Gateway 1 - Procurement Strategy Approval: Parking and Traffic Enforcement and Associated Services
ApprovedExecutive1 paper
AI summarySouthwark Cabinet approved external parking and traffic enforcement procurement for a contract starting 1 April 2020, with four initial years, two possible three year extensions and up to £42m in total, and noted four services will be brought under council management [D].
Written from the decision and the officer reportPDF Pro
OutcomeApprovedStarts 1 April 2020, with two possible extensions. [P1]
MoneyAnnual £4.2m; initial £16.8m [P1]Up to £42m if both extensions are used. [P1]
What happens nextProcure and award contract [P55]Single lot open EU procedure, seeking five tenders. [P56] [P58]
Who it affectsResidents, businesses and visitors [P113]Services apply across all borough communities. [P113]
What was decided
Southwark Cabinet approved the procurement strategy for a new external contract for parking and traffic enforcement and associated services. The contract is to commence on 1 April 2020, run for four years and be extendable twice for three years. Report P1
Cabinet noted that early appeals and challenge correspondence, parking permits and administration, the parking call centre and school crossing patrol officers would be brought under council management. This followed the Gateway 0 decision. Report P2, P5
The approved strategy uses one contractor and a single lot through the EU open procedure. The award will be based on price at 60% and quality and innovation at 40%. Report P55, P56, P102
Why
Doing nothing was rejected because parking and traffic enforcement is a statutory obligation. Every highway authority must ensure the function is delivered. Report P34
Delivering the full service requires specialist vehicles, equipment, software and training. External contractors provide bulk purchasing power, specialist subcontractor agreements and flexible staffing, and these services have always been outsourced since 1994. Report P37, P38
Cabinet had already approved bringing the selected services under council management at Gateway 0. The estimated £250,000 net internal cost increase was expected to be largely offset by reduced current contract costs. Report P4, P5, P132
What happens next
Develop the specification and tender documents with the procurement, legal contracts and finance teams. A project board will review the documents monthly. Report P92, P93, P95
Run the single lot open EU procedure, advertise in OJEU and Contracts Finder, and seek at least five tenders. The award report will go through Gateway 2, with price weighted 60% and quality and innovation 40%. Report P56, P58, P83, P97, P102
Complete consultation with the incumbent supplier and potential tenderers, and undertake due diligence on employee transfer and pension effects. Additional council resources are needed for correspondence, permits, the call centre, human resources, payroll and recruitment. School crossing patrols will join the road safety team. Report P90, P130, P131, P137
The money
£42m Maximum estimated contract value if both extensions are used Report P1
£16.8m Estimated value across the initial four year term Report P1
£4.2m Estimated annual value of the external contract Report P1
£12.6m Estimated value of each possible three year extension Report P1
£250,000 Estimated net increase in internal costs from bringing services under council management Report P132
Options considered
Chosen: New external contract using an open EU tender. A new supplier would be selected through an EU compliant tender. The market is expected to be competitive. Report P30, P44, P58
Rejected: Restricted procurement procedure. The report says the UK on street parking enforcement industry is large enough to seek at least five tenders under the open procedure, so a restricted process is unnecessary. Report P58
Chosen: One contractor and a single lot. The report says this provides a simpler letting process, lower procurement costs and officer time, and a straightforward contractor relationship. Report P55, P56, P57
Chosen: British Parking Association model contract. It uses key performance indicators to support a constructive partnership rather than an adversarial relationship. It has been used successfully in the current contract. Report P29, P45, P59
Rejected: Do nothing. Parking and traffic enforcement is a statutory obligation and must be delivered by every highway authority. Report P34
Rejected: Frameworks. There are no known frameworks for parking enforcement. Separate frameworks for related services do not meet the requirement. Report P42
Rejected: Joint Borough procurement. A joint operation is unlikely to produce much or any saving and may require additional management support. Report P49, P50
Rejected: Voluntary sector or not for profit. No known voluntary sector or not for profit organisations provide the required service. Report P53
Implications
Financial: Moving the selected services under council management is estimated to add £250,000 in net internal costs. This should be largely offset by lower current contract costs and contained within existing parking revenue budgets. Report P132, P133, P142, P143
Financial: Any parking service surplus is ring fenced for parking and related services and may only be used under section 55 of the Road Traffic Regulation Act 1984 as amended. Report P13
Legal: The procurement must follow the Public Contracts Regulations 2015 and the council's Contract Standing Orders. A provider change is likely to be a service provision change under TUPE, but its effect depends on workforce arrangements, so due diligence and further legal advice are needed. Report P89, P90, P151, P152
Equalities: Cabinet should consider the Public Sector Equality Duty. Periodic equality analysis is recommended to demonstrate compliance and measure the likely and actual effects on individuals and groups, especially people with characteristics protected by law. Report P153, P154
Staffing: Additional resources are required for correspondence, permits, the call centre, human resources, payroll and recruitment. School crossing patrols will join the road safety team, with parking services continuing to fund them. Report P130, P131
Climate: Contract requirements should support sustainability and reuse of parking and traffic enforcement waste. New fleet should use the latest Euro standard engines, sustainable transport should be encouraged where feasible, and half of enforcement vehicles are currently fully electric. Report P123, P124
Other: The contractor is expected to have a trade union agreement. Social value requirements include the London Living Wage, job creation and local employment, apprenticeships, work placements, local recruitment, the Southwark Diversity Standard and vehicle safety pledges. Report P118, P121
Risk: Delaying procurement could require an extension of the existing APCOA contract. Other risks include systems transition, staffing and equipment, weak competition and insufficient project resources. Report P67, P68, P69, P70, P72
Who and where
All borough communities and groups Report P112, P113
Residents Report P113
Businesses Report P113
Visitors and people passing through the borough Report P113
Elderly people, disabled people and young children Report P113
Parking permit, challenge and call centre users Report P5, P36
Council parking, customer service, road safety and support staff Report P130, P131
Incumbent provider and prospective tenderers Report P89, P137
Timeline
6 February 2019: Gateway 0 cabinet approval Report P4
30/04/2019: Planned Gateway 1 approval Report P81
01/07/2019: OJEU notice, Contracts Finder opportunity and invitation to tender Report P81
02/09/2019: Tender return deadline Report P83
10/12/2019: Planned Gateway 2 contract award approval Report P83
06/01/2020: Planned contract award, contract register entry and award notices Report P84, P85, P86
01/04/2020: Contract start Report P87
31/03/2024 or 31/03/2030: Initial contract completion, or contract completion if extensions are exercised Report P87
Plain English for the jargon
Gateway 0: Earlier cabinet approval of delivery options for parking and traffic enforcement services [P4]
Gateway 1: Cabinet approval stage for the procurement strategy [P4] [P6]
Gateway 2: Approval stage for the contract award report [P83]
BPA model contract: British Parking Association contract based on key performance indicators [P29] [P45]
KPI: Key performance indicator used to assess the service [P59] [P126]
OJEU: The procurement journal where contract and award notices are placed [P85] [P97]
SQ: Standard Questions assessed before tender proposals [P101]
TUPE: Transfer of Undertakings (Protection of Employment) Regulations 2006, which apply when service delivery changes [P89]
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item12
Resolved
That the procurement strategy outlined in the report for the parking and traffic enforcement services contract - namely that the council will procure a new contract externally for the provision of parking and traffic enforcement and associated services to commence 1 April 2020, for a period of four years with two possible three-year extensions at an estimated annual value of £4.2m, meaning £16.8m across the initial term and up to £42m if both contract extensions are used, each having a value of £12.6m, be approved. 2. That it be noted that the services detailed in paragraph 4 of the report will be brought in-house as outlined in the Gateway 0 report.
Word for word from the decision Southwark published for this meeting.Source: moderngov.southwark.gov.uk
Report to Cabinet (decommissioned, for the Executive after, 16 pages
Recommendations
1. That cabinet approve the procurement strategy outlined in this report for the parking and traffic enforcement services contract, namely that the council will procure a new contract externally for the provision of parking and traffic enforcement and associated services to commence 1 April 2020, for a period of four years with two possible three-year extensions at an estimated annual value of £4.2m, meaning £16.8m across the initial term and up to £42m if both contract extensions are used, each having a value of £12.6m.
2. That cabinet note that the services detailed in paragraph 4 will be brought in- house as outlined in the Gateway 0 report.
BACKGROUND INFORMATION
3. This Gateway 1 procurement strategy approval report refers to the strategic options assessment and procurement proposal (Gateway 0) for delivery of Parking and traffic enforcement services approved by the cabinet on 6 February 2019.
4. The Gateway 0 approved the bringing in house of: Early appeals and challenge correspondence Parking permits and administration Parking call centre School crossing patrol officers.
5. The Gateway 0 required officers to prepare a Gateway 1 report for further cabinet consideration and to outline the procurement strategy for the outsourced services.
6. During 2011-12 Southwark Council carried out a competitive tender process under the EU Restricted route to procure services for their parking enforcement and associated services responsibilities. The provision of the services was a single contract with a single supplier who would utilise a number of specialist parking sub-contractors to deliver the service.
7. Following evaluation the contract was awarded to APCOA Parking UK Ltd, with the main sub-contractors being Paybyphone (permits and virtual pay and display), Conduent (parking and traffic enforcement IT), Siemens (CCTV cameras and maintenance) and ELV (vehicle removals and car pound).
8. The contract commenced on 1 April 2013 for a duration of 4 years taking the contract through to an expiry date of 31 March 2017. The contract allowed for an option for Southwark Council to extend the contract for 3 years by informing APCOA in writing with a minimum of three months’ notice. Following due process at the Southwark Council cabinet meeting on 13 December 2016 an extension of this contract for 3 years was approved.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Cabinet (decommissioned, for the Executive after at Southwark and we tell you when its next papers are published, before the meeting rather than after it.
Review of Void Disposal StrategyThat the progress of disposals of void housing properties since April 2009 be noted. 2. That the importance of void d...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.