AI summarySouthwark Cabinet agrees £164.5m main works contract with BY Development Limited for Phase 2 of the Tustin Estate, delivering 284 new homes from May 2026.
Written from the decision and the officer reportPDF Pro
OutcomeNotedFour blocks, with break clause for three
Money£164,499,943Main works, five years from May 2026
What happens nextEarly works January 2026, main works May 2026Break clause decision by end of October 2026
Who it affectsTustin Estate residents and wider borough284 new homes in Phase 2, demolition of two blocks
What was decided
Cabinet agreed the council should enter into the Phase 2 main works contract with BY Development Limited in the estimated sum of £164,499,943, for five years from May 2026. Report P4, P63
Cabinet noted Phase 1 is about to complete, delivering 167 new homes, including 157 council homes for social rent and 10 homes for resident leaseholders. Report P2, P23
Cabinet noted the main works contract will include separate prices for each of the four Phase 2 blocks, with a break clause exercisable before the end of October 2026 to exclude blocks F1, F2 and H. Report P5, P32
Why
The redevelopment is part of the council's housing delivery programme and is expected to deliver significant benefits, including improved housing quality, while avoiding higher future costs. Report P6, P7, P8
The scheme provides the best balance of competing factors after modelling work over the last 18 months, and was supported by Cabinet in December 2025. Report P10, P11
Bids to the GLA secured an additional £29.64m of grant funding, bringing Phase 2 grant support to £54.6m. Report P67, P68
What happens next
The council will enter the Phase 2 early works contract in the sum of £10,668,322 from January 2026, then start demolition of Heversham House and Kentmere House in April 2026. Report P14, P16, P18
The main works contract can be entered into once demolition finishes and the Building Safety Regulator signs off detailed designs through Gateway 2, anticipated May 2026. Report P17, P18, P31
Before exercising the break clause on blocks F1, F2 and H, the council will work out and scrutinise the final cost of Phase 2b. Report P32, P64
The money
£164,499,943 Estimated cost of the Phase 2 main works contract Report P4, P63
£10,668,322 Previously approved Phase 2 early works contract Report P14, P63
£76,041,345 Final cost of Phase 2a (Block G2) Report P64
£88,458,598 Indicative cost of Phase 2b (Blocks F1, F2 and H) Report P64
£54.6m Total GLA grant funding committed to Phase 2 Report P68
£29.64m Additional GLA grant funding secured beyond the original £24.96m Report P67
£73m Total GLA grant allocated to affordable housing across all Tustin phases Report P69
Options considered
Chosen: Phase 2 scheme as set out in this report. Provides the best balance of competing factors after modelling over the last 18 months and was supported by Cabinet in December 2025. Report P4, P10, P11
Implications
Financial: Upfront investment for Phase 2 is higher, but the revised plan is expected to reduce future costs for later phases and helps manage HRA cashflow and borrowing costs. Report P80, P81
Legal: Sharpe Pritchard is providing legal advice on the use of Compulsory Purchase Order powers as a last resort where voluntary agreement with leaseholders cannot be reached. Report P15, P53, P62
Equalities: An updated Equality and Health Impact Assessment has been carried out and rehousing policies are in place to mitigate impacts on tenants and leaseholders, including vulnerable residents. Report P50, P53, P54
Climate: Phase 2 proposals will reduce carbon emissions by 85% beyond Part L 2021 Building Regulations. Report P60
Risk: The break clause before the end of October 2026 allows the council to exclude, delay or change blocks F1, F2 and H, providing a control on Phase 2b costs. Report P32, P64
Other: A General Fund bid and potentially an Educational Capital bid will be made for the replacement school, which is in Phase 3. Report P71
Who and where
Existing Tustin Estate tenants and leaseholders in Heversham House and Kentmere House, facing rehousing and possible CPO action as a last resort Report P15, P48, P50
Future residents of 284 new homes in Phase 2, including 279 council homes for social rent and 5 homes for resident leaseholders Report P7
Wider Tustin Estate community, including the Residents Project Team and Tustin Estate Community Association, consulted on the scheme Report P72
Borough residents, through the council's wider housing delivery programme Report P8, P42
Timeline
October 2022: Overall development agreement signed with Bouygues Development for all four phases Report P13, P22
January 2026: Phase 2 early works contract entered into (£10,668,322) Report P14, P18
January 2026: First residents due to move into Phase 1 homes Report P23
April 2026: Demolition of Heversham House and Kentmere House starts Report P18
May 2026: Phase 2 main works construction contract entered into (commencement of five-year period) Report P4, P18
End of October 2026: Latest date to exercise the break clause to exclude blocks F1, F2 and H Report P5, P32
2033: Overall programme completion extended to this year under the revised plan Report P81
Plain English for the jargon
BY Development Limited: Trading name of BYUK Development Ltd., the council's development partner for the Tustin Estate Renewal, part of Bouygues Development.
Phase 2a: Sub-phase of the Tustin Estate redevelopment covering Block G2 only.
Phase 2b: Sub-phase of the Tustin Estate redevelopment covering Blocks F1, F2 and H.
Building Safety Regulator Gateway 2: Statutory design sign-off stage for higher-risk buildings under the Building Safety regime.
Compulsory Purchase Order (CPO): Legal power the council may use as a last resort to obtain vacant possession of properties needed for the redevelopment.
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item13
Resolved
That it be noted that since the development agreement was signed in October 2022, the Tustin Estate Renewal has been progressing well on site, and that Phase 1 is about to complete and will deliver 167 new homes, including 157 council homes for social rent, and 10 homes for resident leaseholders. 2. That it be noted that the council will enter into the Phase 2 early works contract a s referred to in the 2 December 2025 cabinet report. 3. That it be agreed the council should enter into the Phase 2 main works contract with BY Development Limited in the estimated sum of £164,499,943 for a period of five years, commencing May 2026. 4. That it be noted that the main works contract will include the construction of all four blocks within Phase 2, but will include separate prices for the development of each of the four blocks within Phase 2, with a break clause that can be exercised before the end of October 2026 to exclude blocks F1, F2 and H.
Word for word from the decision Southwark published for this meeting.Source: moderngov.southwark.gov.uk
Report to Cabinet (decommissioned, for the Executive after, 10 pages
Recommendations
Recommendations for the Cabinet
1. The cabinet note that since the development agreement was signed in October 2022, the Tustin Estate Renewal has been progressing well on site, 1 and that Phase 1 is about to complete and will deliver 167 new homes, including 157 council homes for social rent, and 10 homes for resident leaseholders.
2. The cabinet notes that the council will enter into the Phase 2 early works contract as referred to in the 2 December 2025 Cabinet report.
3. The cabinet agrees that the council should enter into the Phase 2 main works contract with BY Development Limited in the estimated sum of £164,499,943 for a period of five years, commencing May 2026.
4. The cabinet note the main works contract will include the construction of all four blocks within Phase 2, but will include separate prices for the development of each of the four blocks within Phase 2, with a break clause that can be exercised before the end of October 2026 to exclude Blocks F1, F2 and H.
Reasons for recommendations
5. As referred to in previous Cabinet reports the Tustin Estate redevelopment is expected to create significant benefits, including improving housing quality.
6. As agreed in a previous Cabinet report work has already started on Phase 2. Phase 2 will deliver 284 new homes including 279 council homes for social rent, and 5 homes for resident leaseholders. The additional report was needed because the council required more time to agree Phase 2a.
7. It should also be noted that the Tustin Estate redevelopment forms a key part of the council’s housing delivery programme. If the development were not to proceed, these numbers, the remaining affordable homes which have not yet been built, would need to be delivered at an alternative time in the future, likely for significantly more cost.
ALTERNATIVE OPTIONS CONSIDERED AND NOT RECOMMENDED
8. Over the last 18 months various options have been modelled, and this resulted in a report that was considered by Cabinet in December 2025.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Cabinet (decommissioned, for the Executive after at Southwark and we tell you when its next papers are published, before the meeting rather than after it.
Review of Void Disposal StrategyThat the progress of disposals of void housing properties since April 2009 be noted. 2. That the importance of void d...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.