Apologies
To receive any apologies for absence.
Southwark Cabinet approved £256m for heating and water contracts and a £40m communal heating framework. It agreed to bring later Aylesbury Estate phases back under council control and approved £12.88m for mental health housing, the Elephant and Castle Health Centre acquisition in principle, and around 50 alms houses for older people.
What the committee will consider, in order, with every paper attached to its item. End of Term Report 2022 - 2026 is the main business; one item may be taken in private.
To receive any apologies for absence.
In special circumstances, an item of business may be added to an agenda within five clear working days of the meeting.
To note the items specified which will be considered in a closed meeting.
Members to declare any interests and dispensations in respect of any item of business to be considered at this meeting.
To approve as a correct record the minutes of the open section of the meeting held on 2 February 2026.
Decision: That the minutes of the meeting held on 2 February 2026 be approved as a correct record and signed by the chair. Decision page
To receive any questions from members of the public which have been submitted in advance of the meeting in accordance with the cabinet procedure rules. The deadline for the receipt of public questions is midnight Tuesday 10 March 2026.
To consider any deputation requests. To consider any deputation requests. The deadline for the receipt of deputation requests is midnight Tuesday 10 March 2026.
To consider a petition.
Decision: That the petition submitted by Clive Rates and Tristan Honeybourne about Dulwich Village High Street, requesting Southwark Council offer more free parking, remove road restrictions and reverse parking charges in Dulwich Park be considered. Councillor John Batteson, cabinet member for climate emergency, jobs and transport responded to the petition at the meeting, reinforcing his commitment to continue working with local businesses, the trader’s association, residents, ward councillors and the... Decision page
To notethe reportincluding progressof the c orporate p arenting s trategy,areas of focus for 2025 and work of the corporate parenting committee.
Decision: That the reportincluding progressof c orporate p arenting s trategy,areas of focus for 2025 and work of the corporate parenting committee be noted. 2. That it be noted that achild and young person friendlyeasy readversion of thereport willbe sharedwidely with children in care and care leavers andmade publicly available and easily accessible on the council’s website. 3. That changes to Southwark council’s housing allocations scheme, which will see care leavers have access to one-bed properties... Decision page
To note the council’s performance and delivery against the Council Delivery Plan commitments as outlined in the end of term report.
Decision: That the council’s performance and delivery against our council delivery plan commitments as outlined in our end of term report (Appendix 1 of the report) be noted. Decision page
To approve the basis of the variation to the Development Partnership Agreement (DPA), which will see the developer complete three phases of the estate renewal (Plot 18, FDS C, Phase 2B) and for the future phases (Phases 2C, 3 and 4) of the estate renewal to return to the control of the council.
Decision: That the basis of the variation to the development partnership agreement (DPA) be agreed, which will see the developer complete three phases of the estate renewal (Plot 18, FDS C, Phase 2B) and for the future phases (Phases 2C, 3 and 4) of the estate renewal to return to the control of the council, as detailed in paragraph 17 of the report. 2. That authority be delegated to negotiate and approve a proposal for the variation of the development partnership agreement (DPA) to the strategic... Decision page
To approve the acquisition of premises for the Elephant and Castle Health Centre delivered using strategic community infrastructure levy (CIL).
Decision: That the acquisition of premises for the Elephant and Castle Health Centre delivered to shell and core using strategic community infrastructure levy (CIL) be approved. 2. That the negotiations of detailed terms be subject to a full business case, prior to formal committal, and delegated to the c abinet member for equalities, democracy and finance in consultation with the strategic director of resources and the director of planning and growth be approved. 3. That finalising the fit-out cost is... Decision page
To agree that the council will work with United St Saviour’s Charity (USTSC) to explore the feasibility of bringing forward new Older People’s Housing developments on the sites at 1 Ann Moss Way and 153-159 Abbeyfield Road, drawing on the principles of the Appleby Blue development.
Decision: That it be agreed that the council will work with United St Saviour’s Charity (USTSC) to explore the feasibility of bringing forward new Older People’s Housing developments on the sites at 1 Ann Moss Way and 153-159 Abbeyfield Road, drawing on the principles of the Appleby Blue development. 2. That it be noted that this work will assess the potential to deliver approximately 50 homes at social rent levels, subject to site capacity, financial viability and wider programme considerations. 3. That... Decision page
To approve the award of eight contracts for the delivery of mental health supported housing provision.
Decision: That the award of eight contracts for the delivery of mental health supported housing provision be approved. The contracts will commence on 6 July 2026 , for a period of either four or five years as shown in the table in paragraph ? 2 of the report, with an option to extend for a further two years, for an estimated maximum annual contract value of £1.95m and a whole life contract value inclusive of extensions of £12.88m. 2. Contracts recommended for award: Four-year contracts to align with... Decision page
To approve the procurement strategy to undertake a procurement exercise for eight heating and water repairs, maintenance, refurbishment and replacement work contracts.
Decision: That the procurement strategy outlined in the report to undertake a procurement exercise for eight heating and water repairs, maintenance, refurbishment and replacement be approved. Work contracts for the lots referred to below, each for an initial period of five years from 5 April 2027 (at an estimated combined total of £112m for the initial period) with the option to extend for up to a further five years (at an estimated combined total of £144m for the extension period), making a total... Decision page
To consider the responses to the recommendations of the housing, community safety and community engagement commission: Southwark Community Safety Partnership.
Decision: That the response to recommendations 1-10 of the overview and scrutiny committee be noted. Decision page
To consider the responses to the recommendations in respect of the overview and scrutiny committee report.
Decision: That all recommendations made by the overview and scrutiny committee as set out in the report be agreed. Decision page
That the press and public be excluded from the meeting for the following items of business on the grounds that they involve the likely disclosure of exempt information as defined in categories 3 and 5 of paragraph 10.4 of the access to information procedure rules of the Southwark Constitution. The following is a summary of the decisions taken in the closed part of the meeting.
To approve as a correct record the closed minutes of the meeting held on 2 February 2026.
Item 10 is where most of this meeting's papers sit: 3 papers, about 39 MB.
To note the council’s performance and delivery against the Council Delivery Plan commitments as outlined in the end of term report.
This is the first time this subject appears in the meetings we have read.
Get the decision the day it is recorded, and anything that comes back to the committee on this subject.
All 24 papers in one list, with the item each belongs to, its size, and our copy of it. Download any paper from our archive once signed in; read and search it here with Pro.
Every Cabinet (decommissioned, for the Executive after meeting we have read, the dates it has set for the future, and each time those dates have changed.
Choose what you want to hear about. The preview is built from this committee's real papers and changes, so you can see what would have reached you.
Southwark, Cabinet (decommissioned, for the Executive after
One alert, sent weekly, on titles and decisions.
Unlimited alerts the same day, searching every page.
Your team, with every match pushed into your own tools.
Every council's records in your own products and research.
Papers, decisions and date changes for the Cabinet (decommissioned, for the Executive after, and every other committee you follow, the day they appear.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.