Asset Management Strategy - Kitchens and Bathrooms
AgreedExecutive2 papers
AI summaryCabinet agreed a six year kitchen and bathroom programme to deliver by March 2021, starting in 2015/16 [D]. The capital refresh included a £186.3m provisional sum for kitchens and bathrooms [P73].
Written from the decision and the officer reportPDF Pro
OutcomeAgreedDelivery by March 2021, starting in 2015/16 [D]
Money£186.3m provisional sum [P73]Within housing investment in excess of £1 billion [P73]
What happens nextConsultation, then Cabinet approval [P4] [P6]Residents to be consulted; plans due March 2015 [P4] [P6]
Who it affectsCouncil tenants and residents [P2] [P51]Qualifying kitchens and bathrooms in council homes [P30]
What was decided
Cabinet agreed a six year kitchen and bathroom programme as part of the wider asset management strategy. The goal is delivery by March 2021. Report P2
The initial one year programme will run alongside the final year of Warm, Dry and Safe in 2015/16. It will replace kitchens older than 20 years and bathrooms older than 30 years. Officers were instructed to consult residents on the next five years after 2015/16. Report P3, P4
Cabinet noted the housing stock asset evaluation and required further work to test and refine its results. Officers must develop a 30 year financial business plan and asset management strategy principles for Cabinet approval in March 2015. Report P5, P6
Why
The current Warm, Dry and Safe programme included some bathroom work but not comparable kitchen work, unless there was a serious health and safety issue. Initial Savills findings also gave the council confidence that it had the financial capacity to deliver the programme. Report P15, P17, P18
Age was chosen because it is more objective and straightforward than condition. Condition can involve subjective interpretations and challenge. Report P28
Running the first year with Warm, Dry and Safe was expected to provide value for money because site set up and most personnel were already in place. Bulk purchasing and price harmonisation may create savings, but these were not yet quantifiable. Report P32, P36
What happens next
Officers must consult residents borough wide on the programme for the next five years after 2015/16, within the overall asset management strategy consultation. Report P4
Contractors will carry out further surveys to confirm how many kitchens and bathrooms need renewal. Actual first year costs and unit rates will be reviewed to revise the subsequent programme. Report P34, P36
Officers must bring a 30 year financial business plan and future asset management strategy principles to Cabinet in March 2015. They must also prepare the cyclical programme for April 2016 to March 2021. Report P6, P31
The money
£186.3m Provisional sum for kitchens and bathrooms within the revised housing stock investment approved in March 2014 Report P73
£326m Investment programme for the council's five year Warm, Dry and Safe programme Report P19
Over £237m Spent on Warm, Dry and Safe by the end of 2014 Report P22
in excess of £1 billion Revised ten year housing stock investment programme approved in March 2014 Report P73
Options considered
Chosen: Six year programme as part of the wider asset management strategy. It advances the manifesto commitment to provide kitchens and bathrooms for council tenants. Report P2, P69
Chosen: Deliver the initial year with the final Warm, Dry and Safe programme year. Site set up and personnel were already largely in place, supporting value for money. Report P3, P32
Chosen: Use age as the sole renewal criterion. Age was seen as more objective and straightforward than condition, so the approach would be fairer. Report P28, P29
Rejected: Use condition as an eligibility criterion. Condition was described as open to broader and subjective interpretations and therefore challenge. Report P28
Chosen: Consult residents on the remaining five year programme. The remaining programme forms part of the borough wide asset management strategy consultation. Report P4, P70
Rejected: Include the Aylesbury Estate in the future programme. It is part of a separate estate regeneration programme. Report P38
Rejected: Include High Investment Needs Estates in the future programme. Kitchens and bathrooms have already been renewed there where required. Report P39
Implications
Financial: The ongoing cyclical programme's provision will be considered through the asset management strategy consultation. Unit rates are based on existing partnering contracts and include allowances for costly work, with first year costs informing revisions. Report P35, P36, P73
Legal: There are no specific legal implications from the recommendations, and legal services will continue advising the Warm, Dry and Safe programme. Leaseholders remain responsible for internal works and are excluded. Report P74, P81
Equalities: Age based eligibility was chosen for fairness. Tenants with specific needs will be considered during and after works, and better accommodation is expected to contribute to health and wellbeing. Report P28, P53
Climate: Project briefs will cover Sustainable Homes requirements, whole life costs, sustainable sourcing, low running costs and recycling where practicable. Report P63, P67
Risk: Residents near major works may experience short term disruption. The Considerate Contractor scheme will be used to minimise disturbance. Report P51, P60
Staffing: No staffing issues arise directly from the report at this stage. Personnel resources were largely already in place for the combined programme. Report P32, P78
Other: Residents in the final Warm, Dry and Safe year will receive more internal works, and the council must communicate that this is part of an ongoing programme. Report P37
Other: Local supply chains, labour, training, apprenticeships and increased trade with local traders may provide wider benefits. Report P55, P56, P58
Who and where
Council tenants with qualifying kitchens or bathrooms in homes receiving programme works Report P30
Residents affected by major works or living close to new developments Report P51
Tenants with specific needs Report P53
Leaseholders, who are responsible for internal works under their leases and are excluded from the programme Report P74
Aylesbury Estate residents, excluded because the estate has a separate regeneration programme Report P38
High Investment Needs Estate residents, excluded because kitchens and bathrooms have already been renewed where required Report P39
Local businesses and construction workers through local supply chains, labour and training initiatives Report P55, P56
Timeline
18 October 2011: Cabinet agreed the five year Warm, Dry and Safe programme, with a £326m investment. Report P19
June 2013: Savills issued its final Stock Options Appraisal report following the Housing Commission report in 2012. Report P8
March 2014: Cabinet approved revised ten year housing stock investment, including a £186.3m provisional sum for kitchens and bathrooms. Report P73
March 2015: Cabinet was to consider the financial business plan, strategy principles and related report. Report P6, P13
2015/16: The initial one year kitchen and bathroom programme coincided with the final Warm, Dry and Safe year. Report P3
2016: Warm, Dry and Safe had a target for 90% of homes to meet the decent homes standard. Report P17
April 2016 to March 2021: The balance of kitchens and bathrooms was to be installed through cyclical works in estates and street properties. Report P31
March 2021: Target date for delivering kitchens and bathrooms to every council tenant. Report P2
Plain English for the jargon
Warm, Dry and Safe (WDS): Programme with a target for 90% of homes to meet the decent homes standard by 2016 [P17].
