AI summarySouthwark Cabinet agrees to end the developer's role on later Aylesbury Estate phases, keeping Plot 18, FDS C and Phase 2B with the developer and bringing Phases 2C, 3 and 4 back to the council.
Written from the decision and the officer reportPDF Pro
OutcomeAgreedFuture phases return to council control
MoneyFinancial contribution to developer requiredAmount set out in closed version of the report
What happens nextNot stated
Who it affectsAylesbury Estate residents and renewal programmeAround 4,200 new homes planned overall
What was decided
The Cabinet approved the basis of varying the Development Partnership Agreement so the developer finishes Plot 18, FDS C and Phase 2B, and hands back Phases 2C, 3 and 4 to the council. Report P2
Authority to negotiate and approve the variation was delegated to the Strategic Director of Housing, in consultation with the Strategic Director of Resources. Report P3
The Cabinet noted that a further report will come to a later meeting on how the future phases will be delivered. Report P4
Why
The change lets the council take the rest of the estate forward with alternative delivery partners. Report P5, P34
A judicial review, R (Dennis) v London Borough of Southwark, was upheld, finding that the drop-in full planning application for Phase 2B would be physically incompatible with the Outline Planning Permission. Report P27
Section 106 for Phase 2B was agreed and awaiting formal GLA approval in February 2026 before a decision notice could be issued. Report P26
What happens next
Write formally to the developer to accept the Heads of Terms, instruct solicitors to prepare the deed of variation, agree a communications strategy, and get the deed ready for signature. Report P10, P11, P12
Review existing information on Phase 2C and develop a high-level programme of activities, including vacant possession of 1-240 Wendover, completing the housing needs survey, procuring a demolition contractor and setting out routes to market. Report P37, P38, P39
Complete the Equalities Impact Assessment, including health impacts, to inform the future programme. Report P23, P47, P49
The money
50% affordable housing by habitable room Overall masterplan target for the estate renewal Report P20
640 new homes Planned on Phase 2B, 41% affordable by number, 50% by habitable rooms Report P31
321 new homes Planned on FDS C, 131 affordable with 100% council nomination rights to 56 social rent homes Report P32
1,041 homes Already delivered across Sites 1A and 7, FDS A and B, and Plot 18 Report P24
around 4,200 new homes Total planned across the Aylesbury Estate renewal Report P16, P20
Options considered
Rejected: Continue with the Development Partnership Agreement in its current form. Not recommended, to allow the council to take the rest of the estate forward with alternative delivery partner/s Report P7, P5
Chosen: Vary the DPA so the developer completes Plot 18, FDS C and Phase 2B, with future phases returning to the council. Enables the council to take forward the remainder of the estate with alternative delivery partner/s Report P2, P5, P30, P31, P32, P33, P34
Implications
Financial: A financial contribution to Notting Hill Genesis to end its involvement in the future phases will be required; the basis is set out in the closed version of the report and the council will meet the cost through existing capital programme arrangements, which may require re-profiling of the Housing Investment Programme. Report P63, P64, P65
Legal: Any future proposals for Phases 2C, 3 and 4 will be subject to the council's contract standing orders, and a further judicial review claim on Phase 2B could be lodged within 6 weeks of the decision notice. Report P28, P61
Equalities: An Equality Impact Assessment, including socio-economic and health impacts, is under way to inform the future programme and the Public Sector Equality Duty under the Equality Act 2010 applies. Report P46, P47, P48, P49, P60
Climate: Phases 2B and FDS C are being taken forward using air source heat pumps, photovoltaic panels, Sustainable Urban Drainage systems and reuse of existing built material, and council involvement of future phases allows the rest of the rebuilding to meet the highest possible sustainability standards. Report P52, P53, P54
Risk: Re-profiling the Housing Investment Programme may temporarily reduce capacity to deliver some housing-related capital schemes within the year, though gaining full control of the future phases is expected to reduce long-term operational and programme risk. Report P65
Who and where
Residents of the Aylesbury Estate, including 9 remaining occupants of 1-240 Wendover and 7 leasehold interests to be acquired for Phase 2C Report P38, P39
Notting Hill Genesis (NHG), the current development partner Report P58, P63
Future residents of around 4,200 new homes planned under the estate renewal, including 50% affordable homes by habitable room Report P16, P20
The local community, to be re-engaged on a revised vision for the estate Report P45
Timeline
2004: Council approved the Aylesbury Estate renewal Report P15
2010: Aylesbury Area Action Plan adopted by Southwark Council Report P17
2014: Second developer entered into the Development Partnership Agreement with the council Report P15
2015: Outline planning permission granted for the masterplan Report P51
2017: Sites 1A and 7 completed; council took the decision to acquire FDS A and B from the developer Report P15, P25
2019: FDS C was demolished and cleared Report P32
February 2026: Section 106 for Phase 2B was awaiting formal GLA approval Report P26
3 March 2026: Final report dated and sent to the Constitutional Team Report P72
2026-05-28: Cabinet decision to vary the DPA
Plain English for the jargon
DPA: Development Partnership Agreement, the contract between the council and the developer for the Aylesbury Estate renewal
FDS: First Development Sites, the earlier phases of the estate renewal
AAAP: Aylesbury Area Action Plan, the 2010 planning framework for the renewal
OPP: Outline Planning Permission, the overarching planning consent for the whole estate
Section 106: A planning obligation agreement between a developer and the local authority
JR: Judicial Review, a court challenge to the lawfulness of a decision
EQIA: Equality Impact Assessment, used to assess equalities, socio-economic and health impacts
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item11
Resolved
That the basis of the variation to the development partnership agreement (DPA) be agreed, which will see the developer complete three phases of the estate renewal (Plot 18, FDS C, Phase 2B) and for the future phases (Phases 2C, 3 and 4) of the estate renewal to return to the control of the council, as detailed in paragraph 17 of the report. 2. That authority be delegated to negotiate and approve a proposal for the variation of the development partnership agreement (DPA) to the strategic director of housing, in consultation with the strategic director of resources. 3. That it be noted that a report will be presented to a future cabinet meeting on the revised way forward for delivering the future phases of the Aylesbury Estate.
Word for word from the decision Southwark published for this meeting.Source: moderngov.southwark.gov.uk
Report to Cabinet (decommissioned, for the Executive after
Recommendations
Recommendations for the Cabinet
1. That the Cabinet approves the basis of the variation to the Development Partnership Agreement (DPA), which will see the developer complete three phases of the estate renewal (Plot 18, FDS C, Phase 2B) and for the future phases (Phases 2C, 3 and 4) of the estate renewal to return to the control of the 1 council, as detailed in paragraph 17.
2. That the Cabinet delegates authority to negotiate and approve a proposal for the variation of the Development Partnership Agreement (DPA) to the Strategic Director of Housing, in consultation with the Strategic Director of Resources.
3. That the council’s Cabinet notes that a report will be presented to a future Cabinet meeting on the revised way forward for delivering the future phases of the Aylesbury Estate.
Reasons for recommendations
4. As set out in the background section, to enable the council to take forward the remainder of the estate with alternative delivery partner/s.
ALTERNATIVE OPTIONS CONSIDERED AND NOT RECOMMENDED
5. To continue with the DPA in its current form.
POST DECISION IMPLEMENTATION
6. The table below sets out the key activities that will take place, subject to the necessary Cabinet approval.
Key Activity Write formally to the developer to accept the Heads of Terms to the DPA deed of variation Instruct solicitors to prepare the deed of variation
Communications strategy agreed with the developer to publicise the revised DPA.
Deed of variation to the DPA ready for signature.
BACKGROUND INFORMATION
7. The Aylesbury Estate renewal programme is transforming the 1960s housing estate, once known for its poor condition and outdated infrastructure, into a modern, mixed-tenure neighbourhood. Led by Southwark Council with its development partners.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Cabinet (decommissioned, for the Executive after at Southwark and we tell you when its next papers are published, before the meeting rather than after it.
Review of Void Disposal StrategyThat the progress of disposals of void housing properties since April 2009 be noted. 2. That the importance of void d...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.