Quarterly Capital Monitoring Outturn Report for 2014/15 and Capital Programme Refresh for 2014/15-2023/24
NotedExecutive5 papers
AI summarySouthwark Cabinet approved capital budget virements and funded variations, and agreed how CIL may partly or fully fund council projects. It noted 2014/15 underspends of £7.2m for the general fund and £8.3m for housing, which will be reprofiled.
Written from the decision and the officer reportPDF Pro
OutcomeNotedGeneral fund and housing outturn positions were noted.
Money£7.2m general fund; £8.3m housingBoth were favourable variances and will be reprofiled.
What happens nextFurther reprofiling during 2015/16Updated procurement and contract information is required.
Who it affectsCapital programme and local communitiesLocal CIL funding is intended to show local benefit.
What was decided
Cabinet noted the 2014/15 outturn and wider programme positions for both the general fund and housing investment programme. Report P2, P3
Cabinet approved the virements and funded variations to both capital programmes. Report P4
Cabinet approved budget reprofiling and agreed the process for identifying projects that CIL may fund in full or in part. Report P5, P6
Why
The variations largely reflected budget reprofiling caused by complexities in procuring contracts and works, contract management and monitoring. Report P15
Budgets needed to match the 2014/15 outturn with forecast expenditure and resources in 2015/16 and later years. Report P5, P177
CIL is restricted to infrastructure that supports growth, with 70% for strategic projects, at least 25% for local areas and 5% allowed for administration. Report P106, P107, P111, P113, P159, P164
What happens next
Service managers will review forecasts during 2015/16 and reprofile budgets using the latest procurement and contract management information. Report P5, P178
The Infrastructure Planning Board will assess strategic CIL proposals and submit recommendations to Cabinet through capital monitoring reports. Report P159, P161
The planning service will administer CIL and publish annual spending and allocation proposals. Report P169
The money
£7.2m General Fund 2014/15 favourable variance Report P15
£77.7m Final 2014/15 general fund expenditure against a revised budget of £85m Report P24
£168.6m Final 2014/15 housing investment expenditure against a budget of £176.9m Report P26, P102
£585.6m Refreshed general fund capital programme for 2014/15 to 2023/24 Report P9
£1,538.4m Refreshed housing investment programme for 2014/15 to 2021/22 Report P9, P102
£1m Virement for Peckham Rye revitalisation and a new play area Report P60
approximately £8m per annum Expected CIL generation once fully established Report P157
Options considered
Chosen: Note the general fund outturn and wider programme position. The outturn variation was largely explained by budget reprofiling and delivery complexity. Report P2, P15
Chosen: Note the housing investment outturn and wider programme position. The favourable housing variance was reprofiled into 2015/16. Report P3, P102
Chosen: Approve the virements and funded variations. The variations provide the up to date budget position as at 1 April 2015. Report P4, P179
Chosen: Approve budget reprofiling. Forecast expenditure and resources needed to reflect the 2014/15 outturn. Report P5, P177
Chosen: Agree the process for identifying CIL funded projects. CIL is intended for infrastructure that supports growth and requires a defined allocation process. Report P6, P158, P159
Implications
Financial: The general fund and housing programme variances will be reprofiled into 2015/16 and later years. Report P102, P177
Financial: The £1m Parks allocation requires a virement from Environment and Leisure to the Chief Executive's department. Report P60
Legal: CIL spending and allocation proposals must be published annually, and Regulation 123 items cannot also seek section 106 obligations. Report P169, P171
Other: An Infrastructure Planning Board will assess strategic CIL proposals and send recommendations to Cabinet. Report P155, P159, P161
Risk: Programme slippage, funding uncertainty, management capacity and contract issues could affect delivery. Report P178, P182
Staffing: Dedicated finance teams and qualified departmental finance managers help control programme finances. Report P182
Other: The report is expected to have no or very limited direct impact on local people and communities. Report P184
Legal: Cabinet must monitor the council's financial position and act on any deterioration. Report P190
Who and where
Residents, learners, visitors and businesses in the borough Report P10
Council housing residents needing safety and decency improvements Report P104, P118
People affected by development in local areas Report P163, P164
School communities using expanded and maintained schools Report P34
People using roads, parks, libraries and leisure facilities Report P51, P58, P69, P71
People needing Disabled Facilities Grant adaptations Report P81
Peckham residents benefiting from transport improvements Report P93
Capital programme staff and service managers Report P182
Timeline
2014/15: Final outturns were recorded for the general fund and housing investment programme. Report P15, P102
25 March 2015: Council Assembly approved Southwark CIL and had agreed refreshed capital programmes. Report P9, P155
31 March 2015: Unapplied capital balances were committed to existing projects, subject to final account adjustments. Report P145
1 April 2015: CIL applied to applicable planning permissions, and updated capital budgets were recorded. Report P155, P179
during 2015/16: Further budget reprofiling and service manager forecast reviews were required. Report P5, P178
quarter 2 of 2015/16: Most remaining Warm, Dry and Safe major works were expected to be committed. Report P110
10 July 2015: The final capital monitoring report was dated. Report P196
March 2016: A 90% housing decency target was set. Report P104, P118
Plain English for the jargon
CIL: A floor space charge for infrastructure, applying to applicable planning permissions from 1 April 2015.
