London Borough of Southwark
Cabinet (decommissioned, for the Executive after, Thursday 28 May 2026 at 3.00pm

Gateway 1: Procurement Strategy Approval Security Cover in Supported Hostels

Approved Executive 2 papers

AI summarySouthwark Cabinet approved a £5.525m procurement strategy to deliver security across five supported hostels from November 2026 for up to five years, with the award decision delegated to the housing director.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedSingle contract across five hostels
Money£5.525m total estimated£1.105m a year for three years, extendable by two
What happens nextTender to be publishedFind a Tender notice planned for 18 February 2026
Who it affectsFive supported hostelsVulnerable residents and security suppliers in Southwark

What was decided

Cabinet approved the procurement strategy for the supported hostels security contract at an estimated annual value of £1.105m, running for three years with the option to extend by up to two further years, making a total estimated contract value of £5.525m. Report P1

Cabinet delegated the Gateway 2 award decision to the Strategic Director of Housing, in consultation with the Cabinet Member for Council Homes. Report P2, P167

Why

Three of the five security contracts need reprovisioning, and a single retender offers a chance to reshape provision for residents with mental health, domestic violence and substance misuse needs, and bring consistency across the hostels. Report P10, P11, P13, P14

A Competitive Flexible Procedure under the Procurement Act 2023 was chosen as the route most likely to attract specialist suppliers experienced in safeguarding vulnerable adults in housing or care settings. Report P40, P41, P45, P47

What happens next

A single procurement process will run, with the tender notice planned for publication on Find a Tender on 18 February 2026, contract award expected on 7 August 2026 and the contract due to start on 1 November 2026. Report P8, P66

The contract runs to 31 October 2029 initially, with a possible extension to 31 October 2031; monthly performance reviews and annual reviews will be in place for at least the first year. Report P66, P133, P134

The money

  • £1.105m Estimated annual contract value Report P1, P143
  • £5.525m Estimated total contract value excluding VAT Report P1, P143
  • £6.630m Estimated total contract value inclusive of VAT Report P143

Options considered

  • Rejected: Do nothing. Hostels cannot be left unguarded without placing vulnerable residents at considerable risk Report P28
  • Rejected: Carry on with the current split arrangements. Fails to improve safety, wellbeing and consistency for residents Report P29
  • Rejected: Insource the security service. The council has no direct experience of running security services and another London council found in-housing more expensive once on-costs were added Report P30, P31, P32, P33, P34
  • Rejected: Buy through a Soft Facilities Management framework (ESPO or CCS). Listed suppliers mostly focus on concierge, retail, leisure or CCTV rather than specialist housing support for vulnerable adults Report P35, P36, P37, P38
  • Rejected: Open procedure competitive tender. Would require substantial officer time to assess all anticipated bids at once Report P44
  • Chosen: Competitive Flexible Procedure tender as a single contract. Multi-stage approach with a Procurement Specific Questionnaire shortlist allows a specialist single contract covering all five hostels Report P45, P47, P48

Implications

  • Financial: Contract costs are recovered through residents' service charges, which are eligible for housing benefit, so there should be little to no net impact on the council assuming minimal void periods. Report P147, P148, P159
  • Equalities: An Equalities Impact and Needs Assessment found no anticipated negative impacts, with the new service expected to have a positive effect on residents, including those from ethnic minority and other underrepresented groups. Report P93, P96, P97, P169
  • Legal: The procurement follows the light touch provisions of the Procurement Act 2023 using a Competitive Flexible Procedure, and the Public Sector Equality Duty under section 149 of the Equality Act 2010 has been considered. Report P40, P168, P169
  • Climate: The specification will require suppliers to have environmental policies and encourage low-carbon transport, route optimisation, energy saving and reduced single-use plastics. Report P107, P108, P109
  • Risk: Key risks are procurement slipping on timescale, weak bid quality, and bids exceeding budget; an annual price review mechanism is included to manage the latter. Report P52, P53, P54
  • Staffing: There are no staffing implications for the council; current contractor staff may have TUPE rights to transfer to any new supplier. Report P68, P140

Who and where

  • Residents of the five Southwark supported hostels, including adults with mental health needs, histories of domestic violence, substance misuse or offending Report P10, P17, P88
  • Current and prospective security suppliers, with an emphasis on attracting SMEs and Voluntary, Community and Social Enterprises Report P20, P22, P23, P40
  • The council's Housing Needs and Support division, which will manage and monitor the new contract Report P83, P139

Timeline

  • 18/02/2026: Planned publication of tender notice on Find a Tender Report P65
  • 20/03/2026: Planned closing date for expressions of interest Report P65
  • 28/04/2026: Planned closing date for return of tenders Report P65
  • 28/05/2026: Cabinet approval of Gateway 1 procurement strategy (this decision)
  • 21/07/2026: Planned approval of Gateway 2 contract award report Report P65
  • 07/08/2026: Planned contract award Report P65
  • 01/11/2026: Planned contract start Report P65
  • 31/10/2029: Initial contract completion date Report P65
  • 31/10/2031: Contract completion date if extension is exercised Report P65

Plain English for the jargon

  • Procurement Act 2023 (PA2023): UK law setting out how public bodies buy goods, services and works
  • Light touch services: A category of services under the PA2023 with fewer procurement rules and more flexibility
  • Competitive Flexible Procedure: A multi-stage tendering route under the PA2023, allowing shortlisting through a Procurement Specific Questionnaire before issuing an Invitation to Tender
  • Procurement Specific Questionnaire (PSQ): First-stage assessment of supplier eligibility, standards and capability before tendering
  • TUPE: Transfer of Undertakings (Protection of Employment) regulations giving staff the right to move to a new employer when a contract changes hands
  • EINA: Equalities Impact and Needs Assessment, the council's analysis of how a decision affects protected groups
  • SIA: Security Industry Authority, the body that licenses security operatives in the UK
  • London Living Wage (LLW): An independently set minimum hourly pay rate for London, higher than the national minimum wage
  • Find a Tender: The UK government's online portal for publishing public sector contract opportunities
  • Gateway 1 and Gateway 2: Southwark Council's decision stages for approving procurement strategy (Gateway 1) and the contract award (Gateway 2)
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item17

Resolved

That the procurement strategy outlined in the report for the supported hostels security contract at an estimated annual value of £1.105m for a period of three years with the option to extend by a further period of up to two years, making a total estimated contract value of £5.525m be approved. 2. That the delegation of the gateway 2 award decision report to the strategic director of housing in consultation with the cabinet member for council homes be approved.
Word for word from the decision Southwark published for this meeting. Source: moderngov.southwark.gov.uk

Follow this further

Built from Southwark's papers

What the report saysPro

Report to Cabinet (decommissioned, for the Executive after, 23 pages

Recommendations

1. The Cabinet approves the procurement strategy outlined in this report for the Supported Hostels security contract at an estimated annual value of £1.105m for a period of three years with the option to extend by a further period of up to two years, making a total estimated contract value of £5.525m.

2. The Cabinet approves the delegation of the Gateway Two award decision report to the Strategic Director of Housing in consultation with the Cabinet Member for Council Homes.

Reasons for recommendations

3. The reasons for the recommended procurement approach are detailed in paragraphs 29 and 30 of this report.

ALTERNATIVE OPTIONS CONSIDERED AND NOT RECOMMENDED

4. The alternative options considered for this procurement are set out in paragraphs 18 to 28 of this report.

POST DECISION IMPLEMENTATION

5. Once the recommendation(s) within this report have been approved:

i. There will be a procurement process followed by the award of a single contract. ii. The details of the planned contract management and monitoring regime are set out in paragraphs 82 to 89 of this report. iii. The timeline for implementation of this report is set out within the body of the report at paragraph 43.

BACKGROUND INFORMATION

6. The council currently operates five supported hostels in the Borough. Support is provided to residents living in these supported hostels for a range of complex support needs from domestic violence, substance misuse, mental health and offending.

7. The council insourced three of these Mental Health Homelessness Hostels in April 2022. Security at these three hostels is currently provided by the supplier that used to work for the previous hostels’ service provider. Security at the remaining two hostels is provided under a separate free-standing contractual arrangement with the council’s facilities management contractor’s security services sub-contractor via the council’s Corporate Facilities Management (CFM) Department.

Summary of the business case/justification for the procurement

8. There is a contractual need to reprovision three of these services and an opportunity, by simultaneously re-tendering the remaining two, to reshape and enhance provision for meeting the complex needs of residents with mental health, domestic violence and substance misuse issues.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Equalities Impact and Needs AnalysisAppendix 1 17 pages Download
PDF
Report: GW1 Supported Hostels Security February 2026Report 23 pages DownloadRead as text

At this meeting

Whole meeting

Who was there

10 of 21 attended
SK
Councillor Sarah King Leader of the CouncilChair, present
JA
Councillor Jasmine Ali Deputy Leader and Cabinet Member for Children, Education and RefugeesCommittee Member, present
EA
Councillor Evelyn Akoto Cabinet Member for Health and WellbeingCommittee Member, present
JB
Councillor John Batteson Cabinet Member for Climate Emergency, Jobs and BusinessCommittee Member, present
SC
Councillor Stephanie Cryan Cabinet Member for Equalities, Democracy and FinanceCommittee Member, present
EC
Councillor Ellie Cumbo Cabinet Member for Parks and CultureCommittee Member, present
HD
Councillor Helen Dennis Cabinet Member for New Homes and Sustainable DevelopmentCommittee Member, present
NE
Councillor Natasha Ennin Cabinet Member for Community Safety and NeighbourhoodsCommittee Member, present
JM
Councillor James McAsh Cabinet Member for Clean Air, Streets and WasteCommittee Member, present
PM
Councillor Portia Mwangangye Cabinet Member for Council HomesCommittee Member, present
DF
Doreen Forrester-BrownOfficer, expected
RC
Rhona CadenheadOfficer, expected

All 21 on the meeting page

On this subject at Southwark

Search all
  1. Gateway 1: Procurement Strategy Approval Security Cover in Supported HostelsThis decision
  2. Gateway 1 – Procurement Strategy Approval -The NestApproved
  3. Gateway 1 - Procurement Strategy Approval - Southwark and Lambeth Barristers FrameworkApproved
  4. Gateway 1 - Procurement Strategy Approval - Framework contracts to provide bailiff services to the Revenues & Benefits and Parking ServicesApproved
  5. Gateway 2: Contract Award Approval - Corporate Insurance Procurement (excluding Property Insurance)Approved
  6. Gateway 1 - Initial Procurement Strategy, Parking and Traffic Enforcement Services ContractAgreed

More from Southwark Cabinet (decommissioned, for the Executive after

All decisions
MeetingDecisionOutcome
28 May 2026 Election of Chair for the meetingThat Councillor Maisie Anderson be elected chair for this meeting. Decided Open
28 May 2026 Notification of any items of business which the chair deems urgentIt was agreed that all the deputations would be heard so that consideration of these representations could be given p... Agreed Open
28 May 2026 Disclosure of Interests and DispensationsDecision Maker (IDM) report in respect of this issue. Councillor Peter John also declared a personal, non prejudicial... Decided Open
28 May 2026 Review of Void Disposal StrategyThat the progress of disposals of void housing properties since April 2009 be noted. 2. That the importance of void d... Noted Open
28 May 2026 Housing Revenue Account - Approval of Housing Revenue Budget Account 2011/12That the savings required to deliver a balanced housing revenue account (HRA) for 2011/12 be noted. 2. That the propo... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies