AI summarySouthwark Cabinet endorsed priorities for British Land negotiations on Canada Water, authorised talks and a land acquisition investigation, and required a progress report in Spring 2015 [D]. No direct resource implications are identified [P51].
Written from the decision and the officer reportPDF Pro
OutcomeAgreedPriorities, detailed terms and acquisition investigation approved [D].
MoneyNo direct resource implicationsDetailed assessment follows negotiations [P51].
What happens nextNegotiate, investigate acquisition, reportProgress report due in Spring 2015 [D].
Who it affectsCanada Water town centreHarmsworth Quay and shopping centre sites [D].
What was decided
Cabinet endorsed the core priorities for negotiations with British Land concerning a legal redevelopment agreement [D][P1][P39]. The housing target is 35% of general needs housing, split 70/30 between rent and shared ownership, with the rented element retained as council housing [P30]. Other priorities cover freeholds, long term income, a council owned leisure centre site, education and possible school space, jobs and business starts, transport and cycling links, and local training and employment [P28][P29][P31][P32][P34][P35][P36][P37][P38]. Report P1, P28, P29, P30, P31, P32, P34, P35, P36, P37, P38, P39
Officers were authorised to negotiate detailed terms with British Land and report progress on the agreement in Spring 2015 [D][P2]. Report P2
Officers were authorised to investigate acquiring property interests in the Canada Water Area Action Plan core area, including possible use of statutory powers, for coordinated and comprehensive town centre redevelopment [D][P3]. Report P3
Why
British Land's plans for the shopping centre and headquarters create an opportunity for coordinated, comprehensive Canada Water redevelopment. Existing leases at both sites may need restructuring [P26]. Report P26
The council's ambition includes a new shopping destination, leisure facilities, a major King's College London campus, jobs, a range of homes including council housing, and identified community infrastructure gaps [P23]. Report P23
Canada Water is identified as an opportunity area with capacity for up to 3,500 new homes and 2,000 jobs [P17]. Regeneration should also benefit existing people and newcomers, spread investment across the area, address transport effects and maximise local training and employment [P24][P38]. Report P17, P24, P38
What happens next
Officers will negotiate detailed terms with British Land and report progress in Spring 2015 [D][P2]. Report P2
Officers will investigate additional property interests in the core area, including statutory powers, and return with specific proposals [P3][P42]. Report P3, P42
British Land will carry out public engagement before formal planning applications, which will not be submitted until July 2015 at the earliest [P45][P49]. Report P45, P49
The money
up to £10m King's College London bid to the Treasury for Centre for Urban Science and Progress development support Report P19
Options considered
Chosen: Negotiate detailed terms with British Land. The endorsed core priorities set the parameters for the legal agreement and negotiations [D][P1][P39][P40]. Report P1, P39, P40
Rejected: Continue separate contractual arrangements for the headquarters site. British Land's announcement ended work on the headquarters site in isolation and required consideration of both sites together [P26]. Report P26
Chosen: Investigate acquiring additional core area property interests. Additional land may be needed for coordinated and comprehensive redevelopment [P3][P41][P42]. Report P3, P41, P42
Implications
Financial: There are no direct resource implications at present [P51][P57]. A detailed assessment of the emerging commercial structure will follow negotiations [P51]. Report P51, P57
Legal: The endorsed priorities set the parameters for negotiation of a legal redevelopment agreement [D][P1][P39]. The acquisition investigation may include the use of statutory powers [D][P3][P42]. Report P1, P3, P39, P42
Other: The scheme must provide 35% affordable housing as a percentage of general needs housing, split 70/30 between rent and shared ownership [P30]. The rented element will remain council housing [P30]. Report P30
Risk: The planning application is likely to be an outline application across both sites, with a detailed phase 1 application around the Canada Water basin [P44][P48]. Its scale requires a full EIA [P44][P48]. Report P44, P48
Other: The council will retain freeholds of the headquarters and shopping centre sites and seek a long term income stream from increased land and property prices and development profit [P28][P29]. Report P28, P29
Other: Regeneration should benefit all sections of the existing population and newcomers, with investment benefits spread around the whole area [P24]. Report P24
Other: Transport work includes updating the model for several travel modes, considering Lower Road gyratory improvements and a Surrey Quays station entrance, and supporting pedestrian and cycling links [P24][P36][P37]. Report P24, P36, P37
Other: The development mix is expected to include a public leisure centre, education facilities, possible school space, significant jobs, training and business start up opportunities [P31][P32][P34][P35][P38]. Report P31, P32, P34, P35, P38
Who and where
Canada Water's existing population and newcomers Report P24
People seeking homes, including affordable and council housing Report P23, P30
Lower Road traders Report P24
People seeking jobs, training and business start up opportunities Report P35, P38
Current and future school pupils Report P18, P34
Users of the proposed public leisure centre Report P31
King's College London and users of its teaching, research and administrative facilities Report P32, P33
Timeline
November 2013: Cabinet supported a cooperation agreement and the objective of a major King's College London campus at Harmsworth Quay Report P6, P9, P10
April 2014: The revised Canada Water Area Action Plan was published Report P5
6 November 2014: The officer report was finalised Report P62
Spring 2015: Negotiation progress and a detailed resource assessment are due, and adoption of the revised Area Action Plan is expected Report P2, P20, P51
July 2015 at the earliest: Formal planning applications may be submitted Report P45, P49
during 2016: Development of the Centre for Urban Science and Progress could commence if the funding bid succeeds Report P19
Plain English for the jargon
CWAAP: The revised Canada Water Area Action Plan [P5].
KCL: King's College London [P6].
CUSP: Centre for Urban Science and Progress, proposed as a research establishment for sustainable urban systems [P19].
EIA: The full assessment required because of the scale of the planning application [P44][P48].
Freehold: The council's ownership of the headquarters and shopping centre sites [P21][P28].
Heads of Terms: The main terms of the proposed agreement structure, on which officers were due to report [P40].
Shared ownership: One part of the 70/30 affordable housing split, alongside rent [P30].
Statutory powers: Legal powers that may be considered when investigating property acquisitions [P3][P42].
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item17
Resolved
That the core priorities in paragraph 17 of the report which are intended to set the parameters for the negotiations with British Land concerning a legal agreement for the redevelopment of Harmsworth Quay and Shopping Centre sites be endorsed. 2. That officers be authorised to proceed with negotiations to agree detailed terms with British Land and to report back progress regarding the agreement in Spring 2015. 3. That officers be authorised to investigate the acquisition of property interests in the Canada Water Area Action Plan core area, including the use of statutory powers, which may be necessary for the delivery of a coordinated and comprehensive redevelopment of the town centre.
Word for word from the decision Southwark published for this meeting.Source: moderngov.southwark.gov.uk
Report to Cabinet (decommissioned, for the Executive after, 7 pages
Recommendations
1. That cabinet endorses the core priorities in paragraph 17 which are intended to set the parameters for the negotiations with British Land concerning a legal agreement for the redevelopment of Harmsworth Quay and Shopping Centre sites.
2. That cabinet authorise officers to proceed with negotiations to agree detailed terms with British Land and to report back progress regarding the agreement in Spring 2015.
3. That cabinet authorise officers to investigate the acquisition of property interests in the Canada Water Area Action Plan core area, including the use of statutory powers, which may be necessary for the delivery of a coordinated and 1 comprehensive redevelopment of the town centre.
BACKGROUND INFORMATION
4. The council’s vision in the revised Canada Water Area Action Plan [CWAAP] published in April 2014 is “to make best use of the opportunity to create a new destination around the Canada Water [CW] basin which combines shopping, civic, education, and leisure, business and residential uses to create a new heart for Rotherhithe”.
5. Within the context of the emerging revised CWAAP the cabinet in November 2013 considered a report concerning a co-operation agreement with British Land [BL] and King’s College London [KCL] in respect of the future development of the Harmsworth Quay’s site [marked site I on the plan in Appendix 1] . As noted in that report the council owns the freehold of approximately 85% of the site which was occupied under various leases by Associated Newspapers Ltd [ANL]. The freeholds of remaining plots were owned by ANL. The context for the report was twofold:
a. The decision by ANL to relocate their print operation to a site in Essex which led to the company’s subsequent decision in late spring 2013 to put their land interests in HQ on the market. This process resulted in ANL applying during 2012 to the council to assign it’s leases to BL and in March 2013 the council agreed this request; and secondly
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Cabinet (decommissioned, for the Executive after at Southwark and we tell you when its next papers are published, before the meeting rather than after it.
Review of Void Disposal StrategyThat the progress of disposals of void housing properties since April 2009 be noted. 2. That the importance of void d...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.