Draper House Works - Independent Investigation - Update Report

Noted Executive 3 papers

AI summarySouthwark Cabinet noted officers' updated actions after the Draper House major works investigation, covering resident communication, defects and contractor oversight. [D] The officer report was marked as not a key decision. [P170]

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedCabinet noted the updated actions by officers. [D]
MoneyNot stated
What happens nextDraper monitoring and policy reviewMonitoring group and policy review will proceed. [P103] [P119]
Who it affectsDraper House residentsCommunications, defects, surveys and contract management are covered. [P5] [P20]

What was decided

Southwark Cabinet noted officers' updated actions following the independent investigation and the earlier Cabinet report of 9 December 2014 about the Draper House major works contract.

Why

Cabinet had asked for a further report to confirm that residents were invited and able to participate. Report P3

The investigation covered communications, building works, governance and transition. Report P6

The recommendations addressed delays, trust, contractor management, lessons learned and governance. Report P21

What happens next

The Head of Community Engagement will set up a monitoring group for Draper House. It will report to the residents association until the defects liability period ends. Report P103

Two further meetings of the Putting Residents First review were planned for January 2015. Recommendations would then go to the housing Cabinet member and strategic director for immediate implementation. Report P119

Appendix 1 sets out the action plan, including timescales and milestones for implementing the recommendations. Report P100, P101

The money

  • £ 4.3m Procurement threshold above which a quality evaluation must take place Report P145

Options considered

  • Chosen: Set up a monitoring group for Draper House. The group will report to the residents association until the defects liability period ends. Report P103
  • Chosen: Review Putting Residents First through a short task group. Recommendations would go to the housing Cabinet member and strategic director for immediate implementation. Report P117, P119
  • Chosen: Use default notices to escalate poor contractor performance. They became a formal performance measure and were used when performance fell short. Report P130
  • Chosen: Include termination at will clauses in the new contractor framework. The Major Works team had included the clause in the framework being procured. Report P127
  • Rejected: Require termination at will clauses in every other contract. Other contracts are handled case by case because the clause can increase contract costs. Report P126, P128
  • Chosen: Assess extra staff and skills for each significant project. The Head of Major Works makes this assessment for each significant scheme. Report P67
  • Chosen: Carry out resident satisfaction surveys halfway through large projects. Future large projects will have a survey halfway through and at completion. Report P70
  • Chosen: Continue strategic meetings with the Draper Residents Association. The meetings were useful for monitoring action points and were agreed to continue. Report P18

Implications

  • Legal: The council must consider bids from providers meeting its selection requirements under EU procurement rules unless specific exclusion grounds apply. Projects over £ 4.3m need a fair quality evaluation. Report P137, P145
  • Financial: Termination at will clauses can increase contract costs where contractors have made investment, so their use in other contracts is case by case. Report P128
  • Risk: Default notices are now a formal performance measure. Eight had been served on major works partners in the previous 12 months. Report P130
  • Staffing: Significant projects are assessed for extra staff and skills, with two design and delivery managers providing senior support. Report P67
  • Staffing: The Draper House project manager continued through the initial defects period, with handover arrangements to be agreed. Report P54, P55
  • Financial: New framework contracts will set a weekly loss amount that the council can claim for project delay. Report P147
  • Other: No leaseholder at Draper House will pay more than the value of the original consultation notices. Report P141
  • Other: Council responses to resident queries are normally sent within ten working days. Report P27

Who and where

  • Draper House residents, for communications, defects and surveys [P10] [P12] [P14] Report P10, P12, P14
  • Draper Residents Association, for communications and monitoring [P10] [P17] [P103] Report P10, P17, P103
  • Draper House leaseholders, for the consultation charge limit [P140] [P141] Report P140, P141
  • AE Elkins, for defect reporting and site response [P11] [P12] [P13] Report P11, P12, P13
  • Tenants Council and Home Owners Council, for the policy review [P117] [P119] Report P117, P119
  • Ward councillors, for regular scheme briefings [P43] [P44] [P107] Report P43, P44, P107
  • Major works contractors and subcontractors, for performance and payment rules [P130] [P134] [P135] Report P130, P134, P135
  • Future major works residents, for communications and surveys [P27] [P32] [P70] Report P27, P32, P70

Timeline

  • 16 July 2014: The council received the final independent investigation report. [P7] Report P7
  • 18 August 2014: A meeting with the residents association set out transition arrangements and a single council contact. [P57] Report P57
  • 1 September 2014 and 9 September 2014: The investigation report went to the Tenants Council and the scrutiny sub committee. [P4] Report P4
  • 19 September 2014, 6 November 2014, and 15 December: Strategic meetings took place with the residents association chair, the housing strategic director and the independent resident's friend. [P9] Report P9
  • 9 December 2014: Cabinet received the earlier investigation report and asked for a further update. [P3] Report P3
  • 11 December 2014 and January 2015: The Putting Residents First review panel first met, with two further meetings planned. [P70] [P119] Report P70, P119
  • 15 January 2015 and February 2015: The officer report was finalised, and the dedicated project manager's commission was extended. [P170] [P12] Report P170, P12
  • 2026-05-28: Cabinet noted the updated actions. [D]

Plain English for the jargon

  • DRA: Draper Residents Association, involved in communications, reviews and monitoring. [P8] [P17] [P103]
  • Defects liability period: The period after works when defects are addressed and transition arrangements are monitored. [P54] [P56]
  • Putting Residents First: The council's resident consultation process for major works, which was under review. [P69] [P92] [P117]
  • RPT: Residents Project Team, made up of leaseholders and tenants to represent a scheme's residents. [P30]
  • Default notice: A formal notice used when contractor performance does not meet expectations. [P130]
  • AE Elkins: The contractor carrying out works and reporting defects at Draper House. [P11] [P12]
  • Major Works: The council function that manages major building work contracts and project teams. [P67] [P83] [P84]
  • TRA: Tenants and Residents Association, a resident representative body used for consultation. [P28] [P30]
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item8

Resolved

That the updated actions by officers following the publication of the independent investigation report and the previous report to cabinet on 9 December 2014 into the major works contract at Draper House be noted.
Word for word from the decision Southwark published for this meeting. Source: moderngov.southwark.gov.uk

Follow this further

Built from Southwark's papers

What the report saysPro

Report to Cabinet (decommissioned, for the Executive after, 18 pages

Recommendation

1. That cabinet note the updated actions by officers following the publication of the independent investigation report and the previous report to cabinet on 9 December 2014 into the major works contract at Draper House.

BACKGROUND INFORMATION

2. Cabinet received a report on 9 December 2014 following the independent investigation commissioned into the contract at Draper House. Cabinet asked for a further report back on progress to their next meeting, to ensure that residents were invited and able to participate. Previously overview and scrutiny committee received an update report on 14 July 2014 regarding the major works at Draper House and what actions the council had taken, and continued to take, to improve contract management and the communication with residents following the original scrutiny review in June 2013 and report to cabinet in December 2013.

1 3. Since that report the independent investigation report commissioned by the director of legal services and monitoring officer has been produced and reported to cabinet. This had previously been reported to housing and community safety scrutiny sub-committee on 9 September 2014, to Tenants Council on 1 September 2014 and to Home Owners Council on 24 September 2014.

4. This report sets out the updated actions by officers to review and implement the recommendations of the independent report as well as the additional recommendations from the sub-committee on 9 September and Tenants Council on 1 September 2014.

5. The terms of reference for the independent investigation covered three broad areas: • Communications • Building Works • Governance and Transition.

6. The investigation was carried out by Claer Lloyd-Jones and the council received the final report on 16 July 2014. A copy of the report was sent to all the residents living in Draper House, ward councillors, Simon Hughes MP and other interested parties.

7. At the scrutiny meeting on 9 September 2014, the strategic director housing and community services reported that she would take personal responsibility for ensuring that the recommendations of the committee would be implemented fully. She also confirmed that she would meet with the DRA to monitor progress and ensure that actions were kept on track.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Draper House: Summary Action PlanAppendix 1 3 pages Download
PDF
Draper House: Summary of Residents Satisfaction SurveyAppendix 2 2 pages Download
PDF
Report: Draper House Works Independent Investigation updateReport 18 pages DownloadRead as text

At this meeting

Whole meeting

Who was there

10 of 12 attended
PJ
Councillor Peter JohnChair, present
IW
Councillor Ian WingfieldCommittee Member, present
FC
Councillor Fiona ColleyCommittee Member, present
DD
Councillor Dora Dixon-Fyle MBECommittee Member, present
BH
Councillor Barrie HargroveCommittee Member, present
RL
Councillor Richard LivingstoneCommittee Member, present
DM
Councillor Darren MerrillCommittee Member, present
VM
Councillor Victoria MillsCommittee Member, present
MS
Councillor Michael SituCommittee Member, present
MW
Councillor Mark WilliamsCommittee Member, present
EK
Eleanor KellyOfficer, expected
DF
Doreen Forrester-BrownOfficer, expected

On this subject at Southwark

Search all
  1. Draper House Works - Independent Investigation - Update ReportThis decision
  2. Report into Major Works at Draper House (Housing, Environment, Transport and Community Safety Scrutiny Sub-Committee)Noted
  3. Response to the Housing, Environment, Transport and Community Safety Scrutiny Sub-Committee on the Review of Major Works at Draper HouseNoted
  4. Draper House Works – Independent Investigation, Final Report – Officer ResponseNoted

More from Southwark Cabinet (decommissioned, for the Executive after

All decisions
MeetingDecisionOutcome
28 May 2026 Election of Chair for the meetingThat Councillor Maisie Anderson be elected chair for this meeting. Decided Open
28 May 2026 Notification of any items of business which the chair deems urgentIt was agreed that all the deputations would be heard so that consideration of these representations could be given p... Agreed Open
28 May 2026 Disclosure of Interests and DispensationsDecision Maker (IDM) report in respect of this issue. Councillor Peter John also declared a personal, non prejudicial... Decided Open
28 May 2026 Review of Void Disposal StrategyThat the progress of disposals of void housing properties since April 2009 be noted. 2. That the importance of void d... Noted Open
28 May 2026 Housing Revenue Account - Approval of Housing Revenue Budget Account 2011/12That the savings required to deliver a balanced housing revenue account (HRA) for 2011/12 be noted. 2. That the propo... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies