Gateway 3: Variation Decision - Highways and Professional Services - Extension of Existing Contract

Approved Executive 1 paper

AI summaryCabinet approved a maximum two year extension of the Conway Aecom Ltd highways and professional services contract, with a maximum cost of approximately £20m, and delegated the exact period [D]

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedMaximum two years from 31 March 2019 [P35]
Moneyapproximately £20m [D]Maximum variation value, with no minimum annual spend [P13][P70]
What happens nextFuture delivery options review [P3]Gateway 0 report, with Gateway 1 before tender [P3][P35]
Who it affectsBoroughwide roads and pavements [P5][P48]Maintenance, inspections, gully cleaning and winter service [P5][P72]

What was decided

Cabinet approved a maximum extension of the contract with Conway Aecom Ltd from expiry on 31 March 2019 until 31 March 2021, at a cost of approximately £20m. Report P35

Approval of the exact extension period, within the two year maximum, was delegated to the Strategic Director for Environment and Social Regeneration. Report P2, P35

A further Gateway 0 report will set out future highways delivery options after the extension. The council intends to use framework agreements with alternative suppliers for scheme works and professional design under a separate governance process. Report P3, P4

Why

The extension is needed to maintain service continuity and the council's statutory duty to keep highways in a safe condition. Renewing the contract in April 2019 was assessed as not giving the best outcome for Southwark. Report P16

The extension allows a full business appraisal of future delivery options. It also gives officers time to assess market activity and choose the best time to tender. Report P18, P35

The current contract retains core services, competitive rates and supplier knowledge. Alternative frameworks will provide contingency if Conway Aecom Ltd's performance falls short. Report P25, P32, P33, P39

What happens next

The Strategic Director will determine the exact extension period within the two year maximum. The Head of Highways must give at least 3 months notice of any extension award before the contract expires. Report P2, P14, P35

Officers will monitor market intelligence, evaluate delivery options and compile tender and contract documentation during 2018. A Gateway 0 report is anticipated for the relevant cabinet member in early Summer 2018. Report P35, P37

A separate Gateway 1 will be issued before tendering begins. Framework agreements with alternative suppliers will be agreed through a separate governance process. Report P4, P35

The money

  • approximately £20m Maximum cost of the approved contract extension Report P13
  • approximately £10m per annum Anticipated annual variation value, depending on available budgets Report P13
  • 30% Maximum variation value as a share of the original contract value Report P13
  • £66m Estimated original contract value over 6 years Report P9
  • £87m Estimated original contract value over the maximum 8 year period Report P9
  • around £300k Example cost of a second hand road planing machine, around 5 years old Report P27

Options considered

  • Chosen: Extend the current contract while assessing future delivery and tender options. It preserves service continuity and allows time to assess delivery models and the best time to tender. Report P16, P18, P32, P35
  • Rejected: Use the current LoHAC framework. The contract expires in March 2021 with no extension option, future uncertainty, and TUPE and setup costs made it financially unviable. Report P24, P25
  • Rejected: Bring highway services in house. Large setup costs, restricted buying power, short timescales and TUPE implications made the approach unsuitable. Report P26, P27, P28
  • Rejected: Retender immediately. It may not provide best value, market conditions may make rates more expensive, and further assessment was needed. Report P29, P30
  • Rejected: End the existing contract in March 2019 and replace it with another delivery model. The immediate replacement options were each judged not recommended after assessment. Report P22, P25, P28, P30

Implications

  • Financial: The extension creates no minimum spending commitment. Lot A is funded from the Asset Management revenue budget, Lot B from capital receipts, Local Implementation Plan funding and ad hoc project grants or funds, and Lot C from capital or revenue, mostly recovered through grants or external income. Report P70, P72, P73, P74
  • Financial: Base costs on Lots A and B use an inflation mechanism with a built in saving. Lot C uses actual costs without indexation, with KPIs to keep inflationary pressure at the market average. Report P71
  • Risk: Performance has improved following improvement plans, but some KPIs, programme delivery and insurance claims remain concerns. Enhanced monitoring and backup suppliers are in place. Report P10, P11, P39, P43
  • Legal: The report identifies no legal implications. The Director of Law and Democracy notes that the contract contains express provision for extension. Report P69, P80
  • Staffing: The report identifies no resource implications. Report P68
  • Equalities: Continued maintenance especially benefits elderly people, disabled people and young children, and no detrimental local impact was identified. This supports the council's duty to consider effects on the community and protected characteristics. Report P46, P47, P49, P83
  • Climate: The contract calls for highway maintenance arisings to be recycled and reused where possible, environmental assessments, dust suppression and a 95% target for recycling water and waste from gully cleaning and construction. New fleet must use Euro VI engines, with Euro V the minimum for existing fleet, and the diesel fleet uses 5% bio ethanol. Report P61, P62, P63, P64, P65, P66, P67
  • Other: The contract is not exclusive, and other frameworks are intended to provide backup if delivery problems arise. It includes local enterprise engagement and a London Living Wage clause. The provider has reconfirmed employment blacklisting compliance and provided apprenticeship opportunities for local people at the beginning of 2018. Report P33, P39, P54, P55, P57, P58, P59

Who and where

  • All residents and communities across the borough Report P45, P49
  • Elderly people, disabled people and young children Report P46, P49
  • Businesses and visitors Report P49
  • People passing through the borough Report P49
  • People using footways, roads and cycleways Report P41, P45
  • Contractor and subcontractor staff Report P55
  • Local small and medium sized enterprises Report P54
  • Local people in apprenticeship placements Report P57, P58

Timeline

  • 1 April 2013: The original Highways and Professional Services contract commenced for six years. Report P9
  • early Spring 2018: Planned start of tender and contract document compilation. Report P37
  • end of 2018: Anticipated completion of tender and contract documents. Report P37
  • early Summer 2018: Gateway 0 report anticipated for cabinet member consideration. Report P37
  • late 2018: TfL decision anticipated on its proposed contracts strategy. Report P29
  • February 2019: General fund revenue budget for 2019-20 due to be set. Report P86
  • 31 March 2019: Original contract expiry. Report P9
  • 31 March 2021: Maximum extension expiry. Report P35

Plain English for the jargon

  • HAPS: Southwark's contract, covering Lot A highway maintenance, Lot B project works delivery and Lot C professional services [P7][P8]
  • LoHAC: The TfL London Highways Alliance Contract, used by some London boroughs [P6]
  • Gateway 0: A report setting out future highways delivery options for consideration by the relevant cabinet member [P3][P37]
  • Gateway 1: A separate decision point required before the tender process begins [P35]
  • KPI: A measure used to assess provider performance and delivery to the required programme [P10][P71]
  • TUPE: Employment related cost implications considered when services move between delivery arrangements [P25][P26]
  • LLW: London Living Wage, the minimum hourly rate for contractor, subcontractor, casual and agency staff [P55]
  • CVU: The joint venture between Colas, Volker Highways and URS, and the Central area supplier under the TfL contract [P23]
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item12

Resolved

That the extension of the Highways and Professional Services (HAPS) contract with Conway Aecom Ltd from its expiry on 31 March 2019 at a cost of approximately £20m for a maximum period of up to two years and as further detailed in paragraph 26 of the report be approved. 2. That the approval of the period of extension (within the 2 year maximum) be delegated to the strategic director for environment and social regeneration. 3. That it be noted that a further Gateway 0 report will be submitted to the relevant cabinet member for consideration setting out the future delivery options for highways services subsequent to this extension. 4. That the intention to provide resilience by entering into framework agreements with alternative suppliers for both scheme works delivery and professional design services, agreed under a separate governance process be noted.
Word for word from the decision Southwark published for this meeting. Source: moderngov.southwark.gov.uk

Follow this further

Built from Southwark's papers

What the report saysPro

Report to Cabinet (decommissioned, for the Executive after, 13 pages

Recommendations

1. That the Cabinet approve the extension of the Highways and Professional Services (HAPS) contract with Conway Aecom Ltd from its expiry on 31 March 2019 at a cost of approximately £20m for a maximum period (subject to recommendation 2) of up to two years and as further detailed in paragraph 26.

2. That Cabinet delegates the approval of the period of extension (within the 2 year maximum) to the strategic director for environment and social regeneration.

3. That the Cabinet note that a further Gateway 0 report will be submitted to the relevant cabinet member for consideration setting out the future delivery options for highways services subsequent to this extension.

4. The Cabinet notes the intention to provide resilience by entering into framework agreements with alternative suppliers for both scheme works delivery and professional design services, agreed under a separate governance process. BACKGROUND INFORMATION

5. Under the Highways Act 1980 the council, as Highway Authority for most of the public roads and pavements within the borough, has a statutory responsibility to ensure those public highways are maintained to a safe standard. This will cover everything from a standard “pothole” repair to gritting the roads and pavements deemed necessary during freezing conditions and snowfall. In addition to these statutory duties the council also has a responsibility to endeavour to improve the highway network where possible. This is carried out using capital funding which can be from Southwark’s own budgets or from external partners such as Transport for London (TfL) or through developers’ S106 / Community Infrastructure Levy (CIL) funds.

6. Most London boroughs generally deliver highways services through individual service providers on contracts similar to the current HAPS contract. Some of the London boroughs have signed up to the TfL London Highways Alliance Contract (LoHAC) to deliver their services. The LoHAC contracts expire on 31 March 2021 with no option for extension. One London borough – Hounslow – delivers its service through a PFI contract. The highways maintenance, highways improvements and highways professional services market is very competitive throughout the UK. This is even more so in London due to the close proximity of 34 different highway authorities (32 London Boroughs + City of London + Transport for London) and a number of major development sites that require roads, pavements, cycleways, open spaces etc.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Report: Gateway 3: Variation Decision Highways and Professional Services: Extension of existing contractDecisions 13 pages DownloadRead as text

At this meeting

Whole meeting
3Notice of Intention to conduct business in a closed meeting, and any representations receivedOn the agenda 6MinutesApproved 8Petition from Metropolitan Tabernacle Church, Elephant and Castle - Parking issuesOn the agenda 9Response to Deputation Request from local residents in respect of CPZ Zone L - Northern end of Grove Lane, SE5Noted 10Feedback from Southwark ConversationNoted 11Suicide Prevention Strategy and Action Plan 2017-2022Approved
12Gateway 3: Variation Decision - Highways and Professional Services - Extension of Existing ContractThis decision
13Progress report - in-house repairs serviceNoted 14Council Plan Interim Performance Report 2014-15 to 2017-18Noted 15Gateway 0: Nursing Care Strategic Options AssessmentApproved 16Gateway 1: Procurement Strategy Approval - Care at Home and Community for Children and Young People with Special Educational Needs and Disabilities (SEND)Approved 17Southwark School Design GuidelinesApproved 18Gateway 1: Procurement Strategy Approval Abbeyfield Estate HINE (Maydew House) WorksApproved 19Joseph Lancaster Estate, Deverell Street, SE1 - Grant of Long Lease and Housing Funding AgreementNoted 20Gateway 0: Facilities Management Contract for the Council's Operational EstateApproved 21Gateway 2: Contract Award Approval - Door Entry and Warden Call ContractApproved 22Gateway 2: Contract Award Approval - Communal Lighting and Electrical Testing Contracts - Contract A: North of the Borough and Contract B: South of the BoroughApproved 23Canada Water Development AgreementAgreed 24Air Rights above 2-68 and 70-136 Chilton Grove, Surrey QuaysApproved 25Bede Centre, Abbeyfield Estate, RotherhitheApproved 26Air-Rights above Damory House, Abbeyfield Estate, RotherhitheApproved 27Maydew House, RotherhitheApproved 28Air-Rights above Thaxted Court, Abbeyfield Estate, RotherhitheApproved 29Proposed Acquisition of Freehold Interest in Office Accommodation 132 Queens Road, London SE15 2HPNoted 30Acquisition of Champion Hill, Edgar Kail Way SE22Approved

Who was there

10 of 13 attended
PJ
Councillor Peter John OBEChair, present
SC
Councillor Stephanie CryanCommittee Member, present
MA
Councillor Maisie AndersonCommittee Member, present
FC
Councillor Fiona ColleyCommittee Member, present
BH
Councillor Barrie HargroveCommittee Member, present
RL
Councillor Richard LivingstoneCommittee Member, present
VM
Councillor Victoria MillsCommittee Member, present
JS
Councillor Johnson SituCommittee Member, present
IW
Councillor Ian WingfieldCommittee Member, present
MW
Councillor Mark WilliamsCommittee Member, present
EK
Eleanor KellyOfficer, expected
DF
Doreen Forrester-BrownOfficer, expected

All 13 on the meeting page

On this subject at Southwark

Search all
  1. Gateway 3: Variation Decision - Highways and Professional Services - Extension of Existing ContractThis decision
  2. Gateway 3 - Variation Decision - Parking and Traffic enforcement and associated services contractApproved
  3. Gateway 3: Variation Decision - Housing Major Works ContractsApproved
  4. Gateway 3: Variation Decision - Extension to the Consolidated Facilities Management ContractApproved
  5. Gateway 3 - Variation Decision: Parks Grounds Maintenance Contract ExtensionApproved

More from Southwark Cabinet (decommissioned, for the Executive after

All decisions
MeetingDecisionOutcome
28 May 2026 Election of Chair for the meetingThat Councillor Maisie Anderson be elected chair for this meeting. Decided Open
28 May 2026 Notification of any items of business which the chair deems urgentIt was agreed that all the deputations would be heard so that consideration of these representations could be given p... Agreed Open
28 May 2026 Disclosure of Interests and DispensationsDecision Maker (IDM) report in respect of this issue. Councillor Peter John also declared a personal, non prejudicial... Decided Open
28 May 2026 Review of Void Disposal StrategyThat the progress of disposals of void housing properties since April 2009 be noted. 2. That the importance of void d... Noted Open
28 May 2026 Housing Revenue Account - Approval of Housing Revenue Budget Account 2011/12That the savings required to deliver a balanced housing revenue account (HRA) for 2011/12 be noted. 2. That the propo... Noted Open