AI summarySouthwark Cabinet adopted a revised mandate to market Walworth Town Hall for an Arts and Culture D1 use and is investigating a new local Newington Library location [D] [P1] [P2]. No immediate resource implications are identified [P73].
What happens nextAppoint specialist marketing advisers [P43]Then seek expressions of interest and shortlist candidates [P39]
Who it affectsNot stated
What was decided
Southwark Cabinet adopted the revised project mandate to seek expressions of interest for an Arts and Culture D1 use across Walworth Town Hall, Newington Library and the Cuming building. Report P1, P39, P43
Cabinet noted that accommodation for a new Newington Library within the local area is being investigated. Report P2, P46
The mandate ends further design work for the July 2013 vision, and the NEC3 contract with Faithful + Gould will be terminated without a payment. Report P44, P70
Why
The original council led scheme is no longer viable because projected expenditure increased, council services needed less space and revenue resources were reduced. Report P10, P22, P35, P36
Community consultation supported continued public access and respect for the buildings' heritage, while third party investment is needed to meet regeneration objectives. Report P38
A growing local population needs arts and culture facilities, and Walworth Road currently has no facility of this type. Report P30, P31
What happens next
Appoint specialist marketing advisers through separate Gateway reports and develop the marketing brief with them. Report P39, P43
Run expressions of interest, shortlisting and a detailed Invitation to Tender, with community and Walworth Town Hall forum consultation alongside evaluation and the proposed ward councillor survey feeding leasing decisions. Report P39, P64, P65
Continue seeking a permanent local library location of around 1000sqm, with heritage collection displays envisaged in the new facilities. Report P46, P47
The money
£20m Capital bid approved for the Walworth Town Hall redevelopment Report P8
£26million Construction cost estimate before fees and fit out Report P15
over £36million Total project cost including design fees, surveys, consultants, contingency and fit out Report P16
£10million Additional amount above the capital budget for the community forum proposal Report P20
circa £35,000 per month Current maintenance and monitoring expenditure for the town hall and library Report P23
Options considered
Chosen: Revised market led Arts and Culture D1 mandate. Third party investment may support public access, heritage and regeneration objectives. Report P38, P39
Rejected: Original council led redevelopment scheme. The scheme was no longer viable because of costs, reduced service requirements and constrained revenue budgets. Report P10, P17, P22, P35, P36
Rejected: Community forum phased scheme with east wing commercial lease. It still required an additional £10million than allocated in the capital budget. Report P20
Rejected: Lottery funding towards the project shortfall. It had only limited potential and significant council capital funds would still be needed. Report P17
Chosen: Two year meanwhile lease with the Art Academy. The lease is being finalised and the arts facility was envisaged to open in August. Report P24
Chosen: Investigate alternative local Newington Library accommodation. Returning the library to Walworth Town Hall is no longer feasible. Report P46
Chosen: Keep Registrars services at 34 Peckham Road. Combining ceremonies with other functions was costly and difficult for customers. Report P83, P84
Chosen: Continue funding maintenance until a long term solution is agreed. The council has no option but to continue funding maintenance while the buildings' future use is resolved. Report P23, P35
Implications
Financial: Marketing and leasing use existing Regeneration North budgets, with no immediate resource implications. Any additional funding requirement will need separate Cabinet approval. Report P61, P62, P73
Legal: Redevelopment must respect and enhance the Grade 2 listed buildings and meet Southwark conservation policies and Historic England requirements. Report P13
Legal: The Southwark Plan protects the D1 designation to support a range of community uses and diverse local needs. Report P49, P50
Legal: Consultation must occur at a formative stage, be meaningful and allow sufficient time, and its outcome must be considered. Report P69
Risk: The buildings' condition, age and historic importance create a significant risk that project costs escalate further. Report P33, P34
Risk: 24/7 security remains necessary under the council's insurance requirements, including during the Art Academy's interim lease. Report P23, P24
Staffing: Officer time for procurement and related staffing costs can be contained within existing revenue budgets. Report P61, P74
Equalities: The selection process must consider the diverse community's needs, including age and ethnicity, under the Public Sector Equality Duty. Report P59, P68
Who and where
Arts and cultural organisations seeking to use the buildings Report P39
People seeking public access to the town hall complex Report P41
Library users and people viewing the heritage collection Report P46, P47
Local businesses on Walworth Road Report P31
The council's libraries, heritage and registrars services Report P21, P83
The community and Walworth Town Hall forum Report P64
Faithful + Gould Report P44, P70
Art Academy Report P24
Timeline
25 March 2013: A major fire caused significant structural damage to Walworth Town Hall. Report P4
July 2013: Cabinet approved the high level vision for the future use of the building. Report P6
March 2014: Cabinet approved a capital bid for the Walworth Town Hall redevelopment. Report P8
beginning of 2016: The council suspended the design process as projected expenditure increased. Report P10
March 2016: The council consulted the community and received 112 online responses and 28 comments from Walworth Community Council. Report P18
8 June 2017: The final report was dated. Report P91
August: Opening of the Art Academy arts facility was envisaged, subject to completion of the lease. Report P24
December 2018: The lease for the temporary Newington Library in the Artworks scheme was due to end. Report P46
Plain English for the jargon
D1: The use class for the proposed Arts and Cultural use of the buildings [P39]
Expressions of Interest: The first stage for testing interest from arts and cultural organisations [P39]
Invitation to Tender: The second stage for detailed proposals after candidates are shortlisted [P39]
RIBA stage 2: The design stage completed before the council suspended the design process [P10]
Gateway report: A separate report required to approve the appointment of specialist advisers [P43]
Public Sector Equality Duty: The Equality Act 2010 duty to eliminate prohibited conduct and advance equality of opportunity [P68]
Meanwhile use: Temporary use of Newington Library by the Art Academy while a longer term solution is developed [P24]
NEC3 Professional Services Contract: The council's contract with Faithful + Gould as lead consultant, which will be terminated [P44] [P70]
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item12
Resolved
That the revised project mandate (Appendix 1) for Walworth Town Hall as outlined in paragraphs 31-36 of the report to seek expressions of interest from the market for an Arts and Culture D1 use be adopted. 2. That it be noted that accommodation is being investigated for a new Newington Library within the local area.
Word for word from the decision Southwark published for this meeting.Source: moderngov.southwark.gov.uk
Report to Cabinet (decommissioned, for the Executive after, 12 pages
Recommendations
1. That the revised project mandate (Appendix 1) for Walworth Town Hall as outlined in paragraphs 31-36 to seek expressions of interest from the market for an Arts and Culture D1 use be adopted.
2. Note that accommodation is being investigated for a new Newington Library within the local area.
1 BACKGROUND INFORMATION
3. At 12.30pm on 25 March 2013 the Grade 2 listed Walworth Town Hall (WTH) suffered a major fire. The town hall comprised the Walworth one stop shop, the Cuming museum, the council chamber and offices. Initial survey assessment of damage following the 48 hour operation by the fire brigade required to extinguish the fire concluded that there had been significant structural damage to the buildings roof and to the council chamber and museum galleries.
4. Since the fire an extensive programme of remedial works and surveys have been undertaken to secure the damaged town hall building and to protect the structure. As an initial phase of refurbishment the west wing roof was reinstated and a temporary roof was erected over the council chamber and east wing to keep the building weather tight.
5. In July 2013 cabinet approved a high level vision for the Walworth Town Hall which was subsequently supported by the community through a consultation process. The vision included the following key priorities for the future use of the building;
An enhanced Library space A space for the display of the Cuming collection and potentially a Southwark museum A flexible space that could be used for a variety of purposes including community and civic events, exhibitions and performances Facilities for marriage, civil partnership and citizenship ceremonies undertaken by the Southwark registrar’s service.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Cabinet (decommissioned, for the Executive after at Southwark and we tell you when its next papers are published, before the meeting rather than after it.
Review of Void Disposal StrategyThat the progress of disposals of void housing properties since April 2009 be noted. 2. That the importance of void d...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.