Gateway 2 - Contract Award Approval - The Charter School East Dulwich (TCSED) - Phase 1 works contract

Approved Executive 1 paper

AI summarySouthwark Cabinet approved the Phase 1 design and build contract award to Kier Construction Ltd, with £25,325,000 approved [D] [P2] [P3]. Award remains subject to final value for money confirmation and director approval [D] [P4].

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedPhase 1 works on Parcels 1 and 2 [D] [P2]
Money£25,325,000 [D] [P3]Total expenditure for works and associated costs [D] [P3]
What happens nextNot stated
Who it affectsNew 8 form secondary school [P23]School pupils, families and East Dulwich community [P24] [P58] [P59]

What was decided

Cabinet approved the award of the design and build contract to Kier Construction Ltd for Phase 1 works on Parcels 1 and 2 [D] [P2]. The contract period is approximately 72 calendar weeks, from 18 April 2017 to 3 September 2018 [D] [P2]. Report P2

Cabinet approved total expenditure of £25,325,000 for the works and associated Phase 1 development costs [D] [P3]. Report P3

The award is subject to the cost consultant's final report confirming value for money and approval by the strategic director of children's and adults' services before contract award [D] [P4]. Report P4

Why

Year 7 capacity is 3,120 places with 3,060 children, leaving around 60 spare places; around 3,200 places are required from 2024 onwards [P106]. Report P106

The complete new build provides learning and teaching environments and is intended to be an important community asset [P24]. Report P24

Competitive framework rates and package tendering support value for money; at 14 February 2017, approximately 90% of the proposed contract sum by value was firm, with further savings anticipated from the remaining 10% [P41] [P47]. Report P41, P47

What happens next

Before award, the cost consultant must submit a final report confirming value for money, and the strategic director must approve the award [D] [P4]. Report P4

Officers must establish and profile contract budgets in the council's financial information system [P83]. Report P83

The Regeneration Capital Works team will manage the contract with MACE as Employer's Agent, using monthly reviews of cost, programme and quality [P53] [P54]. Report P53, P54

The money

  • £25,325,000 Approved total expenditure for the main Phase 1 works and associated costs Report P3, P79, P92
  • £5,000,000 Existing capital programme allocation for the projected funding shortfall and design quality Report P11
  • £421,990 Total value of Kier Construction Ltd's pre construction services agreement Report P13
  • £510,884 Additional scope for Kier Construction Ltd's pre construction services appointment Report P14
  • £451,700 Total value of the enabling works package awarded to Syd Bishop & Sons Report P15

Options considered

  • Chosen: Award the Phase 1 design and build contract to Kier Construction Ltd. Kier had been appointed through a full tender for pre construction services, and approximately 90% of the proposed contract sum by value was firm [P33] [P47]. Report P2, P33, P47
  • Rejected: Include Parcel 3 in this contract. Phase 2 works on Parcel 3 are subject to a separate procurement. Report P17
  • Rejected: Proceed without final cost consultant confirmation. The award requires confirmation that the contract proposals represent value for money. Report P4, P82

Implications

  • Financial: The maximum contract cost is £25,325,000; the project is jointly funded by the EFA with a Southwark Council contribution [P79] [P81] [P92]. Report P79, P81, P92
  • Financial: The school is responsible for ongoing revenue effects, while other staffing and contract costs must remain within existing departmental revenue budgets [P84] [P85]. Report P84, P85
  • Legal: The proposed contract uses JCT 2011 Design and Build Contract with the council's standard amendments [P16]. The LCP mini competition was conducted under Public Contracts Regulations 2015 [P102]. Report P16, P102
  • Legal: Contract documents must require blacklisting compliance and allow termination for breach; the EFA development agreement must include the risk transfer agreement [P94] [P104]. Report P94, P104
  • Equalities: The scheme is described as inclusive and planned for 1,680 pupils aged 11 to 18; the report records consideration of the council's equality duties [P59] [P67] [P69]. Report P59, P67, P69
  • Climate: Design principles will manage energy use efficiently, and the scheme is achieving a BREEAM rating of Very Good [P73] [P74]. Report P73, P74
  • Risk: Mitigations include a parent company guarantee, site studies, long lead time planning, liquidated damages and regular cost, programme and quality monitoring [P53] [P54] [P56]. Report P53, P54, P56
  • Staffing: No direct staffing impact is expected from the award; the existing Regeneration Capital Works team will resource contract management [P53] [P78]. Report P53, P78

Who and where

  • Secondary school pupils in Southwark Report P23, P59, P106
  • Pupils, staff and parents using the new school Report P24
  • East Dulwich residents and surrounding communities Report P58, P63
  • Kier Construction Ltd and its subcontractors Report P56, P66
  • Local businesses, workers and apprentices Report P63, P65
  • The Charter School Educational Trust Report P59

Timeline

  • 8 December 2015: Cabinet approved the council's agreement with the EFA for procurement and construction delivery Report P11
  • 16 November 2016: Pre Construction Services contract award approval Report P13, P20
  • 16 February 2017: Gateway 3 approval extended Kier's appointment to include full technical design Report P14, P20
  • 21 March 2017: Gateway 2 contract award report approval Report P20
  • 3 April 2017: Contract award and addition to the Contract Register Report P20
  • 4 April 2017: Publication of the award notice on Contracts Finder Report P20
  • 18 April 2017: Contract start Report P2, P20
  • 3 September 2018: Contract completion Report P2, P20

Plain English for the jargon

  • Gateway 2: Approval point used to award the main works contract [P18] [P37]
  • Design and build: Contractor responsibility for developing the design and carrying out the works [P34] [P38]
  • PCSA: Pre Construction Services Agreement, covering design development to RIBA stage 4 [P13]
  • LCP: London Construction Panel framework used to procure the main contractor [P12]
  • Employer's Requirements: Project design and specification issued to Kier Construction Ltd [P42]
  • Value for money: Final confirmation required from the council's cost consultant before contract award [D] [P4] [P82]
  • BREEAM Very Good: Environmental rating achieved by the school scheme [P74]
  • JCT 2011 Design and Build Contract: Proposed contract form, with the council's standard amendments [P16]
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item15

Resolved

That the award of the design and build contract for the Phase 1 works on Parcels 1 and 2 for The Charter School East Dulwich to Kier Construction Ltd for a contract period of approximately 72 calendar weeks commencing on 18 April 2017 and completing on 3 September 2018 be approved. 2. That a total expenditure of £25,325,000 for the works and associated costs with the phase 1 development be approved. 3. That the award be subject to the council’s cost consultant’s final report being submitted confirming that this represents value for money and is approved by the strategic director of children’s and adults’ services prior to contract award.
Word for word from the decision Southwark published for this meeting. Source: moderngov.southwark.gov.uk

Follow this further

Built from Southwark's papers

What the report saysPro

Report to Cabinet (decommissioned, for the Executive after, 15 pages

Recommendations

That Cabinet:

1. Approve the award of the design and build contract for the Phase 1 works on Parcels 1 and 2 for The Charter School East Dulwich to Kier Construction Ltd for a contract period of approximately 72 calendar weeks commencing on 18 April 2017 and completing on 3 September 2018.

2. Approve a total expenditure of £25,325,000 for the works and associated costs with the phase 1 development.

3. Agree that the award is subject to the council’s cost consultant’s final report being submitted confirming that this represents value for money and is approved by the strategic director of children’s and adults’ services prior to contract award. BACKGROUND INFORMATION

4. In March 2015, the Department for Education (DfE) approved The Charter School Educational Trust’s application to open a new secondary school in East Dulwich. The Charter School East Dulwich (TCSED) will be a co-educational, non-selective, non-faith, inclusive secondary school for pupil’s aged 11 – 18 and deliver quality education for young people.

5. The Education Funding Agency (EFA) purchased 5.21 hectares of the Dulwich Community Hospital site from the NHS, which will be leased to TCSED on a peppercorn rent for 125 years. The sale agreement with NHS sees the site area released to the EFA in three parcels for the development as shown in Diagram 1:

 Parcels 1 and 2 (the north east and south west parcels) were released on contract completion in October 2015.

 Parcel 3 is expected to be released in April 2019, with a longstop date of April 2020, when the NHS clinical services are relocated to a new building on the south east corner of the site (the parcel of land being retained by NHS property services). The chateau building is to be retained.

 Note that Parcel 4 is an area of the site which is to be retained by the NHS for the new build health centre providing clinical services.

Diagram 1

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Report: Gateway 2: Contract Award Approval The Charter School East Dulwich (TCSED): Phase 1 works contractReport 15 pages DownloadRead as text

At this meeting

Whole meeting
3Notice of Intention to conduct business in a closed meeting, and any representations receivedOn the agenda 6MinutesApproved 7Deputation RequestsDecided 8Cultural Strategy Refresh 'Creative Southwark 2017 to 2022'Agreed 9Approval to go out to Public Consultation for the Introduction of Public Space Protection Orders (PSPOs) to Tackle Dog Related Anti-Social Behaviour (ASB)Approved 10Customer Access Strategy RefreshNoted 11Gateway 1- Procurement Strategy Approval: Door Entry and Warden Call ContractApproved 12Response to Central London Area Based Review of Skills 2016Noted 13Passmore Centre Investment PlanNoted 14Gateway 1 - Procurement Strategy Approval Proposed expansion of Rotherhithe Primary SchoolApproved
15Gateway 2 - Contract Award Approval - The Charter School East Dulwich (TCSED) - Phase 1 works contractThis decision
16Gateway 1 - Procurement Strategy Approval Southwark Regeneration in Partnership Programme Procurement Approval - Lot AApproved 17Southwark Regeneration in Partnership Programme Lot B Sites AppropriationApproved 1857 Elliotts Row, SE11, 9 Faunce Street, SE17, 24 Woodwarde Road SE22 - Disposal of Freehold interestsDecided 19Agreement of the Heads of Terms for the grant of a long leasehold interest in refurbished space to be provided at Maydew House and surrender of premises at Abbeyfield Road, SE16Approved 20Commercial Property Portfolio: Addition of Income Generating AssetsNoted 21Authorisation of Debt Write-off over £50,000 for Chief Executives Department, Commercial RentApproved 22Exclusion of the Press and PublicDecided 25Commercial Property Portfolio: Addition of Income Generating AssetsOn the agenda

Who was there

11 of 12 attended
PJ
Councillor Peter John OBEChair, present
SC
Councillor Stephanie CryanCommittee Member, present
FC
Councillor Fiona ColleyCommittee Member, present
BH
Councillor Barrie HargroveCommittee Member, present
RL
Councillor Richard LivingstoneCommittee Member, present
VM
Councillor Victoria MillsCommittee Member, present
JS
Councillor Johnson SituCommittee Member, present
MW
Councillor Mark WilliamsCommittee Member, present
IW
Councillor Ian WingfieldCommittee Member, present
MA
Councillor Maisie AndersonCommittee Member, apologies
EK
Eleanor KellyOfficer, present
DF
Doreen Forrester-BrownOfficer, present

On this subject at Southwark

Search all
  1. Gateway 2 - Contract Award Approval - The Charter School East Dulwich (TCSED) - Phase 1 works contractThis decision
  2. Gateway 1 - Highway works contractApproved
  3. Gateway 3 - Variation Decision - Parking and Traffic enforcement and associated services contractApproved
  4. Gateway 1 - Procurement Strategy Approval - Framework contracts to provide bailiff services to the Revenues & Benefits and Parking ServicesApproved
  5. Gateway 2: Contract Award Approval - Corporate Insurance Procurement (excluding Property Insurance)Approved
  6. Gateway 1 - Initial Procurement Strategy, Parking and Traffic Enforcement Services ContractAgreed

More from Southwark Cabinet (decommissioned, for the Executive after

All decisions
MeetingDecisionOutcome
28 May 2026 Election of Chair for the meetingThat Councillor Maisie Anderson be elected chair for this meeting. Decided Open
28 May 2026 Notification of any items of business which the chair deems urgentIt was agreed that all the deputations would be heard so that consideration of these representations could be given p... Agreed Open
28 May 2026 Disclosure of Interests and DispensationsDecision Maker (IDM) report in respect of this issue. Councillor Peter John also declared a personal, non prejudicial... Decided Open
28 May 2026 Review of Void Disposal StrategyThat the progress of disposals of void housing properties since April 2009 be noted. 2. That the importance of void d... Noted Open
28 May 2026 Housing Revenue Account - Approval of Housing Revenue Budget Account 2011/12That the savings required to deliver a balanced housing revenue account (HRA) for 2011/12 be noted. 2. That the propo... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies