Acquisition of the Plot H1 Elephant and Castle Health Centre
ApprovedExecutive2 papers
AI summarySouthwark Cabinet approves in principle acquiring the shell and core of the Elephant and Castle Health Centre from developer Hub using strategic CIL, with detailed terms and fit out subject to later business cases.
Written from the decision and the officer reportPDF Pro
OutcomeApproved
MoneyAcquisition cost in closed reportRejected option estimated at c£1,000,000 per year rent and outgoings
What happens nextFull business case requiredDelegated to cabinet member for equalities, democracy and finance before committal
Who it affectsElephant and Castle residentsTwo existing GP practices to relocate into new health centre
What was decided
Cabinet approved in principle acquiring a 250 year lease of the Elephant and Castle Health Centre shell and core from developer Hub, to be funded through strategic CIL. Report P1, P95
Detailed terms and the fit out cost were made subject to separate business cases, with decisions delegated to the cabinet member for equalities, democracy and finance in consultation with the strategic director of resources and the director of planning and growth. Report P2, P3, P4, P102
Cabinet noted the council's intention to use strategic CIL to fund the fit out, and delegated negotiations and final terms for an under lease of the premises at market rent to the NHS to the director of planning and growth. Report P5, P6, P23, P24
Why
The council has committed under the Elephant and Castle and Walworth Town Centre Action Plan to delivering a new health centre, supported by NHS South East London ICB, which would replace two older premises in poor repair. Report P7, P51, P73, P84, P85
The NHS cannot give the developer a legally binding forward commitment, and without council action the health centre is unlikely to be delivered on Plot H1, the final plot in the Heygate regeneration programme. Report P9, P10, P11, P14, P15, P27, P30
Acquiring the shell and core gives the council a long term income stream from a strong covenant tenant, and flexibility to use the space for private healthcare or commercial use if the NHS does not take it. Report P8, P12, P53, P65, P66, P77
What happens next
Negotiate an agreement for lease with Hub based on the agreed heads of terms, then seek delegated authority from the strategic director of resources to exchange the agreement. Report P21, P32
Once planning is consented, progress the fit out design in collaboration with the NHS, the developer and GP partners, with a separate business case covering the fit out cost. Report P4, P22, P59
Progress the under lease with NHS South East London ICB and GP tenants ahead of practical completion, with terms finalised by the director of planning and growth. Report P6, P23, P24
The money
c£1,000,000 Annual rent and outgoings estimate for the rejected 25 year fitted out lease option Report P16
£1m Strategic CIL previously allocated to Southwark Pensioners Centre at 201 to 203 Camberwell Road Report P40
500,000 Strategic CIL allocation to Pensioners Centre shown in the allocations to date table Report P44
1,250,000 Strategic CIL allocation to Harold Moody Health Centre shown in the allocations to date table Report P44
11,650,000 Total strategic CIL allocated to date excluding Bakerloo Line Extension Report P44
2,653,563 Total strategic CIL allocated to date for Bakerloo Line Extension Report P44
Options considered
Chosen: Acquire the shell and core of the health centre on market terms, funded through strategic CIL. Allows delivery to proceed while giving the council a long term asset, income stream and flexibility of use if the NHS does not take the premises Report P7, P8, P9, P10, P12, P32
Rejected: Take a 25 year lease of the fully fitted out health centre on commercial terms, guaranteeing the developer. Council would be bound to take the lease on practical completion without a guaranteed tenant, with open ended financial risk and reduced incentive for the developer to negotiate with the NHS Report P16, P17, P18
Rejected: Do nothing. The NHS cannot give a legally binding forward commitment, so the developer would not deliver the health centre and it would not be provided at Elephant and Castle Report P14, P15
Implications
Financial: Both acquisition and fit out are intended to be funded from strategic CIL so no additional burden falls on the council capital budget; SCIL drawdown is forecast between 2029 and 2032 and staffing costs sit within existing revenue budgets. Report P59, P60, P103
Legal: Acquisition is supported by section 120 Local Government Act 1972, any future disposal must secure best consideration under section 123, and spending strategic CIL on medical facilities is permitted under regulation 59 CIL Regulations 2010 and section 216 Planning Act 2008. Report P96, P97, P98, P99
Equalities: The Public Sector Equality Duty has been considered across all protected characteristics and an Equality Impacts and Needs Assessment is appended; the new facility is expected to improve access and safety for patients currently in poor premises. Report P75, P76, P77, P85
Climate: The premises will be in a modern building with air source heat pumps rather than gas central heating, and are in a location with strong public transport links that reduce the need for private car journeys. Report P87, P88
Risk: Four project risks are identified: failure to agree terms with the developer, planning not achieved, premises not delivered to required specification, and the NHS being unable to take a lease; mitigations are set out for each. Report P68
Other: Plot H1 is classed as a Higher Risk Building under the Building Safety Act 2022, and the health centre is expected to be treated as an independent section so its fit out may avoid the BSA gateway process. Report P46, P47, P48, P49, P50
Who and where
Existing patients of two GP practices at Elephant and Castle, who will relocate from old, poor condition premises into the new health centre with expanded services Report P73, P84, P85, P78, P79, P80
NHS South East London ICB and local GP tenants, expected to take an under lease at market rent from the council Report P7, P23
Developer Hub, the long leaseholder of Plot H1 since December 2024, who will deliver the shell and core Report P28, P29, P32
London Borough of Southwark, which will own the asset and receive a long term income stream to the general fund Report P8, P53, P109
Timeline
July 2010: Council entered regeneration agreement with Lendlease for the Heygate masterplan Report P27
November 2023: Lendlease granted planning consent 21/AP/1819 for an office led scheme including a new health centre Report P27
December 2024: Hub acquired the long leasehold interest in Plot H1 from Lendlease Report P28
March 2026: H1 residential led planning application 25/AP/2859 expected to be determined at committee Report P28, P34
28 May 2026: Cabinet approves acquisition in principle
2029 to 2032: Forecast drawdown period for strategic CIL for the acquisition Report P60
Q2 2030: Hub is targeting practical completion of the building Report P34
2031 to 2032: Estimated opening to the public after a further 12 to 18 months of fit out Report P34
Plain English for the jargon
Strategic CIL: Strategic Community Infrastructure Levy, 70 per cent of CIL receipts allocated to borough wide infrastructure such as transport and health facilities
CIL: Community Infrastructure Levy, a charge on major developments used to fund new infrastructure to support growth
Shell and core: A building delivered to a basic finished state with services in place but not fitted out for the occupier
ICB: Integrated Care Board, the NHS body responsible for planning local NHS services, here NHS South East London ICB
MOU: Memorandum of Understanding, a non binding statement of intent used in lieu of a legally binding lease commitment
AfL: Agreement for Lease, a conditional contract setting out the terms on which a lease will be granted
HRB: Higher Risk Building under the Building Safety Act 2022, subject to gateway approvals at planning, construction and completion
INT: Integrated Neighbourhood Team, co located primary care, community health, mental health, social care and voluntary sector teams
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item12
Resolved
That the acquisition of premises for the Elephant and Castle Health Centre delivered to shell and core using strategic community infrastructure levy (CIL) be approved. 2. That the negotiations of detailed terms be subject to a full business case, prior to formal committal, and delegated to the c abinet member for equalities, democracy and finance in consultation with the strategic director of resources and the director of planning and growth be approved. 3. That finalising the fit-out cost is subject to a business case at a later stage be delegated to c abinet member for equalities, democracy and finance in consultation with the strategic director of resources and the director of planning and growth be approved. 4. That it noted that it is the intention of the council to use strategic community infrastructure levy (CIL) to fund the fitting out of the premises. 5. That taking forward of negotiations and finalising terms with the relevant NHS body for an under lease of the premises at a market rent from the council be delegated to the director of planning and growth.
Word for word from the decision Southwark published for this meeting.Source: moderngov.southwark.gov.uk
Report to Cabinet (decommissioned, for the Executive after
Recommendations
That the cabinet: 1. Approves the acquisition of premises for the Elephant & Castle Health Centre delivered to shell and core using Strategic CIL.
2. Approve that the negotiations of detailed terms be subject to a full business case, prior to formal committal, and delegated to Cabinet Member for
1 Equalities, Democracy & Finance in consultation with the Strategic Director of Resources and the Director of Planning and Growth.
3. Approves that finalising the fit-out cost is subject to a business case at a later stage delegated to Cabinet Member for Equalities, Democracy & Finance in consultation with the Strategic Director of Resources and the Director of Planning and Growth.
4. Notes that it is the intention of the council to use Strategic CIL to fund the fitting out of the premises.
5. Approves that taking forward of negotiations and finalising terms with the relevant NHS body for an under lease of the premises at a market rent from the council be delegated to the Director of Planning and Growth.
Reasons for recommendations
6. The council has made a commitment to deliver a new state of the art health centre as set out in the Elephant and Castle and Walworth Town Centre Action Plan (Background Papers). This objective is supported by the NHS South East London ICB (ICB) who have included the site within their strategic plan for the borough will provide the council with a memorandum of understanding (MOU) reflecting their desire to take a lease for a new health centre in due course.
7. As set out in the Closed Report, the valuation of a new health centre let to the NHS on market terms is anticipated to be in excess of the costs of purchasing and fitting out the premises making this a potentially profitable long term investment for the council.
8. As one of the final plots to be brought forward in the Heygate regeneration programme, there are limited other opportunities in the future for the council to secure the delivery of the health centre at Elephant and Castle. This proposed acquisition of a shell and core building, delivered to shell and core on market terms, will enable the council to deliver the new health centre at Elephant and Castle.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Cabinet (decommissioned, for the Executive after at Southwark and we tell you when its next papers are published, before the meeting rather than after it.
Review of Void Disposal StrategyThat the progress of disposals of void housing properties since April 2009 be noted. 2. That the importance of void d...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.