AI summarySouthwark Cabinet noted draft stage dates for Ledbury Estate and requested another report on the July 2018 consultation outcome [D]. Refurbishment options were costed at £13.6m, £18.4m, £23.9m and £27.9m; demolition and replacement of existing 220 homes was costed at £59.9m [P28] [P29] [P30] [P31] [P43].
Cabinet noted the draft dates for the key stages agreed by the Ledbury Project Team. Report P3
Cabinet required a further report on the outcome of the resident options appraisal consultation planned for July 2018. Report P4
Why
A Resident Project Group was established to work with officers on the recommendations from the Arup structural assessment dated 20 November 2017. Report P6
The appraisal covers refurbishment, partial demolition with replacement housing, and full redevelopment, taking account of independent cost work. Report P9
Consultation must remain at a formative stage, give interested parties sufficient reasons and adequate time, and have its outcome considered before the final decision. Report P49
What happens next
The independent consultant is to undertake options appraisal work in May/June 2018. Report P13
The Resident Project Team is to meet in May 2018 and June 2018 to receive an update, agree the consultation format and consider the draft options report. Report P14, P15
A further report will set out the July 2018 consultation outcome. The September/October 2018 Cabinet report will include officers' recommendations, consultation results and the wider impact on Southwark's Housing Strategy. Report P4, P16, P17
The money
£13.6m Option 1: strengthening, permanent gap and crack work, renewed kitchens, bathrooms, basins, toilet pans and cisterns, and removal of redundant boilers Report P28, P21, P22, P23, P24, P25, P26
£18.4m Option 2: renewal of all pipework and tanks, and sealing of toilets and bathrooms Report P29
£23.9m Option 3: new lifts, windows, roofs, insulation, water pumps and lighting Report P30
£27.9m Option 4: improved refuse disposal, environmental improvements, landscaping, estate lighting and a sprinkler system Report P31
£59.9m Option for demolishing all existing homes and providing 220 homes Report P43
Options considered
Chosen: Resident options appraisal and consultation process. The appraisal compares refurbishment, partial demolition with replacement housing, and full redevelopment before recommendations go to Cabinet. Report P9, P16, P17
Implications
Financial: The report has no direct financial implications. Future implications depend on the options appraisal recommendations. Report P54
Financial: All Ledbury Estate costs continue to come from contingency sums within the Housing Revenue Account and, where appropriate, the Housing Investment Programme. Report P55
Legal: Consultation must happen at a formative stage, provide sufficient reasons and adequate time, and have its outcome considered before the ultimate decision. The strategy should be reviewed at key development stages. Report P49
Equalities: The council must have due regard under section 149 of the Equality Act 2010. Officers must apply the Public Sector Equality Duty during consultation and members must apply it when the matter returns to Cabinet. Report P50, P51
Legal: Appointments with procurement implications require legal advice and any necessary gateway approval under standing orders and EU Regulations, if applicable. Report P52
Risk: Refurbishment works to strengthen the blocks require everyone to move permanently or temporarily. Report P20
Other: The Resident Project Group asked for sprinkler installation to have greater priority and be included in Option 2. Report P32
Other: The listed consultation priorities are automated sprinklers, communal satellite television, water pipework renewal, sealed bathrooms and toilets, thermal insulation, water pumps, improved rubbish disposal, environmental improvements, and improved lighting. Report P33, P34, P35, P36, P37, P38, P39, P40, P41, P42
Who and where
Ledbury Estate residents and former residents Report P33
Residents needing a temporary or permanent move Report P20
Occupants of the existing 220 homes Report P43
Timeline
Thursday 1 February 2018: A public consultation meeting is to be held Report P44
Friday 2 February 2018: The consultation is to close Report P45
Tuesday 6 February 2018: Cabinet is to receive a verbal update on the consultation outcome Report P45
May 2018: The Resident Project Team is to receive a consultant update and agree the final consultation format Report P14
May/June 2018: The independent consultant is to undertake options appraisal work Report P13
June 2018: The Resident Project Team is to consider the draft report and the options to put to residents Report P15
July 2018: Residents are to be consulted on the options Report P16
September/October 2018: Cabinet is to receive officers' recommendations, consultation results and the wider impact on Southwark's Housing Strategy Report P17
Plain English for the jargon
Options appraisal: Comparing refurbishment, partial demolition with replacement housing, and full redevelopment [P9]
Public Sector Equality Duty: The duty to eliminate discrimination, advance equality of opportunity and foster good relations [P50] [P51]
Housing Revenue Account: A contingency funding source for Ledbury Estate costs [P55]
Housing Investment Programme: A further funding source used where appropriate [P55]
Gateway report: A route for seeking necessary approval where appointments have procurement implications [P52]
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item8
Resolved
That the content of the report be noted. 2. That the draft dates of the key stages that the Ledbury Project Team have agreed be noted. 3. That a further report be received setting out the outcome of the resident consultation on the options appraisal process that is planned to be undertaken in July 2018.
Word for word from the decision Southwark published for this meeting.Source: moderngov.southwark.gov.uk
Report to Cabinet (decommissioned, for the Executive after, 6 pages
Recommendations
That cabinet:
1. Notes the content of this report.
2. Notes the draft dates of the key stages that the Ledbury Project Team have agreed and
3. Receives a further report setting out the outcome of the resident consultation on the options appraisal process that is planned to be undertaken in July 2018.
BACKGROUND INFORMATION
4. A Resident Project Group has been established on the Ledbury Estate to work with Officers on dealing with the recommendations of the Arup report called “Ledbury Estate: Structural Assessment of Bromyard, Peterchurch, Sarnsfield and Skenfrith House” dated 20 November 2017.
5. The Resident Project Group are meeting on a monthly basis and at their last meeting on 16 January 2018, they considered reports on the draft options appraisal brief and draft timeline and the indicative costs of the additional works that the residents had identified to be included in any refurbishment options.
1 Options Appraisal Report
6. At the Resident Project Group 16 January they received a report on the draft outline of a brief to appoint an independent consultant to carry out an options appraisal for the Ledbury Towers. The options may range from refurbishment, to partial demolition and re-provision to full re-development. The options will take into account the work being undertaken by the independent cost consultant which is reported below.
7. The Resident Project Board will be putting forward one leaseholder and one tenant to join the chair of the TRA, the cabinet member for housing and officers on the appointment panel.
8. The Cabinet received a report on 23 January 2018 advising them of the timetable the Resident Project Group had agreed up to the appointment of the independent options appraisal consultants.
9. At their 16 January 2018 the Resident Project Group agreed a draft timeline based on the independent Consultant being appointed to carry out the options appraisal in March 2018 as follows:
a. May/June 2018 Options appraisal work undertaken by the Consultant.
b. May 2018 Resident Project Team to meet to receive an update from the Independent Consultant for the options appraisal and to discuss and agree the final format of resident consultation on the options.
c. June 2018 Resident Project Team to meet to consider the draft report on the options produced by the Independent Consultant and consider the options to be put to residents.
d. July 2018 Resident Consultation on the options.
e. September/October 2018 Report to Cabinet on the Officers recommendations, the results of the resident consultation and the wider impact on Southwark’s Housing Strategy.
Indicative Refurbishment Costs
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Cabinet (decommissioned, for the Executive after at Southwark and we tell you when its next papers are published, before the meeting rather than after it.
Review of Void Disposal StrategyThat the progress of disposals of void housing properties since April 2009 be noted. 2. That the importance of void d...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.