Ledbury Estate Phase A - Appropriation for Planning Purposes
ApprovedExecutive3 papers
AI summaryCabinet approves appropriating Ledbury Estate Phase 1 land to and from planning purposes, clearing the way for 80 new homes including 45 council rented.
Written from the decision and the officer reportPDF Pro
OutcomeApprovedLand moved from housing to planning purposes, then back to housing
MoneyNo net costBoth appropriations on the same day, no debt transfer
What happens nextConstruction to April 2026Building works continue to programme end date
Who it affectsEstate residents and neighboursBromyard House demolished; rights of light affected
What was decided
Approve appropriation of the Phase 1 freehold land from housing to planning purposes under section 226 of the Town and Country Planning Act 1990. Report P2
Approve subsequent appropriation of the same land back to housing purposes under section 9 of the Housing Act 1985 once planning use ends. Report P3
Note that no objections or representations were received in response to the public notices placed in December 2023. Report P24, P25, P26
Why
To remove the risk of third parties using an injunction to delay or stop the construction of new council housing on the site. Report P5, P8, P16, P29, P36
To deliver a Council Plan commitment to build new homes and improve the economic, social and environmental well-being of the area. Report P18, P39
Appropriation is considered proportionate and gives greater certainty than leaving rights of light and covenants in place, with compensation remaining available to affected parties. Report P20, P21, P31, P33
What happens next
The council will continue to review the impact on groups with protected characteristics through an ongoing Equalities Analysis. Report P48
Any claims for interference with rights of light or restrictive covenants will be assessed, with affected parties able to bring compensation claims but not injunctions. Report P16, P20, P21
Options considered
Chosen: Appropriate land to planning purposes then back to housing. Provides certainty by preventing injunctions while preserving compensation rights for affected parties Report P19, P28, P31, P34
Rejected: Do not appropriate the site and accept the risk of injunction. Does not address the central risk of delay or an injunction halting the development Report P30
Rejected: Do not appropriate but take out insurance against claims. Does not address the central risk of delay or an injunction halting the development Report P30
Implications
Legal: Section 203 of the Housing and Planning Act 2016 will be triggered, overriding third party rights and converting them into compensation claims rather than grounds for injunction. Report P5, P16, P66, P77
Equalities: An Equalities Analysis has been undertaken for the project and the council will continue to monitor impacts on protected characteristic groups. Report P48
Climate: The Screening Opinion found no significant environmental effects requiring an Environmental Statement, and new buildings have been designed to mitigate climate impacts. Report P53, P55, P56
Risk: Owners and occupiers in parts of Commercial Way and Ledbury Street may experience rights of light interference and will need to claim compensation rather than seek an injunction. Report P20, P32
Financial: Appropriation will occur on the same day in both directions, resulting in no net transfer of debt and no direct financial implications. Report P57
Who and where
Residents of Bromyard House on the Ledbury Estate (demolished) Report P9, P10
Owners, lessees and occupiers of properties on Commercial Way and Ledbury Street with potential rights of light impact Report P20
Owners of restrictive covenants and statutory provider rights on the Estate Report P8
Future tenants of 45 new council rented homes and purchasers of 15 shared equity homes Report P51, P65
Timeline
14 December 2023: Public notice of intention to appropriate published in Southwark News Report P24
21 December 2023: Second public notice published in Southwark News Report P24
January 2024 to April 2026: Construction phase scheduled Report P13
11 January 2024: Deadline for representations or objections expired with none received Report P25, P26
Plain English for the jargon
Appropriation: The process by which a council changes the statutory purpose for which it holds its own land.
Rights of light: A legal easement giving a property owner the right to receive natural light through defined openings.
Injunction: A court order that requires a party to do or refrain from doing a specific act, here used to halt development.
Section 203 of the Housing and Planning Act 2016: Power that allows a local authority to override easements and other third party rights on land appropriated for planning, with rights converted to compensation claims.
Housing Revenue Account (HRA): A ring-fenced account that councils must keep for income and spending on council housing.
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item14
Resolved
That the land shown outlined on the plan at Appendix A of the report known as Phase 1 of the Ledbury Estate that is currently held for housing purposes, be confirmed as no longer required for those purposes and the appropriation of the land to planning purposes to facilitate the carrying out of the development proposals for the area in accordance with section 226 of the Town and Country Planning Act 1990 and section 122(1) of the Local Government Act 1972 be approved. 2. That following completion of the appropriation at paragraph 1 of the report, the land shown outlined on the plan at Appendix A of the report be confirmed as no longer required for planning purposes, and the appropriation of the land to housing purposes in accordance with section 9 of the Housing Act 1985 and section 122(1) of the Local Government Act 1972 be approved.
Word for word from the decision Southwark published for this meeting.Source: moderngov.southwark.gov.uk
Report to Cabinet (decommissioned, for the Executive after, 10 pages
Recommendations
That Cabinet:
1. Confirms that the land shown outlined on the plan at Appendix A known as Phase 1 of the Ledbury Estate that is currently held for housing purposes, is no longer required for those purposes and approves the appropriation of the land to planning purposes to facilitate the carrying out of the development proposals for the area in accordance with section 226 of the Town and Country Planning Act 1990 and section 122(1) of the Local Government Act 1972.
2. Confirms that following completion of the appropriation at paragraph 1 the land shown outlined on the plan at Appendix A will no longer be required for planning purposes, and approves the appropriation of the land to housing purposes in accordance with section 9 of the Housing Act 1985 and section 122(1) of the Local Government Act 1972.
Background
3. Phase 1 of the Ledbury Estate is situated in a predominantly residential area with a variety of retail and industrial businesses nearby on the Old Kent Road. The council holds the freehold interest in the land within its Housing Revenue Account.
4. This report recommends the council appropriates for planning purposes the freehold land known as Phase 1 in its ownership. This will engage powers under section 203 of the Housing and Planning Act 2016 overriding third party rights in the land which are then converted to a claim for compensation.
5. The report further recommends the land be appropriated back to housing on the basis that this ultimately will be its use.
6. The council has used this statutory mechanism to secure several of its housing development projects.
7. Cabinet should also note that the council has commissioned a Rights of Light Analysis Report to assess the potential effects of the development on any rights of light to some neighbouring properties and businesses outside the Estate and to those properties within the Estate that will be retained. There are some restrictive covenants and rights of statutory providers on the Estate that would also be interfered with. The risk of injunction means that the council should consider the use of its statutory powers to ensure that the development proceeds.
8. The course of action is recommended on the basis it will facilitate delivery of a development with significant public benefit; in the form of a full planning application for Phase 1 comprising the demolition of Bromyard House and the erection of three buildings at 6 storeys (Class C3), and 5 storeys and 14 storeys (Class C3) with associated parking, public realm, open spaces, landscaping and ancillary infrastructure.
9. Phase 1 works therefore, will affect residents of the Estate with the demolition of Bromyard House.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Cabinet (decommissioned, for the Executive after at Southwark and we tell you when its next papers are published, before the meeting rather than after it.
Review of Void Disposal StrategyThat the progress of disposals of void housing properties since April 2009 be noted. 2. That the importance of void d...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.