Report P71, P73, P74

What happens next

Strategic directors will continue management action and budget monitoring to keep services within budget. [P14][P30][P41] Report P14, P30, P41

Any unused contingency will be the first call to support the assumed £6.2m reserve contribution in the 2014/15 budget. [P56] Report P56

The council tax forecast will be updated at quarter three using nine months’ experience. [P89] Report P89

The money

  • £250,000 Threshold above which general fund budget movements require approval. [D][P5] Report P5
  • £6.3m Planned use of reserves in the 2013/14 budget. [P7] Report P7
  • £1.1m Projected savings shortfall at quarter two. [P71] Report P71
  • £515k Estimated business rates account deficit at quarter two. [P95] Report P95
  • £154k Council’s 30% share of the estimated business rates deficit. [P95] Report P95
  • £2.5m Early forecast surplus on the council tax account. [P89] Report P89
  • £1.9m Council’s share of the forecast council tax surplus. [P89] Report P89
  • £231m Cash invested at 30 September 2013. [P99] Report P99

Options considered

  • Chosen: Note the general fund, housing revenue account, reserve and treasury management forecasts. The report was intended to forecast the end of financial year 2013/14 and support a balanced position. [P7] Report P7
  • Chosen: Note forecast council tax collection performance. The council tax account was expected to meet its collection fund target. [P88] Report P88
  • Chosen: Note business rates collection performance and retention risks. The new funding regime presents significant risk and some opportunity. [P83] Report P83
  • Chosen: Approve general fund budget movements exceeding £250,000. Cabinet approval is required for reserve support where the amount is £250k or above. [P78] Report P78

Implications

  • Financial: The general fund total forecast is 322,564 against a revised budget of 327,772, both in the table’s £'000 columns. [P15] Report P15
  • Financial: The housing revenue account forecast is neutral. Reserves are below the optimum level, and deficits or surpluses must be carried forward. [P60][P62][P68] Report P60, P62, P68
  • Financial: Agreed savings are still forecast to be achieved. A £1.1m shortfall in children and adults’ services is offset by compensating savings. [P71][P73][P74] Report P71, P73, P74
  • Risk: Temporary accommodation is the greatest financial risk. Estate voids during Aylesbury Estate regeneration could increase bed and breakfast use. [P35][P36] Report P35, P36
  • Risk: Business rate retention carries significant risk. Shortfalls from 0.1% to 7.5% are not protected and would fall to the council. [P83][P84] Report P83, P84
  • Financial: Council tax is expected to meet its collection target despite an additional £2.8m requirement from the 10% reduction in central government support. [P88] Report P88
  • Staffing: The forecast includes estimates of one off reorganisation and redundancy costs as savings plans continue. [P16] Report P16
  • Risk: Capital preservation and liquidity remain investment priorities. Investments averaged £242m in the first half and stood at £231m at 30 September 2013. [P99] Report P99

Who and where

  • Children in residential care and families with no recourse to public funds Report P21, P23, P30
  • Adults using social care and mental health services Report P23
  • People needing temporary accommodation Report P35, P64
  • Mainstream housing tenants Report P63
  • Council tax payers Report P88
  • Businesses liable for business rates Report P82, P91, P92
  • Council staff affected by service reviews Report P16, P22, P45
  • Southwark residents receiving public health services Report P48, P50, P51, P52

Timeline

  • 29 January 2013: Cabinet set tenants’ rents and service charges. [P11] Report P11
  • 27 February 2013: The council agreed the balanced general fund budget. [P7] Report P7
  • 1 April 2013: New public health responsibilities began. [P48] Report P48
  • 1 June 2013: The GDIT contract ceased and customer service delivery was brought in house. [P33] Report P33
  • 30 September 2013: The quarter two forecast and investment position were reported. [P14][P60][P99] Report P14, P60, P99
  • quarter three: The council tax outturn forecast will be reassessed using nine months’ experience. [P89] Report P89
  • 31 March 2014: Collection fund balances were forecast. [P85][P86] Report P85, P86
  • end of the financial year 2013/14: The council continued working towards a balanced position. [P7] Report P7

Plain English for the jargon

  • General fund: The council revenue budget covering services and related reserve movements. [P2][P14]
  • Housing revenue account (HRA): The account covering housing services, rent, service charges and housing reserves. [P2][P11][P60][P63]
  • Business Rate Retention Scheme: The funding regime under which the council retains 30% of amounts collected. [P82][P91]
  • NNDR: The business rates account. [P86][P90]
  • Dedicated Schools Grant (DSG): The schools grant, including one off funding for eligible two year old places. [P26]
  • Discretionary Housing Payments: Support for council tenants to sustain tenancies and adapt to welfare reform. [P63]
  • Social sector size criteria: Welfare reform rules restricting the size of accommodation covered by housing benefit. [P35][P63]
  • Financial Risk Reserve: Part of the reserves set aside to protect against business rate retention risk. [P94]
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item11

