Gateway 1 Procurement Strategy Approval: Supply of Electricity to All Council Sites

Approved Executive 2 papers

AI summarySouthwark approved a four year electricity procurement strategy for all council sites from 1 October 2016, estimated at £6.4m per annum and £25.6m in total. [D]

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedFour years from 1 October 2016 for council sites. [D]
Money£6.4m per annum; £25.6m [D]Estimated annual and four year total values. [D]
What happens nextGateway 2 report update. [D]Add warm dry safe programme fuel bill outcomes. [D]
Who it affectsAll council sites. [D]Electricity supply from 1 October 2016 for four years. [D]

What was decided

Southwark approved the electricity procurement strategy for supply to all council sites.

The strategy covers four years from 1 October 2016, with an estimated value of £6.4m per annum and £25.6m in total.

The Gateway 2 report must include information on warm dry safe programme outcomes on fuel bills.

Why

The current NPOWER contract ends on 30/09/16, and the approved supply period starts on 1 October 2016. Report P3

What happens next

Add information on warm dry safe programme outcomes on fuel bills to the Gateway 2 report.

The money

  • £6.4m per annum Estimated annual value for electricity supply to all council sites.
  • £25.6m Estimated total value for the four year period from 1 October 2016.
  • £1,341,761.79 Total annual cost in the background pricing data for the period ending 30/09/2015. Report P13, P16

Implications

  • Financial: The approved strategy is estimated at £6.4m per annum and £25.6m in total.
  • Financial: The background pricing data lists a total annual cost of £1,341,761.79 for the period ending 30/09/2015. Report P13, P16
  • Other: The approved strategy covers all council sites for four years from 1 October 2016.
  • Other: The current NPOWER contract ends on 30/09/16. Report P3
  • Risk: Southwark Park Primary School and Town Hall are pending additions, while Chiltern House has missing or queried prices. Report P5, P6
  • Climate: The background site data includes conventional and allocated renewable energy types. Report P1
  • Other: The current arrangement is a fully managed flexible basket using purchase in advance. Report P3

Who and where

  • All council sites
  • NPOWER, the current electricity supplier Report P3
  • Schools at the listed sites, including pending Southwark Park Primary School Report P4, P5
  • Libraries at the listed sites Report P4
  • Leisure centres and pavilion club houses Report P4
  • Housing estates and houses Report P4
  • Council offices and operational sites, including pending Town Hall Report P4, P5
  • Chiltern House, with missing or queried prices Report P6

Timeline

  • 01/10/12: Start of the current NPOWER contract. Report P3
  • 01/10/2014: Start of the background pricing period. Report P13
  • 30/09/2015: End of the background pricing period. Report P13
  • 30/09/16: End of the current NPOWER contract. Report P3
  • 1 October 2016: Start of the approved four year electricity supply period.

Plain English for the jargon

  • Gateway 2: The report that must include warm dry safe programme fuel bill information. [D]
  • Warm dry safe: The programme whose fuel bill outcomes must be included at Gateway 2. [D]
  • Fully Managed (FM): The management type listed for the current electricity contract. [P3]
  • Flexible Basket: The basket type listed for the current electricity contract. [P3]
  • Purchase in Advance (PIA): The purchase method listed for the current electricity contract. [P3]
  • LASER Recovery: The recovery rate listed for the current contract, 0.126 P/kWh. [P3]
  • MPAN: The identifier used for each listed energy supply point. [P1]
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item12

Resolved

That the procurement strategy outlined in the report for the supply of electricity to all council sites as detailed in paragraph 2 of the report, at an estimated value of £6.4m per annum for a four year period from 1 October 2016 giving an estimated total value of £25.6m, be approved. 2. That information on the outcomes of the warm dry safe programme on fuel bills be added into the gateway 2 report.
Word for word from the decision Southwark published for this meeting. Source: moderngov.southwark.gov.uk

Follow this further

Built from Southwark's papers

What the report saysPro

Report to Cabinet (decommissioned, for the Executive after, 4 pages

Supplementary MPAN Data Energy Type 1200060184563 00 845 009 Conventional 1200061414343 00 845 009 Conventional 1200061119538 00 845 009 Conventional 1200010187888 00 845 009 Conventional 1200010187879 00 845 009 Conventional 1200060163493 00 845 009 Conventional 1200060907922 00 845 009 Conventional 1200010191305 00 845 009 Conventional 1200010191652 00 845 359 Conventional 1200060685080 00 845 009 Conventional 1200010187220 00 845 009 Conventional 1200010194991 00 845 009 Conventional 1200061423756 00 845 009 Conventional 1200010188108 00 845 009 Conventional 1200060769261 00 845 009 Conventional 1200010193117 00 845 009 Conventional 1200010193108 00 845 009 Conventional 1200052422091 00 845 009 Conventional 1200010219866 00 845 009 Conventional 1200061065946 00 845 009 Conventional 1200010191332 00 845 009 Conventional 1200010193376 00 845 009 Conventional 1200060165107 00 846 009 Allocated Renewable 1200060165091 00 846 009 Allocated Renewable 1200060165082 00 846 009 Allocated Renewable 1200060917318 00 845 009 Conventional 1200060533397 00 845 009 Conventional 1200010260321 00 846 009 Conventional

1200061433258 1200010192879

1200010187949 Authority: London Borough of Southwark Current Supplier: NPOWER Contract Start Date: 01/10/12 Contract End Date: 30/09/16 Management Type: Fully Managed (FM) Contract Type: Flexible Basket Type: Purchase in Advance (PIA) LASER Recovery: 0.126 P/kWh

Site Name & Address Post Code 132 Queens Road, London SE15 2HP 134 Queens Road, Peckham, London SE15 2HP 7 Talfourd Place Peckham London SE15 5NW Aylesbury Development Area, Thurlow Street, Aylesbury Road, London SE17 2UW Aylesbury Development Area, Thurlow Street, Aylesbury Road, London SE17 2UW Boiler Estate - Boiler House, Royal Road, Otto Street, Walworth London SE17 3NR Canada Water Library, 21 Surrey Quays Road, London SE16 7AN Columbia-Regina Estate, Canada Estate, Moodkee Estate, Bermondsey, London SE16 1BJ Coniston Boiler House, Wyndham Housing Estate, Old Kent Road, London SE5 0XP Dulwich Leisure Centre, 45 East Dulwich Road, London SE22 9AN John Harvard Library, 211 Borough High Street, London SE1 1JA Lock Office, Rope Street/Plough Way, London SE16 1XT Lyndhurst Primary School, Grove Lane, Camberwell, London SE5 8SN Mabel Goldwyn House, 49 Grange Walk, London SE1 3DY Michael Faraday Primary School, Portland Street, London SE17 2HR North Peckham Development - MT Boiler, Blakes Road, Peckham, London SE15 6RP North Peckham Development - MT Boiler, Blakes Road, Peckham, London SE15 6RP Oliver Goldsmith Primary School, 83 Peckham Road, Camberwell, London SE5 8UH Peckham House Healthy Living Centre, 10 Melon Road, Peckham, London SE15 5QN Pynners Pavilion Club House, Dulwich Common, London SE21 7HA Seven Islands Leisure Centre, Lower road, Bermondsey, London SE16 2TU Southwark Mstorey Car Park, Moncreiff Street, London SE15 5AA Southwark Offices, 160 Tooley Street, London SE1 2TZ Southwark Offices, 160 Tooley Street, London SE1 2TZ Southwark Offices, 160 Tooley Street, London SE1 2TZ Southwark Resource Centre, 10 Bradenham Close, London SE17 2QB St Josephs RC Primary School, George Row, London SE16 4UP Wendover Southwark Council (formerly Aylesbury NDC, Wendover 1 Thurlow Street, London SE17 2US

Pending Additions: Southwark Park Primary School, Galleywall Road, London SE16 3PB Town Hall, Peckham Road, London SE5 8PX

Missing/Queried Prices: Chiltern House, Portland Street, London SE17 2RS don Borough of Southwark

y Managed (FM)

chase in Advance (PIA)

Pricing Period 01/10/2014 - 30

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Background document: Copy of Southwark Flexible Electricity Prices Oct' 14Report 4 pages DownloadRead as text
PDF
Report: Gateway 1 Procurement Strategy Approval: Supply of Electricity to All Council SitesReport 11 pages Download

At this meeting

Whole meeting

Who was there

11 of 12 attended
PJ
Councillor Peter JohnChair, present
IW
Councillor Ian WingfieldCommittee Member, present
FC
Councillor Fiona ColleyCommittee Member, present
SC
Councillor Stephanie CryanCommittee Member, present
BH
Councillor Barrie HargroveCommittee Member, present
RL
Councillor Richard LivingstoneCommittee Member, present
DM
Councillor Darren MerrillCommittee Member, present
VM
Councillor Victoria MillsCommittee Member, present
MS
Councillor Michael SituCommittee Member, present
MW
Councillor Mark WilliamsCommittee Member, present
EK
Eleanor KellyOfficer, present
DF
Doreen Forrester-BrownOfficer, expected

On this subject at Southwark

Search all
  1. Gateway 1 Procurement Strategy Approval: Supply of Electricity to All Council SitesThis decision
  2. Gateway 1 – Procurement Strategy Approval -The NestApproved
  3. Gateway 1 - Procurement Strategy Approval - Southwark and Lambeth Barristers FrameworkApproved
  4. Gateway 1 - Procurement Strategy Approval - Framework contracts to provide bailiff services to the Revenues & Benefits and Parking ServicesApproved
  5. Gateway 2: Contract Award Approval - Corporate Insurance Procurement (excluding Property Insurance)Approved
  6. Gateway 1 - Initial Procurement Strategy, Parking and Traffic Enforcement Services ContractAgreed

More from Southwark Cabinet (decommissioned, for the Executive after

All decisions
MeetingDecisionOutcome
28 May 2026 Election of Chair for the meetingThat Councillor Maisie Anderson be elected chair for this meeting. Decided Open
28 May 2026 Notification of any items of business which the chair deems urgentIt was agreed that all the deputations would be heard so that consideration of these representations could be given p... Agreed Open
28 May 2026 Disclosure of Interests and DispensationsDecision Maker (IDM) report in respect of this issue. Councillor Peter John also declared a personal, non prejudicial... Decided Open
28 May 2026 Review of Void Disposal StrategyThat the progress of disposals of void housing properties since April 2009 be noted. 2. That the importance of void d... Noted Open
28 May 2026 Housing Revenue Account - Approval of Housing Revenue Budget Account 2011/12That the savings required to deliver a balanced housing revenue account (HRA) for 2011/12 be noted. 2. That the propo... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies