Gateway 0: Consideration of options for broadband in Rotherhithe
ApprovedExecutive1 paper
AI summarySouthwark Cabinet approved the broadband options assessment for Rotherhithe and Surrey Docks and noted formal market engagement to inform the procurement route. [D] [P3] [P78] Initial legal adviser costs will come from existing budgets, with further revenue and capital costs likely to be identified later. [P104] [P109] [P110]
Written from the decision and the officer reportPDF Pro
OutcomeApprovedIt covers broadband infrastructure in Rotherhithe and Surrey Docks wards. [P2]
MoneyNot stated
What happens nextFormal market engagement recommended [D] [P3]It will inform the solution, specification and procurement route. [P78]
Who it affectsRotherhithe and Surrey Docks [P2]Residents, businesses and the council may gain better connectivity. [P35] [P44]
What was decided
Cabinet approved the strategic options assessment for broadband infrastructure in Rotherhithe and Surrey Docks wards. Report P2
Cabinet noted the recommendation to undertake a formal market engagement exercise. Report P3
The Gateway 0 decision was classified as a key decision. Report P75
Why
Broadband access remained poor, with 26% of the Rotherhithe peninsula unable to receive 10Mbps in 2017, against a Government target of 95% access to fast broadband by the end of 2017. Report P12
The area lacked physical fibre infrastructure, and low density housing made major investment commercially unviable for market leaders. Report P23, P26
The council needed to understand a fast changing market and identify a sustainable, future proof approach before choosing a procurement strategy. Report P27, P44, P45
What happens next
Commission a procurement subject matter expert to advise throughout the process under the existing LBLA legal adviser framework, subject to a separate GW1 report. Report P55, P77
Undertake early formal market engagement to test a full Smart City approach or a service in-fill approach, clarify the solution, specification and procurement route, and include community, economic, social and environmental appraisal in the options assessment. Report P78, P80, P84, P86, P88
Prepare a Gateway 1 procurement strategy report, anticipated in autumn 2017. Report P78
The money
more than £10m Contracts with an estimated value above this threshold require a procurement planning report. Report P106
more than £1 billion Government digital infrastructure investment was planned by 2020-21. Report P30
£740 million National Productivity Investment Fund support for full fibre connections and future 5G communications. Report P30
£400 million Digital Infrastructure Investment Fund support for new fibre networks over the next four years, at least matched by private finance. Report P30
Options considered
Chosen: Use formal market engagement before procurement. It will identify bidders or solutions, build market capacity and inform procurement and contract design. Report P57, P58
Chosen: Test a full Smart City strategic approach during market engagement. This will establish market appetite for a full strategic approach, with Digital Greenwich given as an example. Report P37, P68
Chosen: Test a service in-fill approach during market engagement. This will establish whether a baseline service can cover most of the geography. Report P37, P68
Implications
Financial: There are no financial implications at this point beyond initial external legal adviser costs, which will come from existing budgets. Report P104
Financial: The recommended solution is likely to affect the capital programme, later reports are expected to identify additional revenue and capital costs, and the council aims to seek government, private market or other part funding. Report P93, P95, P110
Legal: Procurement must comply with European Commission state aid and competition rules, supported by external legal assistance and oversight. Report P42, P55, P90
Legal: Potential contracts valued at more than £10m require a procurement planning report, while changes to the Electronics Code increase landlords' and landowners' responsibility to provide telecommunications access. Report P51, P106
Equalities: People unable to receive 10Mbps are at risk of falling further behind, and a community impact assessment will form part of the options appraisal because the solution will directly affect residents and businesses. Report P12, P35, P80
Climate: Environmental and sustainability considerations will be built into the options appraisal and reported in the Gateway 1 report. Report P88
Risk: Failure to act comprehensively could widen community gaps, lose opportunities and leave Fairer Future promises unmet, while insufficient market interest could leave the available options unaffordable. Report P71, P72, P73
Other: The recommended route should align with the council's digital policies, a Smart City approach may require a new policy framework, and wider social, economic and environmental benefits must be considered under the Public Services (Social Value) Act 2012. Report P64, P65, P82
Who and where
Residents of Rotherhithe and Surrey Docks Report P2, P8
Residents and businesses in other low connectivity areas, for possible wider application Report P39
Potential broadband suppliers and bidders Report P58, P59
Community members and local pressure groups Report P97
Timeline
8 June 2017: The final report was dated. Report P131
July: Publication of the Prior Information Notice was scheduled for 4 weeks. Report P59, P62
August/September: Market engagement was scheduled for 6 to 8 weeks. Report P62
September: Analysis and report writing were scheduled for 4 weeks. Report P62
31 October 2017: A strategic procurement route proposal and Gateway 1 were scheduled. Report P62
autumn 2017: The Gateway 1 report was anticipated. Report P78
2026-05-28: Cabinet made the Gateway 0 decision. Report P75
Plain English for the jargon
Mbps: Megabits per second, a measure of data transfer speed. [P8]
Superfast broadband: The Government defines it as speeds greater than 24Mbps, while Ofcom uses greater than 30Mbps. [P8]
Market engagement: A process before procurement that identifies bidders or solutions, builds market capacity, and informs procurement and contract design. [P57] [P58]
Prior information notice: A published notice that lets potential suppliers express interest before formal engagement. [P59]
Gateway 0 and Gateway 1: Gateway 0 approves strategic options, while Gateway 1 approves the procurement strategy. [P2] [P78]
Service in-fill: A possible approach to bring a baseline service to most of the geography, set against a full Smart City approach. [P37] [P68]
Smart City approach: A possible full strategic approach to broadband delivery, with Digital Greenwich given as an example. [P37] [P68]
Social value: Wider social, economic and environmental benefits that the council seeks to secure through procurement. [P82]
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item9
Resolved
That the strategic options assessment for delivery of broadband infrastructure in Rotherhithe and Surrey Docks wards for Southwark Council be approved. 2. That the recommendation to undertake a formal market engagement exercise as set out in the report (at paragraphs 26, 56 and 57) be noted.
Word for word from the decision Southwark published for this meeting.Source: moderngov.southwark.gov.uk
Report to Cabinet (decommissioned, for the Executive after, 13 pages
Recommendations
That the Cabinet
1. Approves the strategic options assessment for delivery of broadband infrastructure in Rotherhithe and Surrey Docks wards for Southwark Council.
2. Notes the recommendation to undertake a formal market engagement exercise as set out in the report (paragraphs 26, 56 and 57).
BACKGROUND INFORMATION
3. Southwark Council is committed to being a digitally inclusive borough and has made promises through the Fairer Future principles to bring superfast broadband to Rotherhithe. Access to high speed broadband is an important part of our Fairer Future promise to build a strong local economy for everyone, by ensuring that all residents have access to the digital tools they need to live and work. This is further emphasised through the Economic Wellbeing Strategy, the Digital Strategy and the council’s Modernisation programme. Access to good internet connections is no longer a luxury; it is a necessity for individuals, businesses and the council alike.
4. The council’s aspiration is also in line with the recent Government Digital Strategy (1 March 2017) setting out an ambitious agenda;
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Councillor Richard LivingstoneCommittee Member, present
VM
Councillor Victoria MillsCommittee Member, present
JS
Councillor Johnson SituCommittee Member, present
IW
Councillor Ian WingfieldCommittee Member, present
MW
Councillor Mark WilliamsCommittee Member, present
EK
Eleanor KellyOfficer, expected
DF
Doreen Forrester-BrownOfficer, expected
TM
Tony ManwaringCouncil Staff, expected
Hear about the next one first
Follow Cabinet (decommissioned, for the Executive after at Southwark and we tell you when its next papers are published, before the meeting rather than after it.
Review of Void Disposal StrategyThat the progress of disposals of void housing properties since April 2009 be noted. 2. That the importance of void d...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.