Cabinet (decommissioned, for the Executive after, Thursday 28 May 2026 at 4.00pm

Gateway 1: Procurement Strategy Approval - Southwark External Solicitors Framework

Approved Executive 2 papers

AI summarySouthwark Cabinet approved the procurement strategy for a 4 year external solicitors framework from 2 July 2018. Southwark's estimated cost is £9 million, and the framework's estimated overall value is £18 million to £25 million. [D]

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApproved4 year external solicitors framework from 2 July 2018 [D]
Money£9 million for Southwark [D]Estimated overall value: £18 million to £25 million [D]
What happens nextStarts 2 July 2018 [D]The approved strategy covers 4 years [D]
Who it affectsAffected London organisations [D]Boroughs, their companies, fire service and clinical groups [D]

What was decided

Southwark Cabinet approved the procurement strategy for a 4 year external solicitors framework from 2 July 2018, with an estimated cost to Southwark of £9 million.

The framework will serve Southwark, other London boroughs and their wholly owned companies, the London fires and rescue service, and Clinical Commissioning Groups in London.

Southwark noted an estimated overall framework value of £18 million to £25 million for all participating organisations, including Southwark, for the 4 year period.

Why

External support is needed because specialist work or capacity gaps mean in house lawyers cannot meet all legal needs. Report P6

What happens next

The external solicitors framework period commences on 2 July 2018.

The money

  • £9 million Estimated cost for Southwark for the 4 year period
  • £18 million to £25 million Estimated overall framework value for all participating organisations, including Southwark, for the 4 year period

Implications

  • Financial: Southwark's estimated cost for the 4 year period is £9 million.
  • Financial: The estimated overall framework value for all participating organisations is £18 million to £25 million for the 4 year period.
  • Other: The framework covers Southwark, other London boroughs and their wholly owned companies, the London fires and rescue service, and Clinical Commissioning Groups in London.

Who and where

  • Southwark
  • Other London boroughs and their wholly owned companies
  • London fires and rescue service
  • Clinical Commissioning Groups in London

Timeline

  • 2 July 2018: The external solicitors framework starts its 4 year period.

Plain English for the jargon

  • Clinical Commissioning Groups (CCGs): London organisations included in the framework. [D]
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item15

Resolved

That the procurement strategy outlined in the report for an external solicitors framework serving Southwark and other London boroughs and their wholly owned companies, London fires and rescue service and Clinical Commissioning Groups (CCGs) in London for a period of 4 years commencing 2 July 2018 at an estimated cost (for Southwark) of £9 million for the 4 year period be approved. 2. That the overall value of the framework agreement is estimated to be in the range of £18 million to £25 million for all participating organisations (including Southwark) for the 4 year period be noted.
Word for word from the decision Southwark published for this meeting. Source: moderngov.southwark.gov.uk

Follow this further

Built from Southwark's papers

What the report saysPro

Report to Cabinet (decommissioned, for the Executive after, 7 pages

Recommendations

1.

That the strategic director of finance and governance approves the extension of the use of the London Borough Legal Alliance (LBLA) framework for a period of 12 months from 1 November 2016 for the provision of external legal solicitors’ advice.

That the strategic director of finance and governance notes that there is a yearly fee of £3,300 which will continue to be paid to Kennedy Cater who manage this framework for all LBLA members and framework users. This is a demand led contract with no guarantee of spend but on current spend it is estimated that spend for this extension period will be in the region of £400k.

BACKGROUND INFORMATION

3.

Legal Services has in-house lawyers but from time to time additional support is required from external solicitors, either because of the specialist nature of the work or due to capacity issues. Under current and future resources it is not possible for all legal needs of the council to be met entirely through the work of Legal Services, and provision is therefore required to have access to external specialists for when the need arises.

In March 2014, the cabinet member for finance, resources and community safety

_ approved the council’s use of the LBLA’s solicitors’ framework for a period of 2

years and 7 months, up to 31 October 2016, which was the remaining period on the LBLA framework. The LBLA framework included provision for extension for a further period of 12 months (from 1 November 2016 to 31 October 2017) and the council has now been notified by LBLA that the extension has been effected with solicitors on the panel. The council therefore has an option of using the framework for a further 12 months.

