Quarterly Capital Monitoring Report Quarter 2 and Capital Progamme Refresh 2013-21
NotedExecutive5 papers
AI summarySouthwark Cabinet noted the general fund and housing investment programmes, approved budget changes including £76.7m for Aylesbury land assembly in phases 1 and 2, and rescheduled spending. Further changes will be needed as updated information emerges.
Written from the decision and the officer reportPDF Pro
OutcomeNotedProgrammes noted, budget changes approved and spending rescheduled.
MoneyAylesbury land assembly £76.7mPhases 1 and 2 budget for 2013/14 to 2019/20
What happens nextFurther reprofiling and resource decisionsUpdated project and funding information is required
Who it affectsCapital projects across the boroughGeneral fund and housing investment spending changes
What was decided
Cabinet noted the general fund capital programme for 2013/14 to 2021/22 at Quarter 2, together with the housing investment programme for 2013/14 and future years. Report P2, P3
It approved budget virements and variations, including £76.7m for land assembly in phases 1 and 2 of the Aylesbury regeneration programme. Report P4, P144
It approved changes to the timing of expenditure and resources for both programmes for 2013/14 and future years. Further changes are expected during the year as newer procurement and contract information becomes available. Report P5, P149
Why
The programme is large and complex, so delays cause planned spending to differ from forecasts. Regular monitoring, departmental reviews and a broad resource base help absorb these changes. Report P9, P10, P21, P149
Warm, Dry and Safe costs are expected to remain above stock condition survey estimates, and the contingency is expected to be inadequate. An earlier report allowed £29m of backlog funding. June 2013 approval added £48.8m, which is included in the adjustments, and a further report will seek any extra resources. Report P123
The Aylesbury proposal uses a development partnership over 20 years. The council would fund land assembly and grant long leases, while the partner funds and builds the development. Later land receipts were expected to offset early land assembly costs. Report P142, P147
What happens next
Cabinet will receive the final outturn position after the programme is monitored through the rest of the financial year. Report P46
Further budget reprofiling will be required as procurement and contract information changes. A separate report will seek any additional Warm, Dry and Safe resources. Report P5, P123, P149
Cabinet was expected to receive a preferred bidder recommendation for Aylesbury in January 2014. A Development Partnership Agreement was planned for April 2014, subject to approval. Aylesbury costs for phases 3 and 4 were due for the early 2014 capital refresh and Quarter 3 report. Report P141, P145, P146
The money
£76.7m Land assembly budget for Aylesbury regeneration phases 1 and 2 for 2013/14 to 2019/20 Report P144
£48.8m Additional backlog funding approved in June 2013 and included in the budget adjustments Report P123
£29m Backlog funding allowed by the 18 October cabinet report Report P123
£80m Warm, Dry and Safe spend target for 2013/14 Report P16, P118
£337.2m General fund expenditure budget for 2013/14 to 2021/22 Report P42
£531.8m Housing investment expenditure budget for 2013/14 and future years Report P43
£95.3m Re-profiled general fund budget for 2013/14 at Quarter 2 Report P14
£131.2m Re-profiled housing investment budget for 2013/14 at Quarter 2 Report P16
Options considered
Chosen: Note the general fund capital programme for 2013/14 to 2021/22 Report P2
Chosen: Note the housing investment programme for 2013/14 and future years Report P3
Chosen: Approve virements and variations, including the Aylesbury budget. The cost analysis estimated £76.7m for land assembly in Aylesbury phases 1 and 2. Report P4, P144
Chosen: Approve reprofiling of expenditure and resources. The budgets reflect the latest information at Quarter 2 and may need further changes. Report P5, P149
Implications
Financial: The forecast says predicted resources are sufficient to meet anticipated spend over 2013/14 to 2021/22. Report P158
Financial: Budget reprofiling changes the timing of expenditure and resources, with further changes likely during 2013/14. Report P5, P149
Risk: Warm, Dry and Safe costs are expected to exceed stock condition survey estimates, leaving contingency inadequate. Report P123
Risk: Additional resources were identified as necessary for substantial fire risks in high rise blocks. Report P126
Legal: Legal implications are in a concurrent report from the Director of Legal Services. The council must maintain a balanced budget and act on deterioration found through monitoring. Report P157, P162
Equalities: Each capital project will be considered against age, disability, faith or religion, gender, race or ethnicity, and sexual orientation. Report P152
Staffing: Additional or specialist staffing resources will be subject to separate reports. Report P156
Other: There was no overall programme consultation, but individual projects remain subject to needed consultation and possible grant or Section 106 conditions. Report P159
As at Quarter 2 2013/14: General fund spend was £23m against a £95.3m budget. Housing investment spend was forecast at £128.2m against £131.2m. Report P14, P16
during 2013/14: Service managers will review expected spend, and further budget reprofiling may be required. Report P149
June 2013: Cabinet approved £48.8m of additional Warm, Dry and Safe backlog funding. Report P123
18 October: A Cabinet report allowed £29m of backlog funding towards the housing investment programme. Report P123
January 2014: Cabinet was expected to receive a preferred bidder recommendation for Aylesbury. Report P141
early 2014: Aylesbury phase 3 and 4 costs were due in the Quarter 3 capital monitor and capital refresh. Report P145, P146
31 March 2014: The CCTV project, the Warm, Dry and Safe two year programme and most parks and public realm schemes were expected to complete. Report P81, P91, P119
April 2014: A Development Partnership Agreement was planned for Aylesbury, subject to approval. Report P141
Plain English for the jargon
General fund capital programme: Council capital spending reported by department, with project detail in Appendices A and D.
