London Borough of Southwark
Executive, Monday 20 July 2026 at 3.00pm

Policy and Resources : Out-turn revenue monitoring report 2025-26

Noted Executive 5 papers

AI summarySouthwark Executive notes £25.3m General Fund overspend for 2025-26, approves use of reserves to balance budget, and records closure of the DSG Safety Valve programme.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedRevenue outturn noted; reserve use approved
Money£25.3m General Fund overspendFunded from reserves
What happens nextSeptember Executive monitoringUpdated £10m savings position due
Who it affectsCouncil reserves and servicesGeneral Fund, HRA, DSG

What was decided

The Executive noted a General Fund overall adverse variance of £25.3m, an HRA adverse variance of £1.4m, and a DSG adverse variance of £1.7m for 2025-26.

The Executive noted closure of the Dedicated Schools Grant Safety Valve programme and the new High Needs Stability Grant arrangements. Report P106

The Executive approved the use of £25.3m of reserves to balance the 2025-26 outturn, alongside interdepartmental budget and reserve movements above £275k. Report P1

Why

Temporary accommodation was again the single largest area of overspend, reflecting national cost and demand pressures that London councils identify as their biggest financial risk. Report P16, P60, P61

The Future Southwark Transformation Programme delivered only £80k of a planned £3m of cross-council savings in 2025-26, contributing a £2.9m adverse variance. Report P24, P85

Adult Social Care and Children's Services faced rising demand and cost pressures, including residential care placements and home-to-school transport for EHCPs. Report P26, P31, P36, P39

What happens next

Regular budget monitoring reports will track delivery of departmental and transformation savings through 2026-27, with the September Executive report to include an updated position on the £10m cumulative savings target. Report P12, P25

The council must submit a local SEND reform plan and secure DfE approval to receive the new High Needs Stability Grant, expected in autumn 2026. Report P106

Mitigating actions continue, including demand management in adult social care, expansion of in-house children's placements, and renegotiation of temporary accommodation provider rates. Report P32, P37, P64

The money

  • £25.3m General Fund overall adverse variance at outturn 2025-26 Report P11
  • £37.8m Departmental adverse variances before use of reserves
  • £17.3m Departmental use of planned reserves to mitigate overspends
  • £4m Contingency fully utilised
  • £2.5m General reserves used in addition to contingency
  • £11.6m Planned collection fund reserves used at year end Report P15
  • £1.4m Housing Revenue Account net adverse variance at outturn Report P87, P92
  • £1.7m Dedicated Schools Grant adverse variance at outturn Report P104
  • £2.77m Additional DfE Safety Valve contribution received for 2025-26 Report P105
  • £8.3m Adverse variance on HRA temporary accommodation rental income under the 2020 Rent Standard Report P88, P94
  • £3.7m Provision for estimated refunds to current HRA tenants covering April 2020 to March 2025 Report P88
  • £32.7m Contingent liability for former tenants and Housing Benefit subsidy, including potential DWP payments Report P88
  • £13.4m Housing General Fund final outturn overspend after use of £2.4m of reserves Report P60
  • £1.5m Housing Benefit subsidy loss on out-of-borough temporary accommodation placements Report P62
  • £11.4m Homelessness Prevention Grant fully utilised in-year for housing needs staffing and prevention Report P63
  • £34.5m Revenue contribution to HRA capital expenditure in 2025-26 Report P90, P101
  • £4.2m Parking Services surplus transferred to the Highways Transformation Reserve Report P49
  • £2.9m Future Southwark Transformation Programme adverse variance from missed savings Report P24, P85
  • £2m Expected recurring annual savings from the Vision360 in-house IT service from 2029-30 Report P74
  • £863k Current total value of voluntary and community sector grants to 28 organisations Report P83

Options considered

  • Chosen: Use £25.3m of reserves to balance the 2025-26 outturn. Required to contain costs within the current funding envelope and balance the General Fund Report P122

Implications

  • Financial: Material reserve drawdown of £25.3m raises concerns about financial sustainability, particularly given reduced funding from the Fair Funding Review. Report P12
  • Financial: The HRA faces a £32.7m contingent liability and relies on continued asset disposals to fund the capital programme. Report P88, P90
  • Legal: Decisions fall under the Executive's responsibility for revenue and capital budgets and financial standing orders; the chief finance officer must report under Section 114 if expenditure becomes unlawful. Report P123, P125
  • Legal: Section 76 of the Local Government and Housing Act 1989 requires the council to prevent debit balances on the Housing Revenue Account. Report P124
  • Equalities: The public sector equality duty under section 149 of the Equality Act 2010 must continue to be considered in any processes to mitigate budget pressures. Report P126, P129
  • Risk: Transformation savings delivery in 2025-26 was substantially below plan, increasing the financial challenge for 2026-27 as delayed savings now need to be delivered alongside the next year's target. Report P24, P25
  • Risk: Falling school rolls across inner London present an ongoing risk to school viability and DSG sustainability. Report P107
  • Climate: The report itself has no direct climate change implications, though the Parking Services surplus is being used to support the Streets for People and transport strategies. Report P49, P114

Who and where

  • Council tenants, particularly those in temporary accommodation and void properties Report P88, P94
  • Adult Social Care service users facing rising demand and complex needs Report P31
  • Children with education, health and care plans and their families Report P36, P39
  • Residents with No Recourse to Public Funds Report P17, P45, P55
  • Schools and governing bodies affected by falling rolls and SEND pressures Report P107
  • Voluntary and community sector organisations funded by the council Report P83
  • Leisure centre users following unplanned facilities maintenance Report P51

Timeline

  • January 2025: HRA budget for 2025-26 agreed Report P113
  • 25 February 2025: Council agreed a balanced General Fund budget for 2025-26 including £19m of efficiencies, savings and additional income Report P6
  • July 2025: MTFS Executive report RAG rated departmental savings for 2025-26 and 2026-27 Report P22
  • February 2026: Local Government Finance Settlement confirmed closure of the Safety Valve Programme and the new High Needs Stability Grant Report P106
  • Autumn 2026: High Needs Stability Grant expected to be paid, subject to DfE approval of Southwark's SEND reform plan Report P106
  • 31 March 2026: End of 2025-26 financial year; reserve balances shown in Appendix D Report P132
  • 1 April 2026: National requirement for borough-wide food waste recycling came into force Report P50
  • September 2026 (Executive): Updated position on the £10m cumulative transformation savings target to be reported Report P25
  • 2026-27: Cumulative £10m transformation savings target now expected to be achieved Report P25
  • 2029-30: Recurring annual savings of £2m expected from the Vision360 in-house IT service Report P74

Plain English for the jargon

  • HRA: Housing Revenue Account: the ring-fenced statutory account through which the council manages its housing stock
  • DSG: Dedicated Schools Grant: ring-fenced government funding for schools
  • Safety Valve Programme: Department for Education agreement providing additional funding to authorities with DSG deficits, now closed and replaced by the High Needs Stability Grant
  • MRP: Minimum Revenue Provision: the minimum amount a council must set aside from revenue each year to repay debt
  • CIL: Community Infrastructure Levy: a charge on new development used to fund infrastructure
  • Section 106: Planning obligations under section 106 of the Town and Country Planning Act 1990 used to secure developer contributions
  • NRPF: No Recourse to Public Funds: a status affecting some residents' eligibility for council-funded support
  • EHCP: Education, Health and Care Plan: a plan for children and young people with special educational needs and disabilities
  • MTFS: Medium Term Financial Strategy: the council's multi-year financial planning document
  • Vision360: Programme to exit the Shared Technology Service with Brent and Lewisham and stand up a new in-house IT service for Southwark
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item11

Resolved

That the following be noted: a) The housing revenue account (HRA) adverse variance of £1.4m b) The general fund overall adverse variance of £25.3m which includes: · Departmental adverse variances of £37.8m · Departmental use of planned reserves of £17.3m · The full utilisation of the £4m contingency together with £2.5m of general reserves. · The use of £11.6m of planned collection fund reserves · Achievement of departmental savings (Appendix C of the report) c) The interdepartmental general fund budget and reserve movements that are less than £275k as shown in Appendix A and Appendix B of the report. d) The £1.7m adverse variance of the ring-fenced dedicated schools grant (DSG) and the closure of the safety valve programme (paragraphs 89-92 of the report). e) The council reserve balances as at 31 March 2026 in Appendix D of the report. 2. That the use of £25.3m of reserves to balance the 2025-26 outturn together with the interdepartmental budget and reserve movements that exceed £275k, as shown in Appendix A and Appendix B of the report be approved.
Word for word from the decision Southwark published for this meeting. Source: moderngov.southwark.gov.uk

Follow this further

Built from Southwark's papers

What the report saysPro

Report to Executive, 23 pages

Reasons for recommendations

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Budget VirementsAppendix A 3 pages Download
PDF
Reserve movementsAppendix B 3 pages Download
PDF
Departmental SavingsAppendix C 6 pages Download
PDF
Reserves at 31 March 2026Appendix D 1 pages Download
PDF
Report: Policy and Resources: Out-turn revenue monitoring Report 2025-26Report 23 pages DownloadRead as text

At this meeting

Whole meeting

On this subject at Southwark

Search all
  1. Policy and Resources : Out-turn revenue monitoring report 2025-26This decision
  2. Policy and Resources: Revenue Monitoring report Month 4, 2026-27Noted
  3. Policy and Resources: Capital Monitoring report Month 4, 2026-27Noted
  4. Policy and Resources: Out-turn capital monitoring report 2025-26Noted
  5. Policy and Resources: Financial Remit reportNoted
  6. Policy and resources strategy 2011/12 - 2013/14 - draft revenue budgetNoted

More from Southwark Executive

All decisions
MeetingDecisionOutcome
13 Oct 2026 MinutesThat the minutes of the meeting held on 15 September 2026 be approved as a correct record and signed by the chair. Approved Open
13 Oct 2026 Deputation requestsRESOLVED - That the written statement from Andrew Eke be heard. Deputation to Southwark Council Executive – Tustin Es... Decided Open
13 Oct 2026 Beormund School Expansion and RelocationThat the proposals to relocate and expand the Beormund Special Primary School be agreed. Agreed Open
13 Oct 2026 Gateway 1 - Highway works contractThat the procurement strategy outlined in the report for the provision of Highways Works be approved, comprising: · L... Approved Open
13 Oct 2026 Climate Change Strategy & Action Plan Update and Annual ReportThat the contribution of communities, schools, businesses and council services in tackling the climate crisis over th... Noted Open