The framework is used by LBLA members (who are the London Boroughs of Barnet, Brent, Camden, Ealing, Hackney, Haringey, Harrow, Hillingdon, Hounslow, Islington, Waltham Forest, Hammersmith & Fulham, Royal Borough of Kensington & Chelsea, Westminster and the City of London) but can also be used by non LBLA members, such as Southwark .

KEY ISSUES FOR CONSIDERATION

Key Aspects of Proposed Variation

6. Approval of this variation would allow the council to use the LBLA solicitors

framework for a further period of 12 months. The framework is split into two parts — Lot 1: the provision of legal advisory services and assistance in relation to complex

7.

regeneration, development, property and planning work. The following solicitor firms have been appointed to this panel: e = Ashfords Bevan Brittan Freeth Carthwright Sharpe Pritchard LLP TLT

- Lot 2: the provision of legal advisory services and assistance in relation to a range of mainstream legal services including litigation, contracts, procurement, PPP/PFI, property and employment. The following solicitor firms have been appointed to this panel:

Ashfords

Michelmores

Pinsent Masons

Sharpe Pritchard LLP

TLT

There is no obligation.on the council to use the framework or for any level of spend with the solicitors on the panel. Appointments through the framework can either be made by a direct order to any of the providers in the relevant fot, or, can be made following a mini-competition between providers. in that lot as appropriate and determined by the council.

The framework includes a number of soft benefits including training, helpline / ad-hoc advice, secondments, use of library and precedents, cost monitoring and pre and post scheme briefings.

Reasons for Variation

9.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Background document: GW3 external solicitors panel reportReport 7 pages DownloadRead as text
PDF
Report: Gateway 1: Procurement Strategy Approval Southwark External Solicitors’ FrameworkReport 13 pages Download

At this meeting

Whole meeting

Who was there

9 of 12 attended
PJ
Councillor Peter John OBEChair, present
SC
Councillor Stephanie CryanCommittee Member, present
FC
Councillor Fiona ColleyCommittee Member, present
BH
Councillor Barrie HargroveCommittee Member, present
RL
Councillor Richard LivingstoneCommittee Member, present
VM
Councillor Victoria MillsCommittee Member, present
JS
Councillor Johnson SituCommittee Member, present
IW
Councillor Ian WingfieldCommittee Member, present
MW
Councillor Mark WilliamsCommittee Member, present
EK
Eleanor KellyOfficer, expected
DF
Doreen Forrester-BrownOfficer, expected
TM
Tony ManwaringCouncil Staff, expected

On this subject at Southwark

Search all
  1. Gateway 1: Procurement Strategy Approval - Southwark External Solicitors FrameworkThis decision
  2. Gateway 1 – Procurement Strategy Approval -The NestApproved
  3. Gateway 1 - Procurement Strategy Approval - Southwark and Lambeth Barristers FrameworkApproved
  4. Gateway 1 - Procurement Strategy Approval - Framework contracts to provide bailiff services to the Revenues & Benefits and Parking ServicesApproved
  5. Gateway 2: Contract Award Approval - Corporate Insurance Procurement (excluding Property Insurance)Approved
  6. Gateway 1 - Initial Procurement Strategy, Parking and Traffic Enforcement Services ContractAgreed

More from Southwark Cabinet (decommissioned, for the Executive after

All decisions
MeetingDecisionOutcome
28 May 2026 Election of Chair for the meetingThat Councillor Maisie Anderson be elected chair for this meeting. Decided Open
28 May 2026 Notification of any items of business which the chair deems urgentIt was agreed that all the deputations would be heard so that consideration of these representations could be given p... Agreed Open
28 May 2026 Disclosure of Interests and DispensationsDecision Maker (IDM) report in respect of this issue. Councillor Peter John also declared a personal, non prejudicial... Decided Open
28 May 2026 Review of Void Disposal StrategyThat the progress of disposals of void housing properties since April 2009 be noted. 2. That the importance of void d... Noted Open