Gateway 3: Variation Decision - Highways and Professional Services - Extension of Existing Contract
ApprovedExecutive1 paper
AI summaryCabinet approved a maximum two year extension of the Conway Aecom Ltd highways and professional services contract, with a maximum cost of approximately £20m, and delegated the exact period [D]
Written from the decision and the officer reportPDF Pro
OutcomeApprovedMaximum two years from 31 March 2019 [P35]
Moneyapproximately £20m [D]Maximum variation value, with no minimum annual spend [P13][P70]
What happens nextFuture delivery options review [P3]Gateway 0 report, with Gateway 1 before tender [P3][P35]
Who it affectsBoroughwide roads and pavements [P5][P48]Maintenance, inspections, gully cleaning and winter service [P5][P72]
What was decided
Cabinet approved a maximum extension of the contract with Conway Aecom Ltd from expiry on 31 March 2019 until 31 March 2021, at a cost of approximately £20m. Report P35
Approval of the exact extension period, within the two year maximum, was delegated to the Strategic Director for Environment and Social Regeneration. Report P2, P35
A further Gateway 0 report will set out future highways delivery options after the extension. The council intends to use framework agreements with alternative suppliers for scheme works and professional design under a separate governance process. Report P3, P4
Why
The extension is needed to maintain service continuity and the council's statutory duty to keep highways in a safe condition. Renewing the contract in April 2019 was assessed as not giving the best outcome for Southwark. Report P16
The extension allows a full business appraisal of future delivery options. It also gives officers time to assess market activity and choose the best time to tender. Report P18, P35
The current contract retains core services, competitive rates and supplier knowledge. Alternative frameworks will provide contingency if Conway Aecom Ltd's performance falls short. Report P25, P32, P33, P39
What happens next
The Strategic Director will determine the exact extension period within the two year maximum. The Head of Highways must give at least 3 months notice of any extension award before the contract expires. Report P2, P14, P35
Officers will monitor market intelligence, evaluate delivery options and compile tender and contract documentation during 2018. A Gateway 0 report is anticipated for the relevant cabinet member in early Summer 2018. Report P35, P37
A separate Gateway 1 will be issued before tendering begins. Framework agreements with alternative suppliers will be agreed through a separate governance process. Report P4, P35
The money
approximately £20m Maximum cost of the approved contract extension Report P13
approximately £10m per annum Anticipated annual variation value, depending on available budgets Report P13
30% Maximum variation value as a share of the original contract value Report P13
£66m Estimated original contract value over 6 years Report P9
£87m Estimated original contract value over the maximum 8 year period Report P9
around £300k Example cost of a second hand road planing machine, around 5 years old Report P27
Options considered
Chosen: Extend the current contract while assessing future delivery and tender options. It preserves service continuity and allows time to assess delivery models and the best time to tender. Report P16, P18, P32, P35
Rejected: Use the current LoHAC framework. The contract expires in March 2021 with no extension option, future uncertainty, and TUPE and setup costs made it financially unviable. Report P24, P25
Rejected: Bring highway services in house. Large setup costs, restricted buying power, short timescales and TUPE implications made the approach unsuitable. Report P26, P27, P28
Rejected: Retender immediately. It may not provide best value, market conditions may make rates more expensive, and further assessment was needed. Report P29, P30
Rejected: End the existing contract in March 2019 and replace it with another delivery model. The immediate replacement options were each judged not recommended after assessment. Report P22, P25, P28, P30
Implications
Financial: The extension creates no minimum spending commitment. Lot A is funded from the Asset Management revenue budget, Lot B from capital receipts, Local Implementation Plan funding and ad hoc project grants or funds, and Lot C from capital or revenue, mostly recovered through grants or external income. Report P70, P72, P73, P74
Financial: Base costs on Lots A and B use an inflation mechanism with a built in saving. Lot C uses actual costs without indexation, with KPIs to keep inflationary pressure at the market average. Report P71
Risk: Performance has improved following improvement plans, but some KPIs, programme delivery and insurance claims remain concerns. Enhanced monitoring and backup suppliers are in place. Report P10, P11, P39, P43
Legal: The report identifies no legal implications. The Director of Law and Democracy notes that the contract contains express provision for extension. Report P69, P80
Staffing: The report identifies no resource implications. Report P68
Equalities: Continued maintenance especially benefits elderly people, disabled people and young children, and no detrimental local impact was identified. This supports the council's duty to consider effects on the community and protected characteristics. Report P46, P47, P49, P83
Climate: The contract calls for highway maintenance arisings to be recycled and reused where possible, environmental assessments, dust suppression and a 95% target for recycling water and waste from gully cleaning and construction. New fleet must use Euro VI engines, with Euro V the minimum for existing fleet, and the diesel fleet uses 5% bio ethanol. Report P61, P62, P63, P64, P65, P66, P67
Other: The contract is not exclusive, and other frameworks are intended to provide backup if delivery problems arise. It includes local enterprise engagement and a London Living Wage clause. The provider has reconfirmed employment blacklisting compliance and provided apprenticeship opportunities for local people at the beginning of 2018. Report P33, P39, P54, P55, P57, P58, P59
Who and where
All residents and communities across the borough Report P45, P49
Elderly people, disabled people and young children Report P46, P49
Businesses and visitors Report P49
People passing through the borough Report P49
People using footways, roads and cycleways Report P41, P45
Contractor and subcontractor staff Report P55
Local small and medium sized enterprises Report P54
Local people in apprenticeship placements Report P57, P58
Timeline
1 April 2013: The original Highways and Professional Services contract commenced for six years. Report P9
early Spring 2018: Planned start of tender and contract document compilation. Report P37
end of 2018: Anticipated completion of tender and contract documents. Report P37
early Summer 2018: Gateway 0 report anticipated for cabinet member consideration. Report P37
late 2018: TfL decision anticipated on its proposed contracts strategy. Report P29
February 2019: General fund revenue budget for 2019-20 due to be set. Report P86
31 March 2019: Original contract expiry. Report P9
31 March 2021: Maximum extension expiry. Report P35
Plain English for the jargon
HAPS: Southwark's contract, covering Lot A highway maintenance, Lot B project works delivery and Lot C professional services [P7][P8]
LoHAC: The TfL London Highways Alliance Contract, used by some London boroughs [P6]
Gateway 0: A report setting out future highways delivery options for consideration by the relevant cabinet member [P3][P37]
Gateway 1: A separate decision point required before the tender process begins [P35]
KPI: A measure used to assess provider performance and delivery to the required programme [P10][P71]
TUPE: Employment related cost implications considered when services move between delivery arrangements [P25][P26]
LLW: London Living Wage, the minimum hourly rate for contractor, subcontractor, casual and agency staff [P55]
CVU: The joint venture between Colas, Volker Highways and URS, and the Central area supplier under the TfL contract [P23]
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item12
Resolved
That the extension of the Highways and Professional Services (HAPS) contract with Conway Aecom Ltd from its expiry on 31 March 2019 at a cost of approximately £20m for a maximum period of up to two years and as further detailed in paragraph 26 of the report be approved. 2. That the approval of the period of extension (within the 2 year maximum) be delegated to the strategic director for environment and social regeneration. 3. That it be noted that a further Gateway 0 report will be submitted to the relevant cabinet member for consideration setting out the future delivery options for highways services subsequent to this extension. 4. That the intention to provide resilience by entering into framework agreements with alternative suppliers for both scheme works delivery and professional design services, agreed under a separate governance process be noted.
Word for word from the decision Southwark published for this meeting.Source: moderngov.southwark.gov.uk
Report to Cabinet (decommissioned, for the Executive after, 13 pages
Recommendations
1. That the Cabinet approve the extension of the Highways and Professional Services (HAPS) contract with Conway Aecom Ltd from its expiry on 31 March 2019 at a cost of approximately £20m for a maximum period (subject to recommendation 2) of up to two years and as further detailed in paragraph 26.
2. That Cabinet delegates the approval of the period of extension (within the 2 year maximum) to the strategic director for environment and social regeneration.
3. That the Cabinet note that a further Gateway 0 report will be submitted to the relevant cabinet member for consideration setting out the future delivery options for highways services subsequent to this extension.
4. The Cabinet notes the intention to provide resilience by entering into framework agreements with alternative suppliers for both scheme works delivery and professional design services, agreed under a separate governance process. BACKGROUND INFORMATION
5. Under the Highways Act 1980 the council, as Highway Authority for most of the public roads and pavements within the borough, has a statutory responsibility to ensure those public highways are maintained to a safe standard. This will cover everything from a standard “pothole” repair to gritting the roads and pavements deemed necessary during freezing conditions and snowfall. In addition to these statutory duties the council also has a responsibility to endeavour to improve the highway network where possible. This is carried out using capital funding which can be from Southwark’s own budgets or from external partners such as Transport for London (TfL) or through developers’ S106 / Community Infrastructure Levy (CIL) funds.
6. Most London boroughs generally deliver highways services through individual service providers on contracts similar to the current HAPS contract. Some of the London boroughs have signed up to the TfL London Highways Alliance Contract (LoHAC) to deliver their services. The LoHAC contracts expire on 31 March 2021 with no option for extension. One London borough – Hounslow – delivers its service through a PFI contract. The highways maintenance, highways improvements and highways professional services market is very competitive throughout the UK. This is even more so in London due to the close proximity of 34 different highway authorities (32 London Boroughs + City of London + Transport for London) and a number of major development sites that require roads, pavements, cycleways, open spaces etc.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Cabinet (decommissioned, for the Executive after at Southwark and we tell you when its next papers are published, before the meeting rather than after it.
Review of Void Disposal StrategyThat the progress of disposals of void housing properties since April 2009 be noted. 2. That the importance of void d...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.