Executive, Tuesday 13 October 2026 at 11.00am

Phase 2b of the Tustin Estate Renewal and Phase 2 Appropriation

Noted Executive 3 papers

AI summarySouthwark Council approved deferring 41 council homes in the F blocks from Phase 2b to Phase 3 [D] [P13]. Updated Phase 2b main works cost is £66,601,435, and the land's purpose will change from housing to planning, then back to housing [D].

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedBlock H proceeds; 41 homes deferred [D] [P13] [P29].
Money£66,601,435 [D]Down from £88,458,598 [D].
What happens nextUse contract break clause [D]Defer 41 council homes to Phase 3 [D] [P13].
Who it affectsTustin Estate residents [D]243 homes and nearby property rights [P27] [P34] [P44].

What was decided

The council noted that it entered the Phase 2 main works contract with BY Development Limited (Bouygues) in March 2026. It approved using the break clause to defer the F blocks to Phase 3. These blocks contain 41 council homes. Report P12, P13

The council noted that the updated Phase 2b main works cost is £66,601,435, rather than £88,458,598 in the February 2026 executive update. Report P76

The council confirmed that the land shown edged red in Appendix A is no longer required for housing purposes. It approved changing the land from housing purposes to planning purposes under section 226 of the Town and Country Planning Act 1990 and section 122(1) of the Local Government Act 1972. After that change is complete, it approved changing the land back to housing purposes under section 9 of the Housing Act 1985 and section 122(1) of the Local Government Act 1972. Report P46

Why

The updated strategy lets the council and Bouygues continue the estate renewal while maintaining commitments to residents [P1] [P8]. Phase 2b forms part of the council's housing delivery programme [P3]. If Phase 2b did not proceed, 133 new council homes for social rent would be delivered at another time, likely at significantly more cost [P3]. Report P1, P3, P8

Concerns about the design and viability of the F blocks led to their deferral [P29]. Moving them to Phase 3 allows time to redesign and reassess them and to finalise long term plans for Pilgrims' Way Primary School [P30]. Further efficiency savings for Block H are unlikely, so proceeding with it helps prevent delays and keeps the programme on schedule [P31] [P32]. Report P29, P30, P31, P32

Where section 203 applies, affected parties cannot seek an injunction to delay or stop the development, but they can seek compensation [P4]. The council considered appropriation proportionate and justified because it reduces delay and cost risk and gives greater certainty [P10]. Report P4, P10

What happens next

Use the Phase 2 main works contract break clause to defer the F blocks and their 41 council homes to Phase 3 [P13] [P88]. Report P13, P88

Formally submit Phase 2b to the Building Safety Regulator through the Building Safety Gateway [P14]. The target for Block H is February 2027 [P16]. Report P14, P16

Carry out the change from housing to planning purposes, then change the land back to housing after completion [D] [P46]. Make budget provision for any compensation claims for reduced property values [P84]. Report P46, P84

The money

  • £66,601,435 Updated Phase 2b main works cost following removal of the F blocks from Phase 2b. The F block sites will be left with piling mats and require further work. Report P76, P77
  • £142,642,780 Updated total for Phase 2 main works. Report P75, P76
  • £88,458,598 Earlier Phase 2b cost recorded in the February 2026 executive update.
  • £26.6m Greater London Authority grant funding attributable to Phase 2b. Report P110
  • £47.6m Greater London Authority grant funding for Phase 2. Report P80
  • £73m Total Greater London Authority grant allocated across all phases. Report P80
  • £164,499,943 Estimated Phase 2 main works contract approved in February 2026. Report P74
  • £76,041,345 Phase 2a cost. Report P76

Options considered

  • Chosen: Proceed with Block H in Phase 2b and defer the F blocks to Phase 3. Concerns about design and viability led to deferral. It allows redesign and reassessment and time to finalise long term plans for Pilgrims' Way Primary School. Report P29, P30
  • Chosen: Change the land to planning purposes and later change it back to housing. This enables section 203 where its conditions are met, reducing injunction risk while preserving compensation rights. Report P4, P10, P24
  • Rejected: Do not appropriate the land, insure against claims and accept potential injunction delays. This could cause lengthy delays and significantly increased costs. An injunction might also succeed and stop the development. Report P10
  • Rejected: Do not proceed with Phase 2b. The 133 new council homes for social rent would need delivery at another time, likely at significantly more cost. Report P3

Implications

  • Financial: The revised strategy improves short term affordability by reducing immediate financing requirements and Housing Revenue Account borrowing pressures. Report P109
  • Financial: Phase 2 is funded from resources supporting the Housing Investment Programme and a Greater London Authority grant. The grant is expected to reduce the council funding required. Report P78, P110
  • Financial: The F blocks remain part of the wider programme. Future reports must determine their funding and affordability. Report P111
  • Risk: Viability depends on regulatory approvals, construction inflation, asbestos and ground condition risks, together with compliance with grant funding conditions. Material cost pressures must be managed through approved project contingencies, compensating savings or future budget approvals. Report P112
  • Financial: The two appropriations cause no net debt transfer because they occur on the same day. The budget must provide for compensation claims for reduced property values. Report P84, P85
  • Legal: Appropriation enables section 203 to override certain third party rights when its conditions are met [P4] [P24]. Where it applies, affected parties can claim compensation instead of seeking an injunction, and the council will pay their professional adviser fees for rights of light claims [P40] [P44]. Report P4, P24, P40, P44
  • Equalities: The updated Equality and Health Impact Assessment identifies positive and negative differential effects for groups with protected characteristics [P64]. Relevant mitigation measures are embedded in the programme, and impacts will continue to be monitored [P63] [P64]. Report P63, P64
  • Climate: The Phase 2 proposals provide more energy efficient housing [P70]. They reduce carbon emissions by 85% beyond Part L 2021 Building Regulations [P71]. Report P70, P71

Who and where

  • Residents of the Tustin Estate Report P17, P18
  • People needing 238 council homes for social rent Report P34
  • Returning leaseholders needing 5 shared equity homes Report P34
  • Owners or lessees of properties with potential rights of light impacts Report P44
  • People claiming loss of value from interference with a right Report P45
  • People needing 53 council homes and 7 homes for returning leaseholders in later phases Report P37
  • Council Housing Revenue Account and General Fund Report P85
  • Pilgrims' Way Primary School Report P30

Timeline

  • October 2022: Development agreement entered with Bouygues for all four phases. Report P19
  • December 2025: Phase 2 changed to 100% affordable housing and split into two sub phases. Report P21
  • February 2026 and March 2026: Phase 2 main works contract approved, then entered into. Report P12, P74
  • 10th and 17th September 2026: Public appropriation notices appeared in Southwark News. Report P47
  • 1 October 2026, 4.00pm: Deadline for representations or objections, with none received to date. Report P47
  • February 2027: Building Safety Gateway submission target for Block H Phase 2b. Report P16
  • September 2027: Phase 2b site start target. Report P16
  • April 2030: Phase 2b practical completion target. Report P16

Plain English for the jargon

  • Appropriation: Changing the purpose for which a council holds land [P24].
  • Break clause: A contract term allowing the council to exclude, delay or change remaining blocks [P12].
  • Building Safety Gateway: The route for formally submitting Phase 2b to the Building Safety Regulator [P14].
  • Section 203 of the Housing and Planning Act 2016: A power allowing development despite interference with certain rights, subject to conditions, with compensation instead [P4].
  • Rights of light: Rights that affected owners or lessees may claim have been interfered with [P44].
  • F blocks: The Phase 2b blocks deferred to Phase 3, containing 41 council homes [P13] [P29].
  • Block H: The Phase 2b block that the council will proceed with [P29].
  • Phase 2b: The sub phase containing Block H after the F blocks are deferred [P29] [P35].
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item12

Resolved

The it be noted that the council entered into the Phase 2 main works contract for the Tustin Estate Renewal with BY Development Limited ( Bouygues) in March 2026. 2. That an updated delivery strategy for Phase 2b which utilises the break clause in the main works contract to defer the F blocks from Phase 2b to Phase 3, as detailed at paragraph 28 of the report be approved. 3. That the updated cost for the Phase 2b main works is £66,601,435 rather than £88,458,598 as in the February 2026 executive update be noted. 4. The that the land shown edged red on the plan at Appendix A of the report (“the Land”) known as part of the Tustin Estate that is currently held for housing purposes be confirmed as no longer required for those purposes and the appropriation of the land from housing to planning purposes to facilitate the carrying out of the development proposals for the area in accordance with section 226 of the Town and Country Planning Act 1990 (“TCPA 1990”) and section 122(1) of the Local Government Act 1972 be approved. 5. That following completion of the appropriation at paragraph 4 of the report, it be confirmed that the land will no longer be required for planning purposes and the appropriation of the Land back to housing purposes in accordance with section 9 of the Housing Act 1985 and section 122(1) of the Local Government Act 1972 be approved.
Word for word from the decision Southwark published for this meeting. Source: moderngov.southwark.gov.uk

Follow this further

Built from Southwark's papers

What the report saysPro

Report to Executive

Reasons for recommendations

6. The updated strategy allows the council and Bouygues to move forward with the Tustin Estate Renewal.

7. As referred to in previous Executive reports, the Tustin Estate Renewal is expected to create significant local benefits.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Tustin Phase 2 Appropriation PlanAppendix A 510 KB Download
PDF
Tustin Phase 2 Appropriation rationaleAppendix B 120 KB Download
PDF
Report: Phase 2b of the Tustin Estate Renewal and Phase 2 AppropriationReport 224 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

0 of 10 attended
JM
Councillor James McAsh Leader of the CouncilChair, expected
VC
Councillor Victor Chamberlain Deputy Leader and Executive Member for Neighbourhoods, Strategic Planning, and WellbeingVice-Chair, expected
AA
Councillor Alexandra Austin Executive Member for Public Works and New HomesCommittee Member, expected
RB
Councillor Rachel Bentley Executive Member for Inclusive Economy, Equalities and DemocracyCommittee Member, expected
RC
Councillor Rebecca Corn Executive Member for Education and CareCommittee Member, expected
SF
Councillor Sam Foster Executive Member for Finance and General PurposesCommittee Member, expected
RP
Councillor Reginald Popoola Executive Member for Council HomesCommittee Member, expected
VT
Councillor Vanessa Threadgold Executive Member for Parks and RecreationCommittee Member, expected
EW
Councillor Eloise Waldon-Day Executive Member for Council Co-ordination and ClimateCommittee Member, expected
DW
Councillor David Watson Executive Member for Community Safety and EngagementCommittee Member, expected

On this subject at Southwark

Search all
  1. Phase 2b of the Tustin Estate Renewal and Phase 2 AppropriationThis decision
  2. Phase 2 of the Tustin Estate Renewal UpdateNoted

More from Southwark Executive

All decisions
MeetingDecisionOutcome
13 Oct 2026 MinutesThat the minutes of the meeting held on 15 September 2026 be approved as a correct record and signed by the chair. Approved Open
13 Oct 2026 Deputation requestsRESOLVED - That the written statement from Andrew Eke be heard. Deputation to Southwark Council Executive – Tustin Es... Decided Open
13 Oct 2026 Beormund School Expansion and RelocationThat the proposals to relocate and expand the Beormund Special Primary School be agreed. Agreed Open
13 Oct 2026 Gateway 1 - Highway works contractThat the procurement strategy outlined in the report for the provision of Highways Works be approved, comprising: · L... Approved Open
13 Oct 2026 Climate Change Strategy & Action Plan Update and Annual ReportThat the contribution of communities, schools, businesses and council services in tackling the climate crisis over th... Noted Open