Resolved

That the following be noted: · the general fund outturn forecast for 2013/14 and forecast net movement in reserves by department · the housing revenue account’s (HRA) forecast outturn for 2013/14 and resulting forecast movement in reserves · the treasury management activity for the first six months of 2013/14. 2. That the forecast performance for the collection of council tax be noted. 3. That the forecast performance for the collection of business rates and the risks associated with the business rate retention scheme be noted. 4. That the general fund budget movements that exceed £250,000, as shown in Appendix A of the report be approved.
Word for word from the decision Southwark published for this meeting. Source: moderngov.southwark.gov.uk

Follow this further

Built from Southwark's papers

What the report saysPro

Report to Cabinet (decommissioned, for the Executive after, 15 pages

Recommendations

1. That the cabinet notes:

• the general fund outturn forecast for 2013/14 and forecast net movement in reserves by department; • the housing revenue account’s (HRA) forecast outturn for 2013/14 and resulting forecast movement in reserves; • the treasury management activity for the first six months of 2013/14.

2. That the cabinet notes the forecast performance for the collection of council tax.

3. That the cabinet notes the forecast performance for the collection of business rates and the risks associated with the Business Rate Retention Scheme.

4. The cabinet approves the general fund budget movements that exceed £250,000, as shown in Appendix A.

BACKGROUND INFORMATION

5. The purpose of this report is to provide a forecast for the end of the financial year 2013/14, using predictions based on the experience to date and knowledge as at the end of quarter two (September 2013). Work continues throughout the council to ensure that a balanced position is achieved by the end of the year. 6. The council agreed a balanced general fund budget of £327.8m on 27 February 2013 based on a nil council tax increase, and £6.3m use of reserves, giving a budget of £334.1m. This budget was set in the context of further significant overall cuts in government funding and the identification of some 25% savings proposals over the three years from 2011/12 to 2013/14 to mitigate against the reduction in resources and to continue to fund the council’s commitments in terms of services provided.

7. The council also approved budget decisions including reductions of some £25m within general fund for 2013/14. Performance on achieving these savings is closely monitored and details are provided in paragraphs 50 to 52 below.

8. The Council Plan placed local needs and accountability as the drivers of performance improvement, and in an environment of significantly reduced funding, the council has to change in fundamental ways. There are a number of transformation projects underway, and work continues to identify further ways of transforming the delivery of services. These transformation or invest to save projects may be funded from on-going positive variances or previously created earmarked reserves which were established to pump prime initiatives.

Housing revenue account

9. Cabinet set tenants’ rents and service charges on 29 January 2013 in line with the government's prescribed formula. The budget included a £6m savings target for 2013/14. The starting point of this process was to listen to residents’ concerns about the services they wish to protect, and identify the potential for better value for money and more efficient ways of working.

KEY ISSUES FOR CONSIDERATION

Current forecast position: General fund

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Budget movements to be approved £250,000 and above and movements to be notedAppendix A 4 pages Download
PDF
Report: Revenue Monitoring Report Quarter 2, 2013/14, including Treasury ManagementReport 15 pages DownloadRead as text

At this meeting

Whole meeting

Who was there

7 of 11 attended
PJ
Councillor Peter JohnChair, apologies
IW
Councillor Ian WingfieldDeputy Chair, present
FC
Councillor Fiona ColleyCommittee Member, present
DD
Councillor Dora Dixon-FyleCommittee Member, present
BH
Councillor Barrie HargroveCommittee Member, apologies
RL
Councillor Richard LivingstoneCommittee Member, present
CM
Councillor Catherine McDonaldCommittee Member, present
VM
Councillor Victoria MillsCommittee Member, present
VW
Councillor Veronica WardCommittee Member, present
EK
Eleanor KellyOfficer, expected
DF
Doreen Forrester-BrownOfficer, expected

On this subject at Southwark

Search all
  1. Revenue Monitoring Report Quarter 2, 2013/14, including Treasury ManagementThis decision
  2. Policy and Resources: Revenue Monitoring report Month 4, 2026-27Noted
  3. Policy and Resources : Out-turn revenue monitoring report 2025-26Noted
  4. Quarter 1 Revenue Monitoring Report 2010/11Noted
  5. Quarter 2 Revenue Monitoring Report - 2010/11Noted
  6. Quarter 3 Revenue Monitoring Report - 2010/11Noted

More from Southwark Cabinet (decommissioned, for the Executive after

All decisions
MeetingDecisionOutcome
28 May 2026 Election of Chair for the meetingThat Councillor Maisie Anderson be elected chair for this meeting. Decided Open
28 May 2026 Notification of any items of business which the chair deems urgentIt was agreed that all the deputations would be heard so that consideration of these representations could be given p... Agreed Open
28 May 2026 Disclosure of Interests and DispensationsDecision Maker (IDM) report in respect of this issue. Councillor Peter John also declared a personal, non prejudicial... Decided Open
28 May 2026 Review of Void Disposal StrategyThat the progress of disposals of void housing properties since April 2009 be noted. 2. That the importance of void d... Noted Open
28 May 2026 Housing Revenue Account - Approval of Housing Revenue Budget Account 2011/12That the savings required to deliver a balanced housing revenue account (HRA) for 2011/12 be noted. 2. That the propo... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies