Appropriation of Land, 1 - 3 Odessa Street, Rotherhithe
ApprovedExecutive3 papers
AI summaryLondon Borough of Southwark approved appropriating council owned land at 1 to 3 Odessa Street for planning, to facilitate the consented regeneration scheme [D] [P5]. Hollybrook underwrites compensation claims, although liability remains with the council [P21].
Written from the decision and the officer reportPDF Pro
OutcomeApprovedLand is no longer required for children’s and adults’ services [P2]
MoneyNo financial implications [P33]Hollybrook underwrites claims; council retains liability [P21]
What happens nextEnable development, with compensation available [P19]After appropriation, rights holders cannot seek an injunction [P19]
Who it affectsNot stated
What was decided
London Borough of Southwark confirmed the land is no longer required for children’s and adults’ services and approved appropriating it for planning purposes under section 122(1) of the Local Government Act 1972 [D] [P2]. Report P2
The approval is intended to facilitate development proposals for the area under section 226 of the Town and Country Planning Act 1990 [P2]. Report P2
Why
The sale contract required the council to appropriate the land after planning permission, subject to Cabinet authority and an indemnity from Hollybrook for compensation costs [P13]. Report P13
Nearby owners may claim loss of light, and an injunction could delay the scheme, create uncertainty or frustrate it [P15]. Report P15
The public interest in a longer Thames Path, new housing, commercial facilities and river focused public realm was judged to outweigh interference with private rights [P27]. Report P27
What happens next
Proceed with the approved appropriation so the development can proceed with greater certainty [P5] [P19] [P24]. Report P5, P19, P24
Complete the freehold transfer to Hollybrook under the sale decision made on 9 December 2014. The covenant release had been agreed and planning consent had been granted [P4] [P5]. Report P4, P5
Any compensation claim is based on the loss in value of the affected property. If the parties cannot agree, the Upper Tribunal (Lands Chamber) determines the compensation [P20]. Report P20
Options considered
Chosen: Appropriate the land for planning purposes. It meets the contractual obligation and reduces the risk that an injunction will delay or frustrate the development [P13] [P24]. Report P13, P24
Implications
Legal: Third party rights can be overridden. Affected owners retain a claim for compensation but cannot seek an injunction to delay or terminate development [P19] [P27]. Report P19, P27
Financial: Both service and planning purposes fall within the General Fund, so appropriation itself has no financial implications. The council remains liable for compensation, but Hollybrook’s indemnity underwrites the claims and related costs, so no adverse financial consequences are expected [P21] [P33] [P34]. Report P21, P33, P34
Risk: Nearby owners may claim loss of light. Without appropriation, an injunction could delay the scheme, create uncertainty or frustrate it [P15] [P24]. Report P15, P24
Legal: Under section 203 of the Housing and Planning Act 2016, building or maintenance work may proceed despite interference with a relevant right or interest, subject to the stated conditions [P43]. Report P43
Legal: The report considers human rights and proportionality, and judges the public interest in the Thames Path, housing, commercial facilities and public realm to outweigh interference with private rights [P27]. Report P27
Equalities: The report finds no disproportionately adverse effects on any sector of society from the recommendation [P32]. Report P32
Other: The scheme would lengthen and improve the Thames Path, remove a closed nightclub, a vacant building and a crane, and add housing, commercial facilities and river focused public realm [P26]. Report P26
Legal: Appropriation notices were published in Southwark News on 9 March 2017 and 16 March 2017. No objections were received [P47]. Report P47
Who and where
Hollybrook, as the developer and intended recipient of the land [P4] [P13] [P19] Report P4, P13, P19
Nearby residents and owners who may experience loss of light [P15] Report P15
Holders of rights over the land that are not registered with the Land Registry, including rights to light [P19] Report P19
Southwark Council, as landowner and compensation liability holder [P21] [P39] Report P21, P39
Children’s and adults’ service functions, for which the land was held [P16] Report P16
The community and Thames Path users, who may gain from the improved path and public realm [P26] Report P26
Timeline
9 December 2014: Cabinet approved the freehold land transfer to Hollybrook, subject to covenant release and planning consent [P4]. Report P4
8 November 2016: Planning Committee resolved to grant consent for a restaurant and residential accommodation above [P5]. Report P5
9 March 2017: The first appropriation notice was published in Southwark News [P47]. Report P47
16 March 2017: The second appropriation notice was published in Southwark News [P47]. Report P47
28 March 2017: Planning consent was granted for the regeneration scheme [P5]. Report P5
5 June 2017: The final report was dated and sent to the Constitutional Team [P55]. Report P55
2026-05-28: Southwark confirmed the land was no longer needed and approved its appropriation for planning purposes [D].
Plain English for the jargon
Appropriation: Changing the purpose for which a council holds land. It can override third party rights, leaving compensation instead of an injunction [P18] [P19].
Planning purposes: Statutory purposes allowing a council to acquire land for development, redevelopment or improvement [P41] [P42].
Public Sector Equality Duty: The duty to eliminate discrimination, advance equality of opportunity and foster good relations [P28] [P29].
Right to light: A private right over land that nearby owners may hold. The scheme could affect it, but compensation is available after appropriation [P15] [P19].
Injunction: A court action used to stop or delay development. After appropriation, a rights holder cannot seek one to delay or terminate the work [P19].
Indemnity: Hollybrook’s contractual promise to cover the council’s costs for compensation claims [P13] [P21].
General Fund: The council fund within which both children’s and adults’ services and planning purposes fall [P33].
Upper Tribunal (Lands Chamber): The body that determines compensation if affected parties cannot agree [P20].
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item14
Resolved
That that the land shown hatched on the plan at Appendix A of the report that is currently held for children’s and adults services purposes service purposes be confirmed as no longer required for those purposes, and the appropriation of the land to planning purposes in accordance with section 122(1) of the Local Government Act 1972 to facilitate the carrying out of the development proposals for the area in accordance with section 226 of the Town and Country Planning Act 1990 be approved.
Word for word from the decision Southwark published for this meeting.Source: moderngov.southwark.gov.uk
Report to Cabinet (decommissioned, for the Executive after, 7 pages
Recommendation
That Cabinet:
1. confirms that the land shown hatched on the plan at Appendix A that is currently held for children’s and adults services purposes service purposes is no longer required for those purposes and approves the appropriation of the land to planning purposes in accordance with section 122(1) of the Local Government Act 1972 to facilitate the carrying out of the development proposals for the area in accordance with section 226 of the Town and Country Planning Act 1990.
1 BACKGROUND INFORMATION
2. On 9 December 2014 cabinet approved that this council-owned freehold property shown hatched on the plan at Appendix A be transferred to Hollybrook Homes once a restrictive covenant has been released affecting the land and planning consent had been secured for its regeneration.
3. Agreement was subsequently reached with the Greater London Authority for the lifting of the aforementioned covenant. On 8 November 2016 planning committee resolved to grant planning consent for the regeneration of the land with a restaurant and residential accommodation above. Following English Heritage’s decision not to list the crane that is currently on the land, planning consent was granted for the scheme on 28 March 2017. The proposed regeneration is therefore nearing to be able to commence.
4. The rationale for the December 2014 cabinet resolution was:
Removal of an obstruction to extend the Thames Path
New river oriented public realm
Removal of a nightclub that had in the past been the source of complaints
Removal of a health and safety hazard namely the crane
Provision of new housing
New commercial space.
5. The sale contract with Hollybrook plc contains an obligation on the council that following grant of planning permission it is to appropriate the land for planning purposes subject to obtaining the necessary authority (from Cabinet) to do so and subject to an indemnity from Hollybrook in respect of the cost of any compensation payable as a result.
KEY ISSUES FOR CONSIDERATION
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Cabinet (decommissioned, for the Executive after at Southwark and we tell you when its next papers are published, before the meeting rather than after it.
Review of Void Disposal StrategyThat the progress of disposals of void housing properties since April 2009 be noted. 2. That the importance of void d...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.