London Borough of Southwark
Cabinet (decommissioned, for the Executive after, Thursday 28 May 2026 at 3.00pm

Phase 2 of the Tustin Estate Renewal Update

Noted Executive 2 papers

AI summarySouthwark Cabinet agrees £164.5m main works contract with BY Development Limited for Phase 2 of the Tustin Estate, delivering 284 new homes from May 2026.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedFour blocks, with break clause for three
Money£164,499,943Main works, five years from May 2026
What happens nextEarly works January 2026, main works May 2026Break clause decision by end of October 2026
Who it affectsTustin Estate residents and wider borough284 new homes in Phase 2, demolition of two blocks

What was decided

Cabinet agreed the council should enter into the Phase 2 main works contract with BY Development Limited in the estimated sum of £164,499,943, for five years from May 2026. Report P4, P63

Cabinet noted Phase 1 is about to complete, delivering 167 new homes, including 157 council homes for social rent and 10 homes for resident leaseholders. Report P2, P23

Cabinet noted the main works contract will include separate prices for each of the four Phase 2 blocks, with a break clause exercisable before the end of October 2026 to exclude blocks F1, F2 and H. Report P5, P32

Why

The redevelopment is part of the council's housing delivery programme and is expected to deliver significant benefits, including improved housing quality, while avoiding higher future costs. Report P6, P7, P8

The scheme provides the best balance of competing factors after modelling work over the last 18 months, and was supported by Cabinet in December 2025. Report P10, P11

Bids to the GLA secured an additional £29.64m of grant funding, bringing Phase 2 grant support to £54.6m. Report P67, P68

What happens next

The council will enter the Phase 2 early works contract in the sum of £10,668,322 from January 2026, then start demolition of Heversham House and Kentmere House in April 2026. Report P14, P16, P18

The main works contract can be entered into once demolition finishes and the Building Safety Regulator signs off detailed designs through Gateway 2, anticipated May 2026. Report P17, P18, P31

Before exercising the break clause on blocks F1, F2 and H, the council will work out and scrutinise the final cost of Phase 2b. Report P32, P64

The money

  • £164,499,943 Estimated cost of the Phase 2 main works contract Report P4, P63
  • £10,668,322 Previously approved Phase 2 early works contract Report P14, P63
  • £76,041,345 Final cost of Phase 2a (Block G2) Report P64
  • £88,458,598 Indicative cost of Phase 2b (Blocks F1, F2 and H) Report P64
  • £54.6m Total GLA grant funding committed to Phase 2 Report P68
  • £29.64m Additional GLA grant funding secured beyond the original £24.96m Report P67
  • £73m Total GLA grant allocated to affordable housing across all Tustin phases Report P69

Options considered

  • Chosen: Phase 2 scheme as set out in this report. Provides the best balance of competing factors after modelling over the last 18 months and was supported by Cabinet in December 2025. Report P4, P10, P11

Implications

  • Financial: Upfront investment for Phase 2 is higher, but the revised plan is expected to reduce future costs for later phases and helps manage HRA cashflow and borrowing costs. Report P80, P81
  • Legal: Sharpe Pritchard is providing legal advice on the use of Compulsory Purchase Order powers as a last resort where voluntary agreement with leaseholders cannot be reached. Report P15, P53, P62
  • Equalities: An updated Equality and Health Impact Assessment has been carried out and rehousing policies are in place to mitigate impacts on tenants and leaseholders, including vulnerable residents. Report P50, P53, P54
  • Climate: Phase 2 proposals will reduce carbon emissions by 85% beyond Part L 2021 Building Regulations. Report P60
  • Risk: The break clause before the end of October 2026 allows the council to exclude, delay or change blocks F1, F2 and H, providing a control on Phase 2b costs. Report P32, P64
  • Other: A General Fund bid and potentially an Educational Capital bid will be made for the replacement school, which is in Phase 3. Report P71

Who and where

  • Existing Tustin Estate tenants and leaseholders in Heversham House and Kentmere House, facing rehousing and possible CPO action as a last resort Report P15, P48, P50
  • Future residents of 284 new homes in Phase 2, including 279 council homes for social rent and 5 homes for resident leaseholders Report P7
  • Wider Tustin Estate community, including the Residents Project Team and Tustin Estate Community Association, consulted on the scheme Report P72
  • Borough residents, through the council's wider housing delivery programme Report P8, P42

Timeline

  • October 2022: Overall development agreement signed with Bouygues Development for all four phases Report P13, P22
  • January 2026: Phase 2 early works contract entered into (£10,668,322) Report P14, P18
  • January 2026: First residents due to move into Phase 1 homes Report P23
  • April 2026: Demolition of Heversham House and Kentmere House starts Report P18
  • May 2026: Phase 2 main works construction contract entered into (commencement of five-year period) Report P4, P18
  • End of October 2026: Latest date to exercise the break clause to exclude blocks F1, F2 and H Report P5, P32
  • 2033: Overall programme completion extended to this year under the revised plan Report P81

Plain English for the jargon

  • BY Development Limited: Trading name of BYUK Development Ltd., the council's development partner for the Tustin Estate Renewal, part of Bouygues Development.
  • Phase 2a: Sub-phase of the Tustin Estate redevelopment covering Block G2 only.
  • Phase 2b: Sub-phase of the Tustin Estate redevelopment covering Blocks F1, F2 and H.
  • Building Safety Regulator Gateway 2: Statutory design sign-off stage for higher-risk buildings under the Building Safety regime.
  • Compulsory Purchase Order (CPO): Legal power the council may use as a last resort to obtain vacant possession of properties needed for the redevelopment.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item13

Resolved

That it be noted that since the development agreement was signed in October 2022, the Tustin Estate Renewal has been progressing well on site, and that Phase 1 is about to complete and will deliver 167 new homes, including 157 council homes for social rent, and 10 homes for resident leaseholders. 2. That it be noted that the council will enter into the Phase 2 early works contract a s referred to in the 2 December 2025 cabinet report. 3. That it be agreed the council should enter into the Phase 2 main works contract with BY Development Limited in the estimated sum of £164,499,943 for a period of five years, commencing May 2026. 4. That it be noted that the main works contract will include the construction of all four blocks within Phase 2, but will include separate prices for the development of each of the four blocks within Phase 2, with a break clause that can be exercised before the end of October 2026 to exclude blocks F1, F2 and H.
Word for word from the decision Southwark published for this meeting. Source: moderngov.southwark.gov.uk

Follow this further

Built from Southwark's papers

What the report saysPro

Report to Cabinet (decommissioned, for the Executive after, 10 pages

Recommendations

Recommendations for the Cabinet

1. The cabinet note that since the development agreement was signed in October 2022, the Tustin Estate Renewal has been progressing well on site, 1 and that Phase 1 is about to complete and will deliver 167 new homes, including 157 council homes for social rent, and 10 homes for resident leaseholders.

2. The cabinet notes that the council will enter into the Phase 2 early works contract as referred to in the 2 December 2025 Cabinet report.

3. The cabinet agrees that the council should enter into the Phase 2 main works contract with BY Development Limited in the estimated sum of £164,499,943 for a period of five years, commencing May 2026.

4. The cabinet note the main works contract will include the construction of all four blocks within Phase 2, but will include separate prices for the development of each of the four blocks within Phase 2, with a break clause that can be exercised before the end of October 2026 to exclude Blocks F1, F2 and H.

Reasons for recommendations

5. As referred to in previous Cabinet reports the Tustin Estate redevelopment is expected to create significant benefits, including improving housing quality.

6. As agreed in a previous Cabinet report work has already started on Phase 2. Phase 2 will deliver 284 new homes including 279 council homes for social rent, and 5 homes for resident leaseholders. The additional report was needed because the council required more time to agree Phase 2a.

7. It should also be noted that the Tustin Estate redevelopment forms a key part of the council’s housing delivery programme. If the development were not to proceed, these numbers, the remaining affordable homes which have not yet been built, would need to be delivered at an alternative time in the future, likely for significantly more cost.

ALTERNATIVE OPTIONS CONSIDERED AND NOT RECOMMENDED

8. Over the last 18 months various options have been modelled, and this resulted in a report that was considered by Cabinet in December 2025.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Tustin Masterplan ImageAppendix 1 1 pages Download
PDF
Report: Phase 2 of the Tustin Estate RenewalReport 10 pages DownloadRead as text

At this meeting

Whole meeting

Who was there

10 of 21 attended
SK
Councillor Sarah King Leader of the CouncilChair, present
JA
Councillor Jasmine Ali Deputy Leader and Cabinet Member for Children, Education and RefugeesCommittee Member, present
EA
Councillor Evelyn Akoto Cabinet Member for Health and WellbeingCommittee Member, present
JB
Councillor John Batteson Cabinet Member for Climate Emergency, Jobs and BusinessCommittee Member, present
SC
Councillor Stephanie Cryan Cabinet Member for Equalities, Democracy and FinanceCommittee Member, present
EC
Councillor Ellie Cumbo Cabinet Member for Parks and CultureCommittee Member, present
HD
Councillor Helen Dennis Cabinet Member for New Homes and Sustainable DevelopmentCommittee Member, present
NE
Councillor Natasha Ennin Cabinet Member for Community Safety and NeighbourhoodsCommittee Member, present
JM
Councillor James McAsh Cabinet Member for Clean Air, Streets and WasteCommittee Member, present
PM
Councillor Portia Mwangangye Cabinet Member for Council HomesCommittee Member, present
DF
Doreen Forrester-BrownOfficer, expected
RC
Rhona CadenheadOfficer, expected

All 21 on the meeting page

On this subject at Southwark

Search all
  1. Phase 2 of the Tustin Estate Renewal UpdateThis decision
  2. Phase 2b of the Tustin Estate Renewal and Phase 2 AppropriationNoted

More from Southwark Cabinet (decommissioned, for the Executive after

All decisions
MeetingDecisionOutcome
28 May 2026 Election of Chair for the meetingThat Councillor Maisie Anderson be elected chair for this meeting. Decided Open
28 May 2026 Notification of any items of business which the chair deems urgentIt was agreed that all the deputations would be heard so that consideration of these representations could be given p... Agreed Open
28 May 2026 Disclosure of Interests and DispensationsDecision Maker (IDM) report in respect of this issue. Councillor Peter John also declared a personal, non prejudicial... Decided Open
28 May 2026 Review of Void Disposal StrategyThat the progress of disposals of void housing properties since April 2009 be noted. 2. That the importance of void d... Noted Open
28 May 2026 Housing Revenue Account - Approval of Housing Revenue Budget Account 2011/12That the savings required to deliver a balanced housing revenue account (HRA) for 2011/12 be noted. 2. That the propo... Noted Open