Community Wellbeing and Housing Committee approved this item on Tuesday 7 January 2025. Below is the council's own wording, with the papers it was decided on.
Option 1 carried (Non-Combustible Timber Upstand) The Committee voted on the options in relation to the grass protection barrier as follows: Option 1: 0 Option 2: 0 Option 3: 0 Option 4: 11 Option 4 carried with the amendment to explore alternative hedging options Committee resolved to: 1. Approve option one and a budget of £3000 in relation to the sauna coals. 2. Approve option 4, subject to exploring alternative hedging solutions and a budget of £10,000 in relation to the barrier to protect the turfed area. 3. Delegate approval of the final solution in relation to the design barrier to protect the turfed area to the Group Head Community Wellbeing in consultation with the Chair and Vice Chair of Community Wellbeing and Housing Committee. The Committee adjourned at 20:23 and readjourned at 20:33. Councillor Brennan left the meeting at 20:33.
Word for word from the decision Spelthorne published for this meeting.Source: democracy.spelthorne.gov.uk
Report to Community Wellbeing and Housing Committee
Community Wellbeing & Housing Committee 7 January 2025 Corporate Policy and Resources Committee 20 January 2025
Title Eclipse Leisure Centre Additional Spend Purpose of the report To make a decision Report Author Kamal Mehmood – Strategic Lead for Leisure & Community Development Richard Mortimer – Asset Management Ward(s) Affected All Wards Exempt No Exemption Reason N/A Corporate Priority Services Recommendations Committee is asked to: Community Wellbeing Housing Committee (CWHC) 1. To approve preferred