New Depot

Noted Executive 2 papers

AI summarySouthwark Cabinet approved in principle a plan costing approximately £25m to combine three depots and relocate the recycling centre. A further decision is required before planning submission. [D][P22][P29][P30][P4]

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedCabinet must approve the project before planning submission. [D][P4]
Moneyapproximately £25m [P30]Approved for inclusion in the capital programme. [D][P3][P65]
What happens nextNot stated
Who it affectsNot stated

What was decided

Cabinet noted the preparatory work and approved development of the depot proposal in principle. Report P2

Cabinet noted the estimated cost and timing and approved the sum for inclusion in the capital programme. Report P3

Officers must return to Cabinet for project approval after legal and financial terms are negotiated and before planning submission. The Leader delegated approval of the revised business case and project initiation document to the cabinet member for finance, performance and Brexit, consulting the cabinet member for environment, transport management and air quality. Report P4, P5

Why

The existing depots are old, crowded at Sandgate Street, have poor staff facilities and are not energy efficient. Separate locations also hinder collaboration and place pressure on service capacity. Report P8, P10, P12

A feasibility study found that the public recycling centre building could accommodate a three storey depot. A capacity study confirmed enough space for the depot and some expansion. Report P21, P22

Using the existing structure has lower capital cost than the wrapping option and is supported by Veolia. Vacating the current sites is expected to generate enough capital receipts to fund the new building. Report P25, P28

What happens next

Officers must report back for Cabinet approval after legal and financial terms have been negotiated and before planning submission. Report P4, P70

Update the detailed business case and project initiation document, including governance, workstreams, timing and revenue implications, for approval under the Leader's delegation. Report P5, P32, P59

Negotiate a commercial lease and changes to the PFI arrangement, and obtain the required DEFRA and Veolia consent before construction. Report P33, P34, P49

The money

  • approximately £25m Estimated total cost, including construction, fit out, highways, associated works and providing the public recycling centre again. Report P30
  • £25m Capital cost approved for inclusion in the council's capital programme. Report P65, P69
  • in excess of £25m Estimated total capital receipts from developing the three vacated depot sites. Report P53, P67

Options considered

  • Chosen: Use the existing public recycling centre building. A feasibility and capacity study found it could house the depot over three storeys. Veolia supports the option, and it has lower capital cost. Report P21, P22, P25
  • Rejected: Build a three storey depot around the existing IWMF. Veolia had insurance concerns and was unwilling to approve it. It also required significant highway works and relocation of a gas main. Report P24, P25
  • Rejected: Use the IWMF car parks. Veolia considered the insurance implications and operational impacts unacceptable. Report P20
  • Rejected: Use Gasworks land. The access road and gas infrastructure constrained the development plots. Report P20
  • Rejected: Use Copeland Road. The site was not large enough to accommodate the new depot. Report P20
  • Rejected: Use Cantium Retail Park. The depot was not compatible with the proposed high density mixed use development and public park. Report P20

Implications

  • Financial: The capital cost is approximately £25m and disposal receipts are estimated to exceed it. The cost is to enter the capital programme. Report P30, P53, P67, P69
  • Financial: The business case must cover the Veolia land lease, giving up the Sandgate Street lease, recycling centre relocation, professional fees and possible Veolia costs. Confirmed revenue effects must enter the budget setting process. Report P32, P54, P57, P68
  • Legal: A Veolia commercial lease is needed. DEFRA and Veolia consent is required before construction because the site lease and PFI contract term extend to 2033. Report P33, P34
  • Legal: The PFI agreement may need to change. Legal services will advise when final terms return to Cabinet. Report P49, P62
  • Risk: The council's insurer indicated cover could be considered in principle, subject to further discussion, fire protection and risk measures. The depot site may attract additional terms for adjoining third party risk. Report P38
  • Equalities: A full equality impact assessment will be part of the project initiation document and will be monitored throughout the project. Report P44
  • Climate: Consolidating three inefficient, energy intensive depots into one energy efficient site is expected to support carbon reduction, air quality and lower travel emissions. Charging points may support more electric vehicles. Report P27, P46
  • Staffing: New welfare facilities may support current staff and recruitment. Staff and service users will be consulted on modern, accessible accommodation and new ways of working. Report P13, P27, P43

Who and where

  • The council's traded services division and cleaning and grounds maintenance teams Report P7
  • Depot, operational and frontline staff Report P8, P12, P27
  • Residents and other service users Report P12, P43
  • Residents using the public recycling centre Report P18, P29
  • Residents in areas identified for redevelopment of current depot sites Report P14, P15
  • Veolia, its staff and the waste operation Report P27, P33, P34, P57
  • DEFRA, as a PFI funder required to consent Report P33, P34
  • The council's insurers, Zurich Municipal, and Veolia's insurers Report P38

Timeline

  • Before the planning application is submitted: Officers must return for Cabinet approval after legal and financial terms have been negotiated. Report P4
  • Before construction can commence: Agreement with DEFRA and Veolia is required. Report P34
  • Until 2033: The proposed site lease and PFI contract term extend. Report P33
  • During the project: The full equality impact assessment will be produced and monitored. Report P44
  • March 2018: Cabinet decided to bring the southern repairs service back in house from October 2018. Report P10
  • October 2018: The southern repairs service was due to return in house. Report P10
  • 2026: London Power Tunnels projects at Gasworks land were programmed to complete. Report P20
  • 30 November 2018: The report was dated as final. Report P77

Plain English for the jargon

  • Depot: A site with offices, stores, workshops and parking for the council's operational fleet. [P7][P8]
  • Household Waste Reuse and Recycling Centre (HWRRC): The public recycling centre where residents can bring waste that does not fit normal waste receptacles. [P18]
  • Integrated Waste Management Facility (IWMF): The waste facility off Old Kent Road that contains the public recycling centre. [P18]
  • Private finance initiative (PFI): The contract arrangement used for the waste management contract and construction of the IWMF. [P33]
  • DEFRA: A PFI funder whose consent is needed for the depot proposal. [P33][P34]
  • Capital receipts: Proceeds expected from developing the current depot sites after they are vacated. [P28][P53]
  • Business case: A detailed assessment of the proposal, updated for approval before the project starts. [P31][P59][P70]
  • Project initiation document: A detailed document setting out governance, workstreams and timing. [P5]
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item18

Resolved

Decisions of the Cabinet 1. That the preparatory work done to date on providing a new depot for the council’s in house services be noted and the proposal to develop this as set out in paragraphs 14, and 16-20 of the report be approved in principle. 2. That the estimated cost and timing of the proposal be noted and the inclusion of this sum in the capital programme as set out in paragraph 24 of the report be approved. 3. That officers be instructed to report back to cabinet for approval of the project once the legal and financial terms have been negotiated and before the planning application is submitted. Decision of the Leader of the Council 4. That the authority for the approval of the revised business case and a detailed project initiation document setting out the governance, workstreams and timing of this project be delegated to the cabinet member for finance, performance and Brexit, in consultation with the cabinet member for environment, transport management and air quality.
Word for word from the decision Southwark published for this meeting. Source: moderngov.southwark.gov.uk

Follow this further

Built from Southwark's papers

What the report saysPro

Report to Cabinet (decommissioned, for the Executive after, 10 pages

Recommendations

Recommendations for the Cabinet

1. That the Cabinet note the preparatory work done to date on providing a new depot for the council’s in house services and approve in principle the proposal to develop this as set out in paragraphs 14, and 16-20 of this report.

2. That the Cabinet note the estimated cost and timing of the proposal and approve the inclusion of this sum in the capital programme as set out in paragraph 24 of this report.

3. That the Cabinet instruct officers to report back to Cabinet for approval of the project once the legal and financial terms have been negotiated and before the planning application is submitted. Recommendation for the Leader of the Council

4. That the Leader delegate to the cabinet member for finance, performance and brexit, in consultation with the cabinet member for environment, transport management and air quality, the approval of the revised business case and a detailed project initiation document setting out the governance, workstreams and timing of this project.

BACKGROUND INFORMATION

5. The council’s traded services division and the head quarters of its cleaning and grounds maintenance teams operate out of three separate depots at Sandgate St, Frensham St and Copeland Rd. It also uses a site at Latona Road to store grit to support the winter services.

6. These depots contain office accommodation, stores, workshops and parking for the council’s operational fleet, and very limited staff welfare facilities. The depots are all old, with poor staff facilities and old fashioned office space that does not meet the council’s standards for the rest of the workforce, and in the case of Sandgate St, is now extremely crowded. The buildings are not energy efficient.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Proposed site planAppendix 1 1 pages Download
PDF
Report: New depotReport 10 pages DownloadRead as text

At this meeting

Whole meeting

Who was there

8 of 14 attended
PJ
Councillor Peter John OBEChair, present
RL
Councillor Rebecca LuryCommittee Member, present
EA
Councillor Evelyn AkotoCommittee Member, present
JA
Councillor Jasmine AliCommittee Member, apologies
SC
Councillor Stephanie CryanCommittee Member, apologies
RL
Councillor Richard LivingstoneCommittee Member, present
VM
Councillor Victoria MillsCommittee Member, present
LP
Councillor Leo PollakCommittee Member, present
JS
Councillor Johnson SituCommittee Member, present
KW
Councillor Kieron WilliamsCommittee Member, present
EK
Eleanor KellyOfficer, expected
DF
Doreen Forrester-BrownOfficer, expected

All 14 on the meeting page

More from Southwark Cabinet (decommissioned, for the Executive after

All decisions
MeetingDecisionOutcome
28 May 2026 Election of Chair for the meetingThat Councillor Maisie Anderson be elected chair for this meeting. Decided Open
28 May 2026 Notification of any items of business which the chair deems urgentIt was agreed that all the deputations would be heard so that consideration of these representations could be given p... Agreed Open
28 May 2026 Disclosure of Interests and DispensationsDecision Maker (IDM) report in respect of this issue. Councillor Peter John also declared a personal, non prejudicial... Decided Open
28 May 2026 Review of Void Disposal StrategyThat the progress of disposals of void housing properties since April 2009 be noted. 2. That the importance of void d... Noted Open
28 May 2026 Housing Revenue Account - Approval of Housing Revenue Budget Account 2011/12That the savings required to deliver a balanced housing revenue account (HRA) for 2011/12 be noted. 2. That the propo... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies