New James Court, Scylla Road – proposed community-led housing
NotedExecutive3 papers
AI summarySouthwark Cabinet approves in principle the disposal of land at New James Court, Scylla Road, Peckham, to London Community Land Trust for around 12 new affordable community-led homes on a long lease.
Written from the decision and the officer reportPDF Pro
OutcomeNotedLand to be transferred to London Community Land Trust
MoneyNil premium; loss of HRA incomecirca £32,432 per annum from 27 garages
What happens nextFinalise contractual termsTarget completion June 2026
Who it affectsGarage tenants and estate residentsPlus future affordable home seekers in Peckham
What was decided
Cabinet noted progress on the pilot and the selection of London Community Land Trust as the preferred delivery partner following a competitive process from November 2024 to February 2025. Report P2
Cabinet approved in principle the disposal of land at New James Court, Scylla Road to London Community Land Trust for community-led affordable housing. Report P2
Authority to approve the detailed contractual terms was delegated to the Director of Planning and Growth, in line with the key terms in the report. Report P3
Why
The disposal supports the council's response to the Southwark Land Commission and brings forward new affordable homes on council land identified by the community as a candidate site. Report P4, P14, P15
It will increase the diversity of affordable housing options, offering a product for those priced out of market housing but not eligible for social housing. Report P4
The site was assessed in 2023 for direct council delivery but was not prioritised due to site capacity, constraints and wider programme financial pressures. Report P6
What happens next
Officers will finalise detailed contractual terms with London Community Land Trust, with a target of June 2026. Report P10, P25
London Community Land Trust will re-engage its design team, consult the community and submit a planning application by the end of 2026, while the council works to secure vacant possession of the garages. Report P30
Conditions on planning, viability, funding and vacant possession are expected to be satisfied in early 2027, with start on site late in 2027 and completion in early 2029. Report P30, P31
The money
circa £32,432 per annum Current HRA rental income from 27 garages on the site that will be lost on disposal Report P53
60-80% of market value Anticipated property sales values under the proposed discounted market sale tenure Report P28
Options considered
Chosen: Dispose of the site to London Community Land Trust on a long leasehold for community-led affordable housing. Brings forward new affordable homes in perpetuity at no capital cost to the council and aligns with the Southwark Land Commission response Report P2, P4, P14, P70, P76, P78
Rejected: Direct delivery of council homes on the site under the council's own programme. Not considered a priority for direct delivery in 2023 due to site capacity, constraints and the wider financial pressures on the programme Report P6
Implications
Financial: Loss of about £32,432 per annum of HRA income from the 27 garages and no capital receipt; disposal and legal costs to be met from existing budgets; development to be funded by London Community Land Trust with no call on council capital resources. Report P53, P54, P55, P72, P73
Legal: Disposal of land held for housing purposes is governed by section 32 of the Housing Act 1985 and is permitted under the General Housing Consents 2013, subject to the council obtaining vacant possession. Report P65, P66, P67
Equalities: An Equalities Impact Assessment has been carried out and is at Appendix 2; the report also addresses the public sector equality duty under section 149 of the Equality Act 2010 and considers the impact of vacating the garages and the affordable housing scheme. Report P44, P68
Climate: New homes are expected to contribute to the council's 2030 carbon neutral target, with developers held to stringent environmental standards under Southwark Plan 2022 policy SP1. Report P50, P51
Risk: The conditional structure of the agreement mitigates risk to the council by requiring planning consent, scheme viability, secured funding and vacant possession before the lease is granted, with longstop dates allowing recovery of the site if milestones are missed. Report P24, P73
Who and where
Existing garage tenants on the New James Court Estate, who will be required to give up their units to enable development Report P26
Residents of the wider New James Court Estate of 50 homes in seven blocks, whose rights of access and utility services through the site must be maintained Report P21, P26
Households priced out of the market but not eligible for social housing, who may apply for the new discounted market sale homes Report P4, P28
Local key workers on lower incomes, identified as a potential priority group for the new homes Report P45
Timeline
2015: Peckham Citizens formed under Citizens UK Report P12, P56
2016: Peckham Citizens Founding Assembly and launch of campaign for community-led homes Report P12, P56
2019: Council began exploring project feasibility with the community steering group Report P12
March 2022 and July 2022: Public engagement events on the Scylla Road site proposals Report P12, P57
August 2022: Progress paused while the council explored direct housing delivery Report P12
2023: Site assessed but not prioritised for direct council delivery; Southwark Land Commission published 'Land for Good' Report P6, P13
July 2024: Cabinet agreed the council's response to the Land Commission and the Scylla Road CLT pilot Report P14, P35
November 2024 to February 2025: Competitive selection process for a community-led housing delivery partner Report P2, P16
April 2025: London Community Land Trust confirmed as preferred delivery partner Report P18
June 2025: London Community Land Trust community engagement event on site Report P58
7 July 2025: Cabinet approved the revised Affordable Housing SPD recognising CLT homes as affordable Report P37
22 January 2026: Final report dated Report P85
28 May 2026: Cabinet decision approving disposal in principle
June 2026: Target for finalising detailed contractual terms Report P10
End of 2026: Target submission of planning application Report P30
Early 2027: Anticipated satisfaction of conditions and grant of lease Report P30, P31
Late 2027: Anticipated start on site Report P31
Early 2029: Anticipated completion of the development Report P31
Plain English for the jargon
Community Land Trust (CLT): A democratic, non-profit body that owns and develops land for the benefit of the local community, keeping homes affordable in perpetuity
Housing Revenue Account (HRA): The ring-fenced account that holds income and expenditure relating to the council's own housing stock
Equalities Impact Assessment (EqIA): An assessment of how a proposal may affect people with protected characteristics and other groups
Supplementary Planning Document (SPD): A document that adds detail to policies in the local plan, including the Affordable Housing SPD adopted by Cabinet on 7 July 2025
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item9
Resolved
That the progress to date in bringing forward a pilot scheme for community-led homes at a site in Peckham, including the selection of London Community Land Trust (“CLT”) as the preferred delivery partner, following a competitive selection process carried out in November 2024 – February 2025 be noted. 2. That an in-principal disposal of land at New James Court, Scylla Road, as shown at Appendix 1 to the report, to London Community Land Trust for the delivery of new community-led affordable homes be approved. 3. That authority be delegated to the director of planning and growth to approve detailed contractual terms for the proposed disposal , in line with the key terms set out within the report.
Word for word from the decision Southwark published for this meeting.Source: moderngov.southwark.gov.uk
Report to Cabinet (decommissioned, for the Executive after, 11 pages
Recommendations
Recommendations for the Cabinet
1. To note the progress to date in bringing forward a pilot scheme for community- led homes at a site in Peckham, including the selection of London Community Land Trust (“CLT”) as the preferred delivery partner, following a competitive selection process carried out in November 2024 – February 2025. 1 2. To approve in principle the disposal of land at New James Court, Scylla Road, as shown at Appendix 1, to London Community Land Trust for the delivery of new community-led affordable homes.
3. To delegate authority to the Director of Planning and Growth to approve detailed contractual terms for the proposed disposal, in line with the key terms set out within this report.
Reasons for recommendations
4. The proposed disposal facilitates the delivery of new affordable homes on council land held for housing purposes and identified by the community as having potential for community-led homes. The proposed terms of the conditional disposal agreement ensure that planning, funding and viability are all resolved prior to the transfer of land taking place. The housing model will increase the diversity of affordable housing options available within the local area, providing a product for those who are priced out of traditional market housing but do not qualify for social housing.
ALTERNATIVE OPTIONS CONSIDERED AND NOT RECOMMENDED
5. In parallel to being identified by Peckham and Southwark Citizens as a candidate site for community-led housing, the proposed site was identified by the council as a candidate for delivery of new affordable homes under the council’s own direct delivery programme. The site was assessed in 2023 but was not considered as a priority site for direct delivery of council homes, given the site capacity and constraints and in the context of the wider financial constraints of the programme.
POST DECISION IMPLEMENTATION
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Cabinet (decommissioned, for the Executive after at Southwark and we tell you when its next papers are published, before the meeting rather than after it.
Review of Void Disposal StrategyThat the progress of disposals of void housing properties since April 2009 be noted. 2. That the importance of void d...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.