Strategic CIL: The 70% allocation proposed for physical infrastructure projects that support growth.
Local CIL: At least 25% of CIL allocated to projects in the relevant local area.
S106: Planning obligations used to secure contributions for infrastructure and affordable housing.
virement: A budget transfer, including £1m from Environment and Leisure to the Chief Executive's department.
reprofiling: Moving budget between years so forecasts match expected spending and resources.
WDS: The Warm, Dry and Safe housing programme for safety and decency works.
HIP: The Housing Investment Programme for housing capital works.
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item17
Resolved
That the outturn position for 2014/15 for the general fund capital programme including the overall position of the programme for the period 2014/15 to 2023/24 as detailed in appendices A and D of the report be noted. 2. That the outturn position for 2014/15 for the housing investment programme, including the overall position of the programme for the period 2014/15 to 2023/24, as detailed in Appendix B of the report be noted. 3. That the virements and funded variations to the general fund and housing investment capital programme as detailed in Appendix C of the report be approved. 4. That the re-profiling of budgets in line with the forecast expenditure and resources in the new financial year 2015/16 and future years in light of the 2014/15 outturn position for both the general fund and housing investment programmes as reflected in Appendices A, B and D be approved and it be noted that further re-profiling will be required during 2015/16 based on more up to date information available at that time. 5. That the process for identifying projects for which community infrastructure levy (CIL) may be used as all or partial funding as detailed in paragraphs 106-118 of the report be agreed.
Word for word from the decision Southwark published for this meeting.Source: moderngov.southwark.gov.uk
Report to Cabinet (decommissioned, for the Executive after, 20 pages
Recommendations
That cabinet:
1. Notes the outturn position for 2014/15 for the general fund capital programme including the overall position of the programme for the period 2014/15 to 2023/24 as detailed in appendix A and D.
2. Notes the outturn position for 2014/15 for the housing investment programme, including the overall position of the programme for the period 2014/15 to 2023/24, as detailed in Appendix B.
3. Approves the virements and funded variations to the general fund and housing investment capital programme as detailed in Appendix C.
4. Approves the re-profiling of budgets in line with the forecast expenditure and resources in the new financial year 2015/16 and future years in light of the 2014/15 outturn position for both the general fund and housing investment programmes as reflected in Appendices A, B and D and note further re-profiling will be required during 2015/16 based on more up to date information available at that time.
1 5. Agree the process for identifying projects for which Community Infrastructure Levy (CIL) may be used as all or partial funding as detailed in paragraphs 106- 118.
BACKGROUND INFORMATION
6. On 22 July 2014, the 2013/14 capital outturn report was presented to the cabinet. This reported the capital outturn position at the end of 2013/14 and approved the council’s capital programme up to 2023/24. At that time, the total value of the general fund programme stood at £509.8m and the housing investment programme stood at £1,075.8m
7. On 25 March 2015, council assembly agreed the recommendations of the 10 February 2015 cabinet for a refreshed general fund capital programme for the period 2014/15 to 2023/24 of £585.6m and the housing investment programme for the period 2014/15 to 2021/22 of £1,538.4m.
8. The scale of the capital programme is immense and with a total forecast spend of over £2billion; the capital programme represents a major element of the council’s financial activities. It has a significant and very visible impact on the borough and hence on the lives of those who live, learn, visit and or do business in the borough.
9. Due to the size and scale of the capital programme and the number of projects involved, it is inevitable that unforeseeable delays can occur which lead to some variations against planned spend. Historically the capital programme has been over programmed in year to compensate for these variations, whilst retaining a balanced programme overall.
10. This report sets out the outturn position for 2014/15 for the General Fund and the Housing Investment Programme (HIP).
KEY ISSUES FOR CONSIDERATION
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Cabinet (decommissioned, for the Executive after at Southwark and we tell you when its next papers are published, before the meeting rather than after it.
Review of Void Disposal StrategyThat the progress of disposals of void housing properties since April 2009 be noted. 2. That the importance of void d...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.