Written from the decision and the officer reportPDF Pro
OutcomeApprovedFunding matched additions; programme changes and departmental transfers were noted [D].
Money£52m forecast general fund surplusResources of £429.6m exceed forecast expenditure of £377.5m [P13].
What happens nextContinue quarterly capital monitoringScheme progress and forecast spending will continue to be reviewed [P12].
Who it affectsCapital programmes and council services
What was decided
Cabinet approved budget additions where additional funding had been secured since the last Cabinet report [D][P2]. Report P2
Cabinet noted the monitoring position for the general fund and housing investment programmes as at 30 September 2011 [D][P3]. Report P3
Cabinet noted additions linked to existing Cabinet decisions and movements of existing schemes between departments [D][P4]. Report P4
Why
Forecast general fund resources of £429.6m exceed forecast expenditure of £377.5m, giving an overall surplus of £52m [P13]. Report P13
Quarterly review identifies schemes unlikely to reach expected spending levels, and the apparent over programming was not considered a cause for concern [P12]. Report P12
The report says approval demonstrates proper administration of the council's financial affairs [P102]. Report P102
What happens next
Continue reviewing the capital programme to identify schemes unlikely to achieve the expected level of spend [P12]. Report P12
Monitor the possible effect of business rates localisation on New Homes Bonus funding from 2013/14 [P15]. Report P15
Provide the expected update in the third quarter on proposed IT projects affected by a change of contractor [P90]. Report P90
The money
£52m Overall forecast surplus against general fund forecast expenditure [P13]. Report P13
£429.6m Forecast available general fund resources [P13]. Report P13
£377.5m Forecast general fund expenditure [P13]. Report P13
£129.1m 2011/12 general fund expenditure budget after the quarter 2 increase [P11]. Report P11
£6.3m Quarter 2 increase to the 2011/12 general fund expenditure budget [P11]. Report P11
£15.1m Favourable 2011/12 general fund forecast expenditure variance [P11]. Report P11
£21.4m Housing expenditure reprofiled from 2011/12 into later years [P14]. Report P14
Financial: New budget additions are matched by additional funding secured since the last Cabinet report [P2]. Report P2
Financial: General fund forecast resources exceed forecast expenditure by £52m [P13]. Report P13
Financial: Housing expenditure of £21.4m was moved from 2011/12 into later years, giving revised forecast expenditure of £78m [P14]. Report P14
Risk: The £15.1m general fund variance relates to reprofiling, a traveller's site delay and the Burgess Park overspend [P11]. Report P11
Risk: Proposed business rates localisation could affect New Homes Bonus capital funding from 2013/14 [P15]. Report P15
Risk: Primary IT contracts are to terminate within the next twelve months, while new contract scope and requirements are under review [P90]. Report P90
Legal: The capital programme is said to satisfy the council's duty under the Local Government Act 1999 [P101]. Report P101
Other: The report describes no or very limited direct impact on local people and communities, although the capital programme will deliver enhancements to amenities and infrastructure [P98]. Report P98
School pupils and school infrastructure Report P23, P26
Adult social care services and community capacity Report P33
Regeneration and transport projects Report P36, P40
Waste and public realm services Report P52, P59
Housing projects outside the council's own housing stock Report P84
Council offices Report P89
Timeline
6 July 2011: Council Assembly agreed the capital programme and contingency allocation [P7]. Report P7
20 September 2011: Quarter 1 capital monitoring was reported to Cabinet [P6]. Report P6
30 September 2011: The monitoring position used for this decision was recorded [P3]. Report P3
October 2011: Capital legacy fund award recommendations were agreed [P79]. Report P79
December 2011: Phase 3b for St Michael's and All Angels Academy and Highshore was expected to reach financial close [P30]. Report P30
January 2012: St Thomas the Apostle College was expected to become operational, and the new waste facility was due to be fully operational [P30][P55]. Report P30, P55
February 2012: Phase 3c was hoped to reach financial close [P30]. Report P30
end of March 2012: Physical works for the Southbank Improvement Project were due to finish [P62]. Report P62
Plain English for the jargon
General fund: Council capital programme reported with the housing investment programme [P3].
Housing investment programme: Capital programme covering housing investment and building safety work [P91][P93].
Reprofiling: Moving planned expenditure into later years [P12][P94].
New Homes Bonus: A resource to ease pressure from housing and population growth [P15].
Capital legacy fund: A £2m provision for a lasting Olympic and Paralympic legacy [P78].
Departmental Capital Review Board: The group that checks project forecasts and profiling each quarter [P51].
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item10
Resolved
That the addition of budgets into the programme, matched by additional funding secured since the last report to cabinet be approved. 2. That the current monitoring position for the general fund capital programme 2011-21 and housing investment programme 2011-16 as at 30 September 2011 (Appendices A, B and D of the report) be noted. 3. That the additions into the programme of budgets relating to existing cabinet decisions and the movement of existing schemes between departments. (Appendix C of the report) be noted.
Word for word from the decision Southwark published for this meeting.Source: moderngov.southwark.gov.uk
Report to Cabinet (decommissioned, for the Executive after, 12 pages
Recommendations
That Cabinet:
1. Approve the addition of budgets into the programme, matched by additional funding secured since the last report to cabinet.
2. Note the current monitoring position for the general fund capital programme 2011-21 and housing investment programme 2011-16 as at 30 September 2011 (Appendices A, B and D).
3. Note the additions into the programme of budgets relating to existing cabinet decisions and the movement of existing schemes between departments. (Appendix C).
BACKGROUND INFORMATION
4. The quarter 1 capital monitor was reported to cabinet on 20 September 2011. It reported a total general fund (GF) programme for 2011-21 of £366m with forecast resources over the same period estimated to be £420m, an overall surplus of £54m. It was noted that the surplus resources will not become 1 available until the later half of the programme, from 2015/16 at the earliest. Overall the GF programme was reported on track to spend within the approved budget.
5. The capital programme 2011-21 report agreed by Council Assembly on 6 July 2011 agreed a sum to increase the capital contingency allocation by £2.8m to £5m in line with the target set in the medium term resource strategy. This report and future reports will present this as a negative figure within the resources section of the monitor, rather than as budget within the finance and resources programme. This change in presentation reflects the fact that we do not yet know in which year expenditure will be incurred against these resources.
6. The total housing investment programme expenditure for up to 2015/16 was reported in quarter 1 as £417m and was fully funded.
KEY ISSUES FOR CONSIDERATION
Summary of spend and resources
7. The original expenditure budget for the general fund programme for 2011/12 of £119.5m was increased to £122.8m in quarter 1. This has further increased by £6.3m in quarter 2 to £129.1m. The current forecast expenditure for the year is showing a favourable variance of £15.1m. The variance relates to a reprofiling of expenditure on the streetscape improvements programmes within regeneration and neighbourhoods; the reprofiling of expenditure within the Southwark schools for the future programme; a delay on one of the travellers’ site projects within the housing general fund programme; and a reprofiling of expenditure within the waste programme in environment as well as a reported overspend on the Burgess Park revitalisation project. The additional budgets between quarter 1 and quarter 2 relate to additional S106 funds within children’s services; additional grant allocations and S106 funds within regeneration and neighbourhoods; upgrade and refurbishment of essential CCTV in environment; and £469k grant funding in health and community services.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Cabinet (decommissioned, for the Executive after at Southwark and we tell you when its next papers are published, before the meeting rather than after it.
Review of Void Disposal StrategyThat the progress of disposals of void housing properties since April 2009 be noted. 2. That the importance of void d...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.