Decent Homes Standard (DH): Standard assessing kitchens and bathrooms for disrepair and modern facilities [P26].
Asset Performance Evaluation: Review of housing assets covering cash flow, financial performance and social sustainability [P10] [P12].
High Investment Needs Estates (HINE): Estates where kitchens and bathrooms have already been renewed where required, and which are excluded from the future programme [P39].
Considerate Contractor scheme: Scheme seeking to minimise disturbance and disruption during construction [P60].
London Living Wage (LLW): Minimum pay rate expected from contractors and subcontractors where appropriate [P61].
Sustainable Homes: Requirements covering construction, design and specification and setting targets to minimise adverse environmental impact [P63].
HIP: Investment programme approved in March 2014 that provisionally included the works [P83].
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item17
Resolved
That a six year kitchen and bathroom programme to “deliver a quality kitchen and bathroom for every council tenant” by March 2021, as part of a wider asset management strategy be agreed. 2. That the initial 1 year kitchen and bathroom programme set out in Appendix 1 of the report to coincide with the final year of the current Warm, Dry and Safe Programme in 2015/16 to replace kitchens older than 20 years and bathrooms older than 30 years be agreed. 3. That officers be instructed to consult residents on the proposals for the next five years of the programme, post 2015/16, as part of the overall asset management strategy consultation that will take place borough wide. 4. That the progress of the asset performance evaluation of the council’s housing stock carried out in partnership with Savills and the council be noted and that further work is being carried out to test and refine the results of the work to date with a 30 year financial business plan and principles for a future asset management strategy and instructs officers to bring these forward for cabinet approval in March 2015. This report will be considered by cabinet in March 2015.
Word for word from the decision Southwark published for this meeting.Source: moderngov.southwark.gov.uk
Report to Cabinet (decommissioned, for the Executive after, 9 pages
Recommendations
That cabinet:
1. Agrees to establish a six year kitchen and bathroom programme to “deliver a quality kitchen and bathroom for every council tenant” by March 2021, as part of a wider asset management strategy.
2. Agrees to the initial 1 year kitchen and bathroom programme set out in Appendix 1 to coincide with the final year of the current Warm, Dry and Safe Programme in 2015/16 to replace kitchens older than 20 years and bathrooms older than 30 years.
3. Instruct officers to consult residents on the proposals for the next five years of the programme, post 2015/16, as part of the overall asset management strategy consultation that will take place borough wide.
4. Notes the progress of the Asset Performance Evaluation of the council’s
1 housing stock carried out in partnership with Savills and the council, that further work is being carried out to test and refine the results of the work to date with a 30 year financial business plan and principles for a future asset management strategy and instructs officers to bring these forward for cabinet approval in March 2015. This report will be considered by cabinet in March 2015.
BACKGROUND INFORMATION
5. Following the Housing Commission report in 2012 the council engaged Savills to carry a Stock Options Appraisal. Their final report was issued in June 2013. This noted that:
‘The development of an active policy of managing housing assets which challenges the value for money of each investment decision, based on an analysis of both the value of future cashflows, and the extent to which investment meets the council’s social housing objectives could improve long term business plan capacity and resident satisfaction.’
6. Subsequently Savills were instructed to carry out further work in conjunction with the council with the Next Steps on Developing Long Term Plans for the Delivery of New Council Homes report which was presented to cabinet in July 2014, noting that a comprehensive appraisal of the overall performance of current Housing Revenue Account (HRA) assets was being undertaken and that the outcome would be reported back to cabinet.
7. The aim of this review was to:
• consider operational cash flows at a local level and assess their worth to the housing business to provide a measure of financial performance • identify non-financial measures of social sustainability and to provide an analysis of this at the same local level.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Cabinet (decommissioned, for the Executive after at Southwark and we tell you when its next papers are published, before the meeting rather than after it.
Review of Void Disposal StrategyThat the progress of disposals of void housing properties since April 2009 be noted. 2. That the importance of void d...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.