Southwark Regeneration in Partnership Programme - Lot A Sites Appropriation

Approved Executive 6 papers

AI summarySouthwark Cabinet approved changing the planning purpose of council land at Manor Place and Braganza Street, enabling consented housing and commercial schemes [D][P14][P16]. The development partner meets construction costs, but proven claims could require council damages payments [P39].

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedConsented homes and commercial schemes may proceed [D][P14][P16].
MoneyNo initial appropriation cost [P40]Partner meets construction costs; damages may still arise [P39][P40].
What happens nextNot stated
Who it affectsNot stated

What was decided

Cabinet confirmed that the council owned land edged red in Appendix 1 and Appendix 2 is no longer required for its present purposes [D][P2]. The land covers 169 to 179 Manor Place, the former Council Office and Stopford Road, and Kennington Workshops at 42 Braganza Street [D]. It approved appropriating the land for planning purposes under section 226 of the Town and Country Planning Act 1990 and section 122(1) of the Local Government Act 1972 [D][P2]. Report P2

After the planning appropriation, the completed housing stock should be appropriated to the Housing Revenue Account [D][P3]. The report refers to the newly built social housing units [P40]. Report P3, P40

Why

Planning consent was granted on 30 January 2018 for 56 flats at Manor Place and 33 residential units at Braganza Street [P14][P16]. The schemes are linked for wheelchair housing and affordable housing provision [P14][P16]. Report P14, P16

Appropriation gives development partners certainty that third party rights cannot be used to obtain an injunction stopping development. Rights holders may instead claim compensation for loss of value [P24]. Report P24

The schemes support the council's commitment to build 11,000 new council homes [P5][P26]. The public interest in about 40% affordable homes was considered to outweigh interference with private rights [P30]. Report P5, P26, P30

What happens next

Development partners will be appointed for the sites. Further consultation will then take place, and the development will have to be submitted for planning [P41]. Report P41

On completion, the council will appropriate land with the newly built social housing units to the Housing Revenue Account [P40]. It will transfer debt equal to the certified market value of the land, with interest determined on completion [P40][P56]. Report P40, P56

Nearby households and businesses will be asked to complete equality monitoring questionnaires at initial and key stages. These will be repeated periodically to assess impacts [P35]. Report P35

Options considered

  • Chosen: Appropriate the sites for planning purposes. The council owns the land, it is no longer needed for its existing purposes, and development work follows existing planning permissions [P45][P46][P53]. Report P2, P45, P46, P53

Implications

  • Financial: The development partner meets construction costs. The council must pay damages where a claimant proves a loss of property value caused by the scheme. Existing resource allocation can accommodate this, and the initial appropriation has no financial implications [P39][P40]. Report P39, P40
  • Financial: On completion, debt equal to the land's certified market value will move from the General Fund to the Housing Revenue Account. The Housing Revenue Account will pay interest on that debt, with the amount set on completion [P40][P56]. Related scheme costs will be contained within the Housing Investment Programme [P56]. Report P40, P56
  • Legal: Appropriation overrides third party rights. Beneficiaries may claim compensation for loss of value but cannot seek an injunction to delay or stop development [P24]. Report P24
  • Risk: The report identified a common law right of light risk from an adjoining owner. This could delay the scheme, cause contractual penalties or prevent delivery [P20]. Report P20
  • Risk: Unregistered rights may emerge during delivery, potentially causing delays, redesign or contractual penalties [P22]. Report P22
  • Equalities: The council considered the Public Sector Equality Duty. It judged the public interest in about 40% affordable homes to outweigh interference with private rights [P30][P31][P54]. Report P30, P31, P54
  • Equalities: Some small social enterprises serving wider ethnic communities experienced negative impacts. A relocation package, interim accommodation and an option to return were agreed [P34]. Report P34
  • Other: The schemes are intended to provide landscaping, commercial space, public realm and workspace while replacing vacant or underused buildings [P28][P29]. Report P28, P29

Who and where

  • People seeking council or affordable homes Report P7, P26, P30
  • Residents of the new developments Report P14, P16, P28, P29
  • Current workshop tenants and small social enterprises Report P29, P34
  • Adjoining owners and holders of unregistered rights Report P20, P22, P24
  • Developers and future development partners Report P11, P41
  • Council General Fund and Housing Revenue Account Report P40, P56
  • Local households and businesses near both sites Report P28, P29, P35

Timeline

  • July 2013: The council pledged to build 11,000 new council homes over a period of 30 years [P5]. Report P5
  • July 2014: The council renewed its pledge and committed to deliver 1,500 of the 11,000 homes by 2018 [P6][P8]. Report P6, P8
  • 13 July 2016: Section 203 of the Housing and Planning Act 2016 came into force [P49]. Report P49
  • 30 January 2018: Planning consent was granted for the Manor Place and Braganza Street developments [P14][P16]. Report P14, P16
  • 3 December 2018: The final report was dated [P62]. Report P62
  • January 2019: A start on site was scheduled [P17]. Report P17
  • June 2020: Practical completion was scheduled by this date [P17]. Report P17
  • 2026-05-28: Cabinet considered the appropriation decision [D].

