Gateway 2 - Contract Award Approval - The Charter School East Dulwich (TCSED) - Phase 1 works contract
ApprovedExecutive1 paper
AI summarySouthwark Cabinet approved the Phase 1 design and build contract award to Kier Construction Ltd, with £25,325,000 approved [D] [P2] [P3]. Award remains subject to final value for money confirmation and director approval [D] [P4].
Written from the decision and the officer reportPDF Pro
OutcomeApprovedPhase 1 works on Parcels 1 and 2 [D] [P2]
Money£25,325,000 [D] [P3]Total expenditure for works and associated costs [D] [P3]
What happens nextNot stated
Who it affectsNew 8 form secondary school [P23]School pupils, families and East Dulwich community [P24] [P58] [P59]
What was decided
Cabinet approved the award of the design and build contract to Kier Construction Ltd for Phase 1 works on Parcels 1 and 2 [D] [P2]. The contract period is approximately 72 calendar weeks, from 18 April 2017 to 3 September 2018 [D] [P2]. Report P2
Cabinet approved total expenditure of £25,325,000 for the works and associated Phase 1 development costs [D] [P3]. Report P3
The award is subject to the cost consultant's final report confirming value for money and approval by the strategic director of children's and adults' services before contract award [D] [P4]. Report P4
Why
Year 7 capacity is 3,120 places with 3,060 children, leaving around 60 spare places; around 3,200 places are required from 2024 onwards [P106]. Report P106
The complete new build provides learning and teaching environments and is intended to be an important community asset [P24]. Report P24
Competitive framework rates and package tendering support value for money; at 14 February 2017, approximately 90% of the proposed contract sum by value was firm, with further savings anticipated from the remaining 10% [P41] [P47]. Report P41, P47
What happens next
Before award, the cost consultant must submit a final report confirming value for money, and the strategic director must approve the award [D] [P4]. Report P4
Officers must establish and profile contract budgets in the council's financial information system [P83]. Report P83
The Regeneration Capital Works team will manage the contract with MACE as Employer's Agent, using monthly reviews of cost, programme and quality [P53] [P54]. Report P53, P54
The money
£25,325,000 Approved total expenditure for the main Phase 1 works and associated costs Report P3, P79, P92
£5,000,000 Existing capital programme allocation for the projected funding shortfall and design quality Report P11
£421,990 Total value of Kier Construction Ltd's pre construction services agreement Report P13
£510,884 Additional scope for Kier Construction Ltd's pre construction services appointment Report P14
£451,700 Total value of the enabling works package awarded to Syd Bishop & Sons Report P15
Options considered
Chosen: Award the Phase 1 design and build contract to Kier Construction Ltd. Kier had been appointed through a full tender for pre construction services, and approximately 90% of the proposed contract sum by value was firm [P33] [P47]. Report P2, P33, P47
Rejected: Include Parcel 3 in this contract. Phase 2 works on Parcel 3 are subject to a separate procurement. Report P17
Rejected: Proceed without final cost consultant confirmation. The award requires confirmation that the contract proposals represent value for money. Report P4, P82
Implications
Financial: The maximum contract cost is £25,325,000; the project is jointly funded by the EFA with a Southwark Council contribution [P79] [P81] [P92]. Report P79, P81, P92
Financial: The school is responsible for ongoing revenue effects, while other staffing and contract costs must remain within existing departmental revenue budgets [P84] [P85]. Report P84, P85
Legal: The proposed contract uses JCT 2011 Design and Build Contract with the council's standard amendments [P16]. The LCP mini competition was conducted under Public Contracts Regulations 2015 [P102]. Report P16, P102
Legal: Contract documents must require blacklisting compliance and allow termination for breach; the EFA development agreement must include the risk transfer agreement [P94] [P104]. Report P94, P104
Equalities: The scheme is described as inclusive and planned for 1,680 pupils aged 11 to 18; the report records consideration of the council's equality duties [P59] [P67] [P69]. Report P59, P67, P69
Climate: Design principles will manage energy use efficiently, and the scheme is achieving a BREEAM rating of Very Good [P73] [P74]. Report P73, P74
Risk: Mitigations include a parent company guarantee, site studies, long lead time planning, liquidated damages and regular cost, programme and quality monitoring [P53] [P54] [P56]. Report P53, P54, P56
Staffing: No direct staffing impact is expected from the award; the existing Regeneration Capital Works team will resource contract management [P53] [P78]. Report P53, P78
Who and where
Secondary school pupils in Southwark Report P23, P59, P106
Pupils, staff and parents using the new school Report P24
East Dulwich residents and surrounding communities Report P58, P63
Kier Construction Ltd and its subcontractors Report P56, P66
Local businesses, workers and apprentices Report P63, P65
The Charter School Educational Trust Report P59
Timeline
8 December 2015: Cabinet approved the council's agreement with the EFA for procurement and construction delivery Report P11
16 November 2016: Pre Construction Services contract award approval Report P13, P20
16 February 2017: Gateway 3 approval extended Kier's appointment to include full technical design Report P14, P20
21 March 2017: Gateway 2 contract award report approval Report P20
3 April 2017: Contract award and addition to the Contract Register Report P20
4 April 2017: Publication of the award notice on Contracts Finder Report P20
3 September 2018: Contract completion Report P2, P20
Plain English for the jargon
Gateway 2: Approval point used to award the main works contract [P18] [P37]
Design and build: Contractor responsibility for developing the design and carrying out the works [P34] [P38]
PCSA: Pre Construction Services Agreement, covering design development to RIBA stage 4 [P13]
LCP: London Construction Panel framework used to procure the main contractor [P12]
Employer's Requirements: Project design and specification issued to Kier Construction Ltd [P42]
Value for money: Final confirmation required from the council's cost consultant before contract award [D] [P4] [P82]
BREEAM Very Good: Environmental rating achieved by the school scheme [P74]
JCT 2011 Design and Build Contract: Proposed contract form, with the council's standard amendments [P16]
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item15
Resolved
That the award of the design and build contract for the Phase 1 works on Parcels 1 and 2 for The Charter School East Dulwich to Kier Construction Ltd for a contract period of approximately 72 calendar weeks commencing on 18 April 2017 and completing on 3 September 2018 be approved. 2. That a total expenditure of £25,325,000 for the works and associated costs with the phase 1 development be approved. 3. That the award be subject to the council’s cost consultant’s final report being submitted confirming that this represents value for money and is approved by the strategic director of children’s and adults’ services prior to contract award.
Word for word from the decision Southwark published for this meeting.Source: moderngov.southwark.gov.uk
Report to Cabinet (decommissioned, for the Executive after, 15 pages
Recommendations
That Cabinet:
1. Approve the award of the design and build contract for the Phase 1 works on Parcels 1 and 2 for The Charter School East Dulwich to Kier Construction Ltd for a contract period of approximately 72 calendar weeks commencing on 18 April 2017 and completing on 3 September 2018.
2. Approve a total expenditure of £25,325,000 for the works and associated costs with the phase 1 development.
3. Agree that the award is subject to the council’s cost consultant’s final report being submitted confirming that this represents value for money and is approved by the strategic director of children’s and adults’ services prior to contract award. BACKGROUND INFORMATION
4. In March 2015, the Department for Education (DfE) approved The Charter School Educational Trust’s application to open a new secondary school in East Dulwich. The Charter School East Dulwich (TCSED) will be a co-educational, non-selective, non-faith, inclusive secondary school for pupil’s aged 11 – 18 and deliver quality education for young people.
5. The Education Funding Agency (EFA) purchased 5.21 hectares of the Dulwich Community Hospital site from the NHS, which will be leased to TCSED on a peppercorn rent for 125 years. The sale agreement with NHS sees the site area released to the EFA in three parcels for the development as shown in Diagram 1:
Parcels 1 and 2 (the north east and south west parcels) were released on contract completion in October 2015.
Parcel 3 is expected to be released in April 2019, with a longstop date of April 2020, when the NHS clinical services are relocated to a new building on the south east corner of the site (the parcel of land being retained by NHS property services). The chateau building is to be retained.
Note that Parcel 4 is an area of the site which is to be retained by the NHS for the new build health centre providing clinical services.
Diagram 1
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Cabinet (decommissioned, for the Executive after at Southwark and we tell you when its next papers are published, before the meeting rather than after it.
Review of Void Disposal StrategyThat the progress of disposals of void housing properties since April 2009 be noted. 2. That the importance of void d...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.