What was decided
Cabinet approved the procurement strategy and bringing selected corporate facilities management services in house when the current contracts expire in June 2020, at an estimated annual cost of £1m. The in house services are Tooley Street cleaning and help desk, Queens Road post room, reception, cleaning and building management, and pest control for the wider council estate. [D] [P2] [P48] Report P2, P48
Further competition will use Crown Commercial Service framework RM3830, Lot 1b, for hard FM, including small works and capital investment projects. The estimated annual cost is £3.6m for hard FM and up to £3.5m for the projects, over five years with up to two further years at the council's discretion, giving an estimated maximum total contract value of £49.8m from June 2020. For project work up to £500k, the main contractor may receive the work if it is a specialist, is adequately performing, the council completes an estimate before tender, and value for money is shown; otherwise the council must tender openly from its approved list, with no additional gateway report where these conditions are met. [D] [P3] [P4] [P125] Report P3, P4, P125
A separate further competition will appoint a second soft FM supplier through the same framework and Lot 1b, at an estimated annual cost of £5.2m for five years with up to two further years at the council's discretion. The estimated total contract value is £36.2m, with an estimated start date of June 2020, and using the framework has no additional cost. [D] [P5] [P6] Report P5, P6
Why
The two current contracts expire in 2020, so replacement arrangements are needed to maintain buildings, meet statutory compliance requirements, and allow time for mobilisation and any staff transfers. [P8] [P16] Report P8, P16
The council rejected one supplier for all services because supplier failure could disrupt service delivery. It also found that bringing all operational estate services in house was not viable because the remaining services were not core business and the service was not yet ready for the added complexity. [P10] [P36] [P37] Report P10, P36, P37
The Crown Commercial Service framework met all essential requirements and offered a wider scope than the alternatives. Lot 1b had 34 suppliers, and the framework had already been tendered under EU procurement rules, so no separate EU tender was needed. [P31] [P39] [P40] [P43] [P129] Report P31, P39, P40, P43, P129
What happens next
The council will set up a programme board, liaise with stakeholders, begin supplier engagement, complete enabling work, and prepare tender documents. [P61] Report P61
The competitions will assess price at 60% and quality at 40%, with separate hard FM and soft FM suppliers, and no supplier winning both. [P73] [P78] Report P73, P78
Tender evaluation is due to finish on 30/09/2019, Gateway 2 contract award approval on 10/12/2019, and contract award on 31/01/2020, before the 01/06/2020 start date. The council will seek staffing information from current suppliers and complete due diligence on TUPE and pensions implications. [P62] [P66] [P67] Report P62, P66, P67
The money
- £86m Overall procurement strategy cost over 7 years, excluding inflation Report P104
- £49.8m Estimated maximum total value for the hard FM contract Report P3, P103
- £36.2m Estimated total value for the soft FM contract Report P5, P103
- £3.6m Estimated annual cost of hard FM Report P3, P103
- £3.5m Up to annual cost for small works and capital investment projects Report P3, P103
- £5.2m Estimated annual cost of soft FM Report P5, P103
- £1m Estimated annual cost of bringing selected services in house Report P2
- £500k Threshold for project related works under the hard FM contract Report P4, P125
Options considered
- Chosen: Crown Commercial Service framework RM3830, Lot 1b. It met all essential requirements and offered the strongest scope. The framework had already been tendered under EU rules, so no separate EU tender was required. Report P31, P39, P40, P129
- Chosen: Bring selected services in house. Some services were viable in house, while bringing all remaining services in house did not offer value for money. Report P36, P47
- Rejected: Single total facilities management supplier. Supplier failure could disrupt service delivery, so hard and soft FM were separated. Report P10
- Rejected: Provide all services in house. The remaining services were not core business, and bringing them in house was not considered to provide value for money. Report P36
- Rejected: Do nothing. Current contracts expire in 2020 and replacement contracts are required. Report P35
- Rejected: Official Journal of the European Union procurement. It would take longer and require more council resource, and would not guarantee suppliers beyond those already on the framework. Report P42, P43
- Rejected: Shared services with neighbouring councils. There are currently no opportunities to join agreements or undertake joint procurement projects. Report P44
- Rejected: ESPO, Fusion 21, NHS SBS and Scape Group frameworks. The services provided did not fully meet the council's operational requirements. Report P154, P157, P165, P167
Implications
- Financial: The strategy is estimated to cost £86m over 7 years excluding inflation. The contract values exclude inflation, annual uplifts are likely, and the full cost will be confirmed at Gateway 2. [P103] [P104] [P109] [P110] Report P103, P104, P109, P110
- Financial: Suppliers may submit higher bids after the Carillion collapse. Any funding shortfall will be addressed through the budget setting process and savings proposals. [P31] [P109] [P121] Report P31, P109, P121
- Legal: TUPE and pensions implications are likely for insourced services and may affect staff moving between suppliers or eligibility for the Local Government Pension Scheme. Contract Standing Orders require Gateway 1 and Gateway 2 reports, although no separate EU tender is needed because the framework was already tendered. Due diligence and staffing information are required before the full implications can be determined. [P64] [P65] [P66] [P129] Report P64, P65, P66, P129
- Staffing: Insourcing is likely to increase CFM staff numbers and management overheads. Procurement, TUPE and HR will need additional specialist resource. [P102] Report P102
- Risk: Delays could leave the council without a facilities management provider in 2020. Two separate suppliers are intended to reduce disruption if one supplier fails. [P10] [P53] Report P10, P53
- Equalities: Suppliers must offer guaranteed hours, operate an Equal Opportunities Policy, comply with equality legislation and meet London Living Wage requirements. A full equalities and health impact assessment will be included. [P87] [P88] [P89] Report P87, P88, P89
- Climate: Appointed suppliers must meet environmental requirements covering plastics, paper, vehicles, energy, water, emissions, waste and low energy equipment. [P92] Report P92
- Other: Contracts will include social value requirements, including local supply chains, apprenticeships for every £1m spent and support for diversity and inclusion. [P40] [P84] [P87] Report P40, P84, P87
Who and where
- Approximately 350 core operational and non residential buildings across the borough Report P11
- Council employees, visitors and members of the public Report P16
- Residents visiting council premises Report P80
- CFM staff who may transfer into the council Report P64, P102
- Incumbent and new supplier staff who may transfer under TUPE Report P65
- Interserve Facilities Management Limited and Kier Facilities Services Ltd Report P13, P14
- Departments commissioning and funding one off works Report P108, P122
- Potential local suppliers and small and medium enterprises in the supply chain Report P27, P76, P84
Timeline
- 11/12/2018: Approval of Gateway 1 procurement strategy report Report P62
- 01/06/2019: Completion of tender documentation Report P62
- 03/06/2019: Invitation to tender Report P62
- 02/08/2019: Closing date for tender returns Report P62
- 30/09/2019: Completion of tender evaluation Report P62
- 10/12/2019: Approval of Gateway 2 contract award report Report P62
- 31/01/2020: Contract award, contract register entry, TUPE consultation start if applicable, and award notices Report P62
- 01/06/2020; 31/05/2025; 31/05/2027: Contract start, initial completion and completion if extensions are exercised Report P62
Plain English for the jargon
- CFM: Corporate Facilities Management, the council function managing facilities and contracts. [P2] [P95]
- FM: Facilities Management, covering building maintenance and related services. [P2] [P11]
- Hard FM: Planned preventative maintenance, reactive maintenance, statutory compliance and small works projects. [P11]
- Soft FM: Help desk, cleaning, pest control, security, confidential waste, vending and mail services between sites. [P11]
- CCS: Crown Commercial Service, which operates the RM3830 Facilities Management Marketplace framework. [P3] [P27]
- TUPE: Transfer of Undertakings (Protection of Employment) Regulations 2006, covering staff transfers when service provision changes. [P64]
- LLW: London Living Wage, required from contractors and subcontractors, where appropriate, under the contract conditions. [P88]
- Lot 1b: The Crown Commercial Service category for total contract values between £7m and £50m, with 34 suppliers. [P29] [P152]