Plain English for the jargon

  • Appropriation: Changing the purpose for which a council holds land or buildings [P24].
  • HRA: Housing Revenue Account, the council account that receives completed social housing and related debt [P3][P40][P56].
  • Southwark Regeneration in Partnership Programme: A joint partnership arrangement that uses established developers' investment and expertise [P11].
  • Public Sector Equality Duty: The general equality duty for public authorities, covering discrimination, equality of opportunity and good relations [P31][P32].
  • Right of light: A common law right assessed more strictly than planning daylight and sunlight tests [P20].
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item21

Resolved

RESOLVED : 1. That the area of council-owned land edged red on the plans at Appendix 1 of the report and Appendix 2, and known as 169-179 Manor Place, the former Council Office, Stopford Road, SE17 and Kennington Workshops 42 Braganza Street SE17 be confirmed as no longer required for the purposes for which they are currently held, and that the appropriation of the land for planning purposes to facilitate the development proposals for the area in accordance with section 226 of the Town and Country Planning Act 1990 and section 122(1) of the Local Government Act 1972 be approved. 2. That once the land is appropriated for planning purposes under the statutory provisions detailed above, the completed housing stock should be appropriated to the housing revenue account.
Word for word from the decision Southwark published for this meeting. Source: moderngov.southwark.gov.uk

Follow this further

Built from Southwark's papers

What the report saysPro

Report to Cabinet (decommissioned, for the Executive after, 9 pages

Recommendations

That cabinet:

1. Confirms that the area of council-owned land edged red on the plans at Appendix 1 and Appendix 2, and known as 169-179 Manor Place, the former Council Office, Stopford Road, SE17 and Kennington Workshops 42 Braganza Street SE17 are no longer required for the purposes for which they are currently held and approves the appropriation of the land for planning purposes to facilitate the development proposals for the area in accordance with section 226 of the Town and Country Planning Act 1990 and section 122(1) of the Local Government Act 1972.

2. Confirms that once the land is appropriated for planning purposes under the 1 statutory provisions detailed above, that the completed housing stock should be appropriated to Housing Revenue Account.

BACKGROUND INFORMATION

3. In July 2013 the council pledged to build a total of 11,000 new council homes over a 30-year period.

4. In July 2014, the council renewed its pledge to deliver a fairer future for all in Southwark in a set of 10 new fairer future promises as well as specific commitments, which include:

• Deliver value for money across all services • Build more quality affordable homes of every kind across the borough • Become an age friendly borough • Revitalise neighbourhoods • Support local people into work.

5. These promises are recognition of the need for new housing supply whilst improving existing housing, educational and health provision across the borough. In line with this the council also made a pledge in July 2014 to deliver 1,500 of the 11,000 new council homes by 2018.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Manor Place ShopsAppendix 1 1 pages Download
PDF
Braganza Street WorkshopAppendix 2 1 pages Download
PDF
. Appropriation BackgroundAppendix 3 3 pages Download
PDF
Image Manor Place ShopsAppendix 4 1 pages Download
PDF
Image BraganzaAppendix 5 1 pages Download
PDF
Report : Lot A Appropriation ReportReport 9 pages DownloadRead as text

At this meeting

Whole meeting

Who was there

8 of 14 attended
PJ
Councillor Peter John OBEChair, present
RL
Councillor Rebecca LuryCommittee Member, present
EA
Councillor Evelyn AkotoCommittee Member, present
JA
Councillor Jasmine AliCommittee Member, apologies
SC
Councillor Stephanie CryanCommittee Member, apologies
RL
Councillor Richard LivingstoneCommittee Member, present
VM
Councillor Victoria MillsCommittee Member, present
LP
Councillor Leo PollakCommittee Member, present
JS
Councillor Johnson SituCommittee Member, present
KW
Councillor Kieron WilliamsCommittee Member, present
EK
Eleanor KellyOfficer, expected
DF
Doreen Forrester-BrownOfficer, expected

All 14 on the meeting page

On this subject at Southwark

Search all
  1. Southwark Regeneration in Partnership Programme - Lot A Sites AppropriationThis decision
  2. Employment and Unemployment in Southwark (Report from Regeneration & Leisure Scrutiny Sub-Committee)Noted
  3. Southwark Regeneration in Partnership ProgrammeAgreed
  4. Gateway 1: Southwark Regeneration in Partnership Programme Procurement ApprovalApproved
  5. Gateway 2: Contract Award Approval - Southwark Regeneration in Partnership Programme Development PartnersNoted
  6. Gateway 1 - Procurement Strategy Approval Southwark Regeneration in Partnership Programme Procurement Approval - Lot AApproved

More from Southwark Cabinet (decommissioned, for the Executive after

All decisions
MeetingDecisionOutcome
28 May 2026 Election of Chair for the meetingThat Councillor Maisie Anderson be elected chair for this meeting. Decided Open
28 May 2026 Notification of any items of business which the chair deems urgentIt was agreed that all the deputations would be heard so that consideration of these representations could be given p... Agreed Open
28 May 2026 Disclosure of Interests and DispensationsDecision Maker (IDM) report in respect of this issue. Councillor Peter John also declared a personal, non prejudicial... Decided Open
28 May 2026 Review of Void Disposal StrategyThat the progress of disposals of void housing properties since April 2009 be noted. 2. That the importance of void d... Noted Open
28 May 2026 Housing Revenue Account - Approval of Housing Revenue Budget Account 2011/12That the savings required to deliver a balanced housing revenue account (HRA) for 2011/12 be noted. 2. That the propo... Noted Open