Housing Investment Programme: Capital works to Housing Revenue Account properties.
Budget virement: A budget allocation change reported for Cabinet approval.
Budget reprofiling: Changing the planned timing of expenditure and resources.
Warm, Dry and Safe: Council housing works measured against the WDS standard.
Section 106: A planning obligation providing developer contributions for schemes.
Community Infrastructure Levy: A proposed council levy that may support appropriate schemes.
Decent Homes Backlog: Backlog funding used to bring Warm, Dry and Safe works forward.
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item12
Resolved
That the general fund capital programme for the period 2013/14 to 2021/22 as at Quarter 2 2013/14, as detailed in appendices A and D of the report be noted. 2. That the housing investment programme for 2013/14 and future years as at Quarter 2 2013/14, as detailed in Appendix B of the report be noted. 3. That the virements and variations to the general fund and housing investment capital programme as detailed in Appendix C of the report, including the updated budget requirement for Phases 1 and 2 of the Aylesbury regeneration programme, as reflected in paragraphs 100-106 of the report be approved. 4. That the re-profiling of the expenditure and resources for 2013/14 and future years for both the general fund and housing investment programmes as detailed in Appendices A, B and D of the report as at Quarter 2 2013/14 be approved and it be noted that further re-profiling will be required during the year based on more up to date information available at that time.
Word for word from the decision Southwark published for this meeting.Source: moderngov.southwark.gov.uk
Report to Cabinet (decommissioned, for the Executive after, 17 pages
Recommendations
That cabinet:
1. Notes the general fund capital programme for the period 2013/14 to 2021/22 as at Quarter 2 2013/14, as detailed in appendices A and D.
2. Notes the housing investment programme for 2013/14 and future years as at Quarter 2 2013/14, as detailed in Appendix B
3. Approves the virements and variations to the general fund and housing investment capital programme as detailed in Appendix C, including the updated budget requirement for Phases 1 and 2 of the Aylesbury regeneration programme, as reflected in paragraphs 100-106.
4. Approves the re-profiling of the expenditure and resources for 2013/14 and future years for both the general fund and housing investment programmes as detailed in Appendices A, B and D as at Quarter 2 2013/14 and note that further re-profiling will be required during the year based on more up to date information available at that time.
BACKGROUND INFORMATION
5. With a total forecast spend of approximately £794m the current capital programme represents a major element of the council’s financial activities. It has a significant and very visible impact on the borough and hence on the lives of those who live, learn, visit and or do business in the borough. 1 6. The Quarter 1 2013/14 capital monitor report indicated that expenditure of £9.9m had been incurred on the general fund capital programme against a budget of £96.3m. This represented a spend of just over 10% to budget as at Quarter 1 and a small favourable variance of £2m was projected against the budget for the year at that point.
7. The Quarter 1 2013/14 capital monitor report also reflected a spend of £10.2m on the Housing Investment Capital programme against a budget of £120.5m which represented a spend 8.5% against the budget for the year.
8. Due to the size and scale of the capital programme and the number of projects involved, it is inevitable that unforeseeable delays can occur which lead to some variations against planned spend. Historically the capital programme has been over programmed in year to compensate for these variations, whilst retaining a balanced programme overall.
9. Robust and continued monitoring of numerous schemes across the departmental capital programme and the complexities of managing the capital programmes of this magnitude will inevitably lead to some variations in the budgeted expenditure which requires re-profiling of the budgets.
10. This report sets out the re-profiled budget and forecast outturn position for 2013/14 and future years for the General Fund and the Housing Investment Programme (HIP) as at Quarter 2 2013/14.
KEY ISSUES FOR CONSIDERATION
General Fund Capital Spend
11. The Quarter 2 capital monitor report indicates that expenditure of £23m incurred against a re-profiled budget of £95.3m showing a spend of 24% to budget on the general fund capital programme. The summary position and the programme details by departments are reflected in Appendices A and D respectively.
Housing Investment Programme Spend
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Cabinet (decommissioned, for the Executive after at Southwark and we tell you when its next papers are published, before the meeting rather than after it.
Review of Void Disposal StrategyThat the progress of disposals of void housing properties since April 2009 be noted. 2. That the importance of void d...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.