Gateway 1 - Procurement Strategy Approval: Replacement of the Enterprise Resource Planning System

Approved Executive 1 paper

AI summarySouthwark Cabinet approves procurement strategy for a fully integrated replacement ERP system, with an estimated maximum value of £35.7m across seven contracts over up to ten years.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedFully integrated ERP solution, seven contract lots via CCS frameworks
Money£35.7m maximum across all contractsOver up to ten years total duration
What happens nextCommence Lot 1 Vendor procurementTender documentation to be finalised
Who it affectsCouncil staff and service usersReplaces 1999 SAP system

What was decided

The Cabinet approved the procurement strategy for replacing the ERP system via CCS framework RM6194 for Vendor, System Implementation Partner, Data Migration and Reporting contracts, and via RM6193 for Business Change Management. Report P2

The Cabinet approved a fully integrated ERP approach, excluding best of breed suppliers from bidding. Report P3, P27

Authority to award contracts and to choose alternative procurement routes was delegated to the Strategic Director of Finance in consultation with the Cabinet Member for Equalities, Democracy and Finance. Report P5, P6

Why

The current SAP system will be unsupported from 2027 and end of life by 2030, so a replacement must be procured, implemented and embedded in time. Report P13, P22

A fully integrated ERP is preferred over a best of breed approach because it provides a single platform, avoids data silos, simplifies integration and supports stronger cyber security. Report P28, P29

Using CCS frameworks satisfies Public Contract Regulations 2015 requirements and lets the council benefit from pre-agreed terms and faster call-off than a full tender. Report P41, P177

What happens next

Tender documentation will be finalised, with procurement commencing for the Vendor contract (Lot 1) followed by the other lots, in line with the detailed timetable in the report. Report P11, P105, P108, P112

If framework timelines become tight, the Strategic Director of Finance may switch to alternative frameworks, may defer Lot 5 Reporting, and may use the replacement RM6194 framework for Lots 6 and 7. Report P91, P92, P93

Contract awards will be sought at Gateway 2, with lots 1 to 5 expected by 02/04/2025 and lots 6 and 7 by 09/01/2026. Report P111, P113

The money

  • £35.7m Estimated maximum value across all seven contracts over up to ten years Report P159
  • £22.75m Estimated cost for the initial three year term Report P158, P159
  • £10.05m Estimated cost for the initial five year extension Report P159
  • £2.9m Estimated cost for the remaining two year term Report P159

Options considered

  • Rejected: Do nothing. Current SAP system becomes unsupported in 2027 and end of life in 2030 Report P34
  • Rejected: Adapt or add modules to the current SAP system. Existing version only supported to 2027 and used until 2030 end of life Report P34
  • Rejected: Implement the most current SAP version. SAP confirmed there is no viable compliant pathway; cost would equal a new system Report P34
  • Chosen: Procure a fully integrated cloud based replacement ERP system. Single platform, consistent processes, stronger data and cyber security, focus in procurement Report P34, P35, P28, P29
  • Rejected: Procure a best of breed solution. Would not deliver a fully integrated solution; risk of data silos and complex integration Report P34, P28

Implications

  • Financial: Most of the estimated cost cannot be capitalised, so the council will need to set aside a significant fund for implementation costs and review revenue budgets post implementation. Report P156, P168
  • Legal: TUPE may apply if there is a change of supplier; the council will carry out due diligence and reflect this in tender documents. Report P116, P117
  • Equalities: The proposal to let a new contract for the finance, procurement, payroll and HR system is not anticipated to adversely impact on Equality Act 2010 duties. Report P136
  • Climate: Suppliers have committed to comply with Procurement Policy Note 06/21 on Carbon Reduction Plans and the council's Climate Change Strategy. Report P140
  • Staffing: The procurement will be managed by external resources with support from internal resources. Report P155
  • Risk: Key risks include procurement delays before framework expiry dates, supplier ceasing to trade, recruitment challenges, data cleansing needs and ERP implementation issues. Report P95, P96, P97

Who and where

  • Council departments using ERP for HR, Finance, Purchase to Pay and Payroll Report P13
  • Suppliers invited to bid across the seven contract lots Report P124
  • Existing supplier staff where TUPE may apply on contract change Report P116
  • Council staff and residents interacting with the new system Report P19, P20

Timeline

  • 19/06/2024: Approval of Gateway 1 Procurement strategy report Report P104
  • 27/06/2024: Invitation to tender for Vendor (Lot 1) Report P106
  • 02/04/2025: Contract awards for lots 1 to 5 Report P111
  • 01/05/2025: Contracts start for lots 1 to 5 Report P111
  • 09/01/2026: Contract awards for lots 6 and 7 (Support and Archiving) Report P113
  • 2027: Current SAP system goes out of support Report P13, P22
  • 30/04/2028: Initial contracts completion date for lots 1 to 5 Report P111
  • 30/04/2035: Contracts completion date for lots 1 to 5 if extensions exercised Report P111

Plain English for the jargon

  • ERP: Enterprise Resource Planning, a single software system covering core organisational processes such as finance, HR, payroll and procurement
  • CCS: Crown Commercial Service, the UK government body that runs framework agreements for public sector procurement
  • RM6194: CCS Back Office Software framework, the recommended route for most of the ERP procurement
  • RM6193: CCS Software Design and Implementation Services framework, used for Business Change Management
  • Best of breed: An approach using several specialist applications from different suppliers, requiring technical integration to behave like one system
  • Gateway 1: The decision stage that approves the procurement strategy before tendering begins
  • Gateway 2: The decision stage that approves the award of contract after tender evaluation
  • TUPE: Transfer of Undertakings (Protection of Employment) Regulations 2006, which can transfer staff to a new supplier
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item11

Resolved

That the procurement strategy for the replacement of the Enterprise Resource Planning (ERP) system, on the basis of a fully integrated ERP solution, via Crown Commercial Service (CCS) framework RM6194 Back Office Solutions for the Vendor, System Implementation Partner, Data Migration, and Reporting contracts, and via the replacement CCS framework for Back Office Solutions for archiving and support costs, and CCS framework RM6193 for Business Change Management, for a period of up to ten years total duration with an estimated maximum value of £35.7m across all contracts as detailed in the financial implication section of the report, be approved. 2. That the approach that the council will procure a fully integrated ERP solution for the reasons noted at paragraphs 17-19 of the report be approved. 3. That it be noted that the procurement strategy relates to seven contracts for the individual aspects of the requirements associated with the ERP system, each for the contract periods and contract values noted in paragraph 23 of the report. 4. That approval be delegated to the strategic director of finance to approve the contract awards to the successful supplier(s) in consultation with the cabinet member for equalities, democracy and finance for the reasons noted in paragraph 61 of the report. 5. That approval be delegated to the strategic director of finance in consultation with the cabinet member for equalities, democracy and finance to approve alternative procurement route/s for all lots if required for the reasons noted at paragraph 49-52 of the report.
Word for word from the decision Southwark published for this meeting. Source: moderngov.southwark.gov.uk

Follow this further

Built from Southwark's papers

What the report saysPro

Report to Cabinet (decommissioned, for the Executive after, 22 pages

Recommendations

That the cabinet:

1. Approves the procurement strategy for the replacement of the Enterprise Resource Planning (ERP) system, on the basis of a fully integrated ERP solution, via Crown Commercial Service (CCS) framework RM6194 Back Office Solutions for the Vendor, System Implementation Partner, Data Migration, and Reporting contracts, and via the replacement CCS framework for Back Office Solutions for archiving and support costs, and CCS framework RM6193 for Business Change Management, for a period of up to ten years total duration with an estimated maximum value of £35.7m across all contracts as detailed in the financial implication section of this report.

2. Approves the approach that the council will procure a fully integrated ERP solution for the reasons noted at paragraphs 17-19.

3. Notes that this procurement strategy relates to seven contracts for the individual aspects of the requirements associated with the ERP system, each for the contract periods and contract values noted in paragraph 23.

4. Delegates approval to the Strategic Director of Finance to approve the contract awards to the successful supplier(s) in consultation with the Cabinet Member for Equalities, Democracy and Finance for the reasons noted in paragraph 61 of this report.

5. Delegates approval to the Strategic Director of Finance in consultation with the Cabinet Member for Equalities, Democracy and Finance to approve alternative procurement route/s for all lots if required for the reasons noted at paragraph 49-52 of this report.

Reasons for recommendations

6. The reasons for recommendations within this report and the approach being for the replacement of the current ERP system are set out in paragraphs 44- 47 of this report.

ALTERNATIVE OPTIONS CONSIDERED AND NOT RECOMMENDED

7. Set out in paragraphs 20-24 of this report. (Section ‘Options procurement route including procurement approach’ of this report).

POST DECISION IMPLEMENTATION

8. Once approval for the recommendations has been received, the procurement of the contracts comprising the ERP programme will commence with the finalisation of requirements, tender documentation and detailed evaluation criteria, which will be approved by the ERP programme board. This will commence with the Vendor contract (Lot 1). The timescales for the procurement processes are set out in the tables at paragraph 56 of this report.

BACKGROUND INFORMATION

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Report: Gateway 1: Replacement of the ERP SReport 22 pages DownloadRead as text

At this meeting

Whole meeting

Who was there

8 of 15 attended
CP
Clive PalfreymanCouncil Staff, expected
DC
Dominic CainCouncil Staff, expected
KW
Councillor Kieron Williams Leader of the CouncilChair, present
JA
Councillor Jasmine Ali Deputy Leader and Cabinet Member for Children, Education and RefugeesCommittee Member, present
EA
Councillor Evelyn Akoto Cabinet Member for Health and WellbeingCommittee Member, apologies
JB
Councillor John Batteson Cabinet Member for Climate Emergency, Jobs and BusinessCommittee Member, present
SC
Councillor Stephanie Cryan Cabinet Member for Equalities, Democracy and FinanceCommittee Member, present
HD
Councillor Helen Dennis Cabinet Member for New Homes and Sustainable DevelopmentCommittee Member, present
NE
Councillor Natasha Ennin Cabinet Member for Community Safety and NeighbourhoodsCommittee Member, apologies
SK
Councillor Sarah King Cabinet Member for Council HomesCommittee Member, present
JM
Councillor James McAsh Cabinet Member for Clean Air, Streets and WasteCommittee Member, present
PM
Councillor Portia Mwangangye Cabinet Member for Leisure, Parks and Young PeopleCommittee Member, present

All 15 on the meeting page

On this subject at Southwark

Search all
  1. Gateway 1 - Procurement Strategy Approval: Replacement of the Enterprise Resource Planning SystemThis decision
  2. Gateway 1 – Procurement Strategy Approval -The NestApproved
  3. Gateway 1 - Procurement Strategy Approval - Southwark and Lambeth Barristers FrameworkApproved
  4. Gateway 1 - Procurement Strategy Approval - Framework contracts to provide bailiff services to the Revenues & Benefits and Parking ServicesApproved
  5. Gateway 2: Contract Award Approval - Corporate Insurance Procurement (excluding Property Insurance)Approved
  6. Gateway 1 - Initial Procurement Strategy, Parking and Traffic Enforcement Services ContractAgreed

More from Southwark Cabinet (decommissioned, for the Executive after

All decisions
MeetingDecisionOutcome
28 May 2026 Election of Chair for the meetingThat Councillor Maisie Anderson be elected chair for this meeting. Decided Open
28 May 2026 Notification of any items of business which the chair deems urgentIt was agreed that all the deputations would be heard so that consideration of these representations could be given p... Agreed Open
28 May 2026 Disclosure of Interests and DispensationsDecision Maker (IDM) report in respect of this issue. Councillor Peter John also declared a personal, non prejudicial... Decided Open
28 May 2026 Review of Void Disposal StrategyThat the progress of disposals of void housing properties since April 2009 be noted. 2. That the importance of void d... Noted Open
28 May 2026 Housing Revenue Account - Approval of Housing Revenue Budget Account 2011/12That the savings required to deliver a balanced housing revenue account (HRA) for 2011/12 be noted. 2. That the propo... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies