What was decided
Cabinet approved the award of SRPP Lot B to Affinity Sutton Homes Ltd, subject to securing the funding requirement. The contract runs for 10 years from 31 October 2016 to 30 October 2026 and will deliver 606 new homes, including 284 council owned homes, plus 4,132m2 of commercial space or community facilities retained by the council and associated infrastructure under the Greater London Authority's London Development Panel Development Agreement. The total development cost is around £153m, with a council subsidy of £11.507m plus land and ancillary costs. Report P3
Cabinet approved £7.84m of Housing Zone grant for SRPP sites in the Old Kent Road/Peckham and Canada Water housing zones. It noted that the programme would seek £11.507m from the S106 affordable housing fund to meet the contract investment requirement. Lot A procurement will be repackaged and reprocured through separate Gateway reports. Report P4, P5, P6
Cabinet approved disposal of the council's Lot B land on the development agreement terms, subject to securing funding and any further negotiations considered necessary by the Director of Regeneration. The Leader delegated to the Cabinet Member for Regeneration and New Homes authority to identify sites with appropriate use and tenure requirements and approve Lot A's repackaging and reprocurement, except for South Dock Marina Boatyard. Lot A's new procurement strategy will go through Gateway 1 approval, and South Dock Marina Boatyard will be presented to Cabinet. Report P7, P10, P58
Why
Affinity Sutton submitted the most economically advantageous tender for Lot B. Its combined price and quality score was 83.05, and it scored highest on both price and quality. Report P94, P162
No tenders were received for Lot A. Bidders said the package was too demanding in technical complexity and risk because of the number and variety of sites, so smaller, more manageable packages were recommended. Report P56, P57, P58
The council considered the investment good value against other ways of procuring council homes. The comprehensive tender process was designed to secure the best price reasonably obtainable and meet market value requirements for the sites. Report P141, P163, P172, P176
What happens next
Secure the £11.507m S106 affordable housing funding before the award and land disposal proceed. Complete any further land negotiations considered necessary by the Director of Regeneration before entering the development agreement. Report P6, P7, P164, P169
Repackage Lot A into smaller, more manageable packages and retender it. Undertake soft market testing and secure Gateway 1 approval, with South Dock Marina Boatyard presented to Cabinet. Report P58, P152
Complete a full equalities impact assessment with the development partner before works start on the first site. Report P111
The money
- around £153m Total development cost for the Lot B contract Report P3
- £11.507m Council subsidy, plus land and ancillary costs Report P3
- £11.507m Additional funding sought from the S106 affordable housing fund Report P6
- £7.84m Housing Zone grant allocated to SRPP sites Report P5
- circa £1.9m Estimated gross revenue each year Report P142
- £1 million Spend threshold for at least one apprenticeship Report P36, P116
Options considered
- Chosen: Award SRPP Lot B to Affinity Sutton Homes Ltd. It submitted the most economically advantageous tender and scored highest on price and quality. Report P94, P162
- Rejected: Award SRPP Lot B to the other bidder. Affinity Sutton offered the best value financial offer and had the highest combined price and quality score. Report P75, P94
- Chosen: Repackage Lot A into smaller, more manageable packages. Smaller packages were recommended after feedback on technical complexity and risk. Report P56, P57, P58
- Rejected: Retain the original Lot A package. No tenders were received, and bidders considered the original package too demanding. Report P56, P57
- Chosen: Dispose of the council's Lot B land under the development agreement. The comprehensive tender process was intended to secure the best price reasonably obtainable and meet market value requirements. Report P7, P172, P176
Implications
- Financial: The award and land disposal depend on securing the additional £11.507m from the S106 affordable housing fund. The total development cost is around £153m, with a council subsidy of £11.507m plus land and ancillary costs. Report P3, P6, P7, P164, P169
- Financial: Revenue lost from car parking and short term lettings is expected to be more than replaced by income from new commercial property and council homes. On current estimates, gross revenue will be circa £1.9m annually. Report P142
- Legal: The procurement used a GLA LDP competitive tender process to meet the full tendering requirements of the Public Contract Regulations 2015. General fund site disposals are governed by section 123 of the Local Government Act 1972, while Housing Revenue Account site disposals are governed by section 32 of the Housing Act 1985 and relevant general consents. Report P168, P171, P173, P174, P175
- Risk: The leading risks are a funding gap, planning consent, additional costs and fewer council homes by 2018, each rated medium likelihood, and failure to achieve Housing Zone grant, rated low likelihood. Report P104
- Equalities: A community impact statement has been completed for two sites where the council will submit the planning application to speed delivery. Similar work is required for the remaining Lot B sites before planning submission. A full equalities impact assessment will be completed with the development partner before works start on the first site. Report P23, P108, P111
- Climate: The development partner must follow the Southwark New Homes Design Guide. Its commercial space requirement is BREEAM very good, and it covers flood risk management, public open space and public transport connectivity. Report P127, P128
- Staffing: The Housing Regeneration Programme Manager will be responsible for overall programme delivery under the Head of Regeneration. The restructured Regeneration Team is considered able to manage the additional workload. Report P136
- Other: Contract commitments include promoting and using local suppliers and businesses where applicable, at least one apprenticeship for every £1 million spent, and London Living Wage payments across the supply chain. Report P36, P116, P123
Who and where
- Council tenants and people seeking council homes Report P35, P120
- People seeking intermediate tenure homes Report P35, P44
- Local key workers Report P35, P44
- People seeking market sale homes Report P35
- People living, accessing or working near the development Report P109
- People with protected characteristics Report P110, P177
- Local suppliers and businesses Report P116
- Apprentices and supply chain workers Report P36, P123
Timeline
- 26/05/2016: Closing date for tender returns Report P30, P55
- 20/09/2016: Planned Cabinet approval of contract award Report P30
- 05/10/2016: End of scrutiny call in and implementation notice Report P30
- 06/10/2016: Contract award Report P30
- 07/10/2016: Added to the Contract Register Report P30
- 31/10/2016: Contract starts Report P3, P30
- by 2018: Up to 150 council homes in progress Report P35
- 30/10/2026: Contract completes Report P3, P30
Plain English for the jargon
- SRPP: Southwark Regeneration in Partnership Programme, which develops council sites with developers and registered providers [P14] [P19].
- S106: Section 106 planning obligation funding, used here for affordable housing and other development initiatives [P6] [P115].
- GLA: Greater London Authority [P3] [P22].
- LDP: London Development Panel framework used to procure development partners [P22] [P46].
- Lot A: Eight SRPP sites that received no tenders and will be repackaged and reprocured [P23] [P56] [P58].
- Lot B: Ten SRPP sites awarded for housing, retained commercial or community space and associated infrastructure [P23] [P27] [P35].
- Gateway 1: Procurement strategy approval stage for Lot A [P10] [P58].
- Gateway 2: Contract award approval stage [P29] [P30].