Gateway 1: Procurement Strategy Approval - Contractor Services for the Delivery of Sceaux Gardens

Approved Executive 3 papers

AI summarySouthwark Cabinet approved a two stage restricted OJEU tender for 80 new homes at Sceaux Gardens, with an estimated works contract sum of £24,000,000 [D] [P6]. It delegated three Gateway 2 award decisions to the Strategic Director of Housing and Modernisation [D].

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedRestricted process; three Gateway 2 award decisions delegated [D]
Money£24,000,000 works contract [D]Total project estimate is £28,700,000 [P158]
What happens nextGateway 2 delegation [D]Strategic Director decides in consultation with Cabinet Member [P2]
Who it affects80 new homes [P6]33 homes demolished, giving 47 net additional homes [P6] [P157]

What was decided

Cabinet approved the two stage restricted OJEU procurement strategy for the Sceaux Gardens works contractor [D].

The approval set an estimated contract sum of £24,000,000. Phase 1 was expected to commence in April 2019 and be completed within 18 months. Phase 2 was anticipated to be completed within the following 18 months [D].

Cabinet delegated the award decisions for the Principle Development Agreement and the first and second phase build contracts to the Strategic Director of Housing and Modernisation, in consultation with the Cabinet Member for Social Regeneration, Great Estates and New Council Homes [D].

Why

The scheme is phased and likely to take at least three years. A single stage tender could deter contractors and increase council costs because contractors would price future build and material inflation [P28]. Report P28

The chosen process fixes overheads, profit and preliminary costs at the first stage. Stage two then reviews subcontract returns and build costs before fixed price JCT contracts are entered for each phase [P32] [P119]. Report P32, P119

The council expected this route to give contractors certainty about future costs and inflation, increase responses and provide value for money [P33] [P36] [P37]. Report P33, P36, P37

What happens next

Conduct soft market testing and submit a planning application, anticipated for January 2019 [P7] [P17]. Report P7, P17

Publish the OJEU notice and Contract Finder advert, assess PAS 91 submissions, and invite the top five bidders to submit an ITT. Any bidder within 5% of the fifth highest bidder may also be invited at the council's discretion [P38] [P39] [P40] [P88] [P100]. Report P38, P39, P40, P88, P100

Evaluate ITTs using a 60/40 price to quality ratio and recommend the highest scoring tenderer. Following Gateway 2 approval, enter the Principle Development Agreement, then run stage two for each phase and award individual JCT build contracts [P40] [P41] [P43] [P90] [P120]. Report P40, P41, P43, P90, P120

The money

  • £24,000,000 Total estimated works contract sum Report P2
  • £28,700,000 Estimated total cost to be procured through the strategy Report P158
  • £4,700,000 Leaseholder buybacks, homeloss and disturbance payments, professional fees, internal costs and contingency Report P158
  • over £15,000,000 Budgeted within the Housing Investment Programme Report P158
  • £0.6m, £6.2m, £8.9m, £8.1m, £3.9m, £1.0m Forecast works spend from spend to date through 2023/24 Report P161
  • £1m One apprentice required for every £1m of contract value Report P142
  • £15m Threshold above which procurement strategy approval was reserved to Cabinet Report P179

Options considered

  • Rejected: Existing OJEU compliant framework. Frameworks offered a more limited market and less flexibility for the phased two stage scheme. Report P25, P26
  • Rejected: Single stage OJEU compliant Invitation to Tender. A single stage process was likely to be unattractive and increase costs because contractors would price future build and material inflation. Report P28
  • Rejected: Two individual OJEU compliant processes. This could extend the programme and create value and transition problems with separate contractors working in the same estate. Report P30
  • Chosen: Two stage OJEU compliant Invitation to Tender. It suits phased delivery, locks in costs at both stages, improves competition and supports value for money. Report P32, P33, P35, P36, P37

Implications

  • Financial: The approval has no direct financial effect. The estimated total project cost is £28,700,000, and borrowing may be needed if final programme spend leaves a funding shortfall in the housing capital programme [P157] [P158] [P159]. Report P157, P158, P159
  • Legal: The works must follow the Public Contract Regulations 2015 and Public Sector Directive 2014/24/EU. The council intends to use a bespoke Principle Development Agreement and JCT Design and Build Contract 2016. TUPE should not apply at commencement because no existing contractor is delivering the work, but it could apply if the contractor changes [P21] [P83] [P86] [P174]. Report P21, P83, P86, P174
  • Equalities: The Public Sector Equality duty applies. The scheme should help households in need, including younger families needing larger homes and older people or disabled people. 50% of homes are for existing local tenants and all new rented homes will be at social rent levels, while nearby households may face short term disruption [P122] [P124] [P125] [P126] [P138] [P181]. Report P122, P124, P125, P126, P138, P181
  • Climate: The design must address whole life cycle costs, sustainable sourcing, environmentally benign heating and lighting, reuse and recycling, and Code of Sustainable Homes criteria or any successor requirement [P145] [P146] [P147]. Report P145, P146, P147
  • Risk: Controls include soft market testing, waiting for planning permission, financial and credit checks, and locking in overheads, profit and preliminary costs. The evaluation also uses minimum quality pass marks [P46] [P47] [P48]. Report P46, P47, P48
  • Staffing: Existing staff and budgets are sufficient for the timetable. Officer time is funded from capital budgets for the individual projects [P154] [P155] [P156]. Report P154, P155, P156
  • Other: The successful contractor must meet London Living Wage requirements. The council will seek local employment and training, and require one apprentice for every £1m of contract value [P133] [P134] [P142]. Report P133, P134, P142
  • Other: The New Homes Development Team will manage the contractor appointment, with monthly formal reviews of cost, quality and programme. A six monthly report will go to the Departmental Contract Review Board and an annual report to the Corporate Contract Review Board [P149] [P152] [P177]. Report P149, P152, P177

Who and where

  • Households in housing need across Southwark Report P124
  • Existing tenants from the local area Report P126, P137
  • Households on the council housing register Report P137
  • Households near the development during construction Report P125
  • Younger families needing larger homes Report P122
  • Older people and disabled people Report P124
  • Tenants being decanted and residents of other estate blocks Report P15
  • Local people and apprentices Report P134, P135, P142

Timeline

  • 12 March 2019: Estimated date of planning approval Report P59
  • 18 March 2019: Publication of OJEU Notice Report P59
  • April 2019: Phase 1 expected to commence, with completion within 18 months
  • 28 June 2019: Closing date for return of tenders Report P59
  • 12 August 2019: Approval of Gateway 2 Contract Award Report Report P59
  • 30 September 2019: PDA entered, contract starts and phase 1 second stage Invitation to Tender issued Report P60
  • 30 June 2021: Initial phase 1 contract completion date Report P69
  • 20 December 2021; 30 September 2023: Phase 2 JCT contract award, then the phase 2 and overall initial completion dates Report P60, P75, P78

Plain English for the jargon

  • OJEU: Official Journal of the European Union. The contract will be advertised through an official notice [P88].
  • ITT: Invitation to Tender. Shortlisted organisations submit priced bids and quality method statements [P39] [P40] [P102].
  • PDA: Principle Development Agreement. The overarching agreement sets overheads, profit, preliminary costs and the second stage process [P41].
  • JCT contract: The fixed price build contract entered separately for each phase [P32] [P43].
  • Gateway 2: The award approval point for the PDA and the separate build contract reports [P41] [P120].
  • TUPE: Provisions that could apply if the contractor changes during the works, with relevant provisions included in contract amendments [P83].
  • PAS 91 PQQ: Government standard prequalification questionnaire used to assess and shortlist tenderers [P38] [P70] [P92].
  • Soft market exercise: Early testing of contractor interest before the main tender [P46] [P88].
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item20

Resolved

That the strategy of procuring the works contractor for Sceaux Gardens through a two stage restricted OJEU tender process outlined in the report for new homes delivery with a total estimated contract sum of £24,000,000 with phase 1 expected to commence in April 2019 and be completed within 18 months, and phase 2 anticipated to be completed within 18 months following this, be approved. 2. That of the award decision for the three Gateway 2 reports for Sceaux Gardens (Principle Development Agreement and the subsequent build contracts for the first and second phases) be delegated to the strategic director of housing and modernisation, in consultation with the cabinet member for social regeneration, great estates and new council homes, for the reason outlined in paragraph 33 of the report.
Word for word from the decision Southwark published for this meeting. Source: moderngov.southwark.gov.uk

Follow this further

Built from Southwark's papers

What the report saysPro

Report to Cabinet (decommissioned, for the Executive after, 19 pages

Recommendations

That cabinet:

1. Approves the strategy of procuring the works contractor for Sceaux Gardens through a two stage restricted OJEU tender process outlined in this report for new homes delivery with a total estimated contract sum of £24,000,000 with phase 1 expected to commence in April 2019 and be completed within 18 months, and phase 2 anticipated to be completed within 18 months following this. 2. Approves the delegation of the award decision for the three Gateway 2 reports for Sceaux Gardens (Principle Development Agreement and the subsequent build contracts for the first and second phases) to the Strategic Director of Housing and Modernisation, in consultation with the Cabinet Member for Social Regeneration, Great Estates and New Council Homes, for the reason outlined in paragraph 33.

BACKGROUND INFORMATION

3. This procurement strategy relates to the procurement of the main works construction contract for Sceaux Gardens, which is part of the council’s programme to build 11,000 new homes.

4. The New Homes Development Programme is aimed at creating new homes from existing council assets and acquiring new assets. The principle of New Homes Development was agreed by Cabinet in July 2012. This site forms part of the phase 3 programme, Cabinet approved the inclusion of the Phase 3 sites within the New Homes Development Programme on the 15th September 2015.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Florian and Racine equalities impact assessmentAppendix 1 29 pages Download
PDF
Sceaux Gardens ImagesAppendix 2 133 MB Copy on its way
PDF
Report: Gateway 1: Procurement Strategy Approval: Contractor Services for the Delivery of Sceaux GardensReport 19 pages DownloadRead as text

At this meeting

Whole meeting

Who was there

10 of 14 attended
PJ
Councillor Peter John OBEChair, present
RL
Councillor Rebecca LuryCommittee Member, present
EA
Councillor Evelyn AkotoCommittee Member, present
JA
Councillor Jasmine AliCommittee Member, present
SC
Councillor Stephanie CryanCommittee Member, present
RL
Councillor Richard LivingstoneCommittee Member, present
VM
Councillor Victoria MillsCommittee Member, present
LP
Councillor Leo PollakCommittee Member, present
JS
Councillor Johnson SituCommittee Member, present
KW
Councillor Kieron WilliamsCommittee Member, present
EK
Eleanor KellyOfficer, expected
DF
Doreen Forrester-BrownOfficer, expected

All 14 on the meeting page

On this subject at Southwark

Search all
  1. Gateway 1: Procurement Strategy Approval - Contractor Services for the Delivery of Sceaux GardensThis decision
  2. Gateway 1 – Procurement Strategy Approval -The NestApproved
  3. Gateway 1 - Procurement Strategy Approval - Southwark and Lambeth Barristers FrameworkApproved
  4. Gateway 1 - Procurement Strategy Approval - Framework contracts to provide bailiff services to the Revenues & Benefits and Parking ServicesApproved
  5. Gateway 2: Contract Award Approval - Corporate Insurance Procurement (excluding Property Insurance)Approved
  6. Gateway 1 - Initial Procurement Strategy, Parking and Traffic Enforcement Services ContractAgreed

More from Southwark Cabinet (decommissioned, for the Executive after

All decisions
MeetingDecisionOutcome
28 May 2026 Election of Chair for the meetingThat Councillor Maisie Anderson be elected chair for this meeting. Decided Open
28 May 2026 Notification of any items of business which the chair deems urgentIt was agreed that all the deputations would be heard so that consideration of these representations could be given p... Agreed Open
28 May 2026 Disclosure of Interests and DispensationsDecision Maker (IDM) report in respect of this issue. Councillor Peter John also declared a personal, non prejudicial... Decided Open
28 May 2026 Review of Void Disposal StrategyThat the progress of disposals of void housing properties since April 2009 be noted. 2. That the importance of void d... Noted Open
28 May 2026 Housing Revenue Account - Approval of Housing Revenue Budget Account 2011/12That the savings required to deliver a balanced housing revenue account (HRA) for 2011/12 be noted. 2. That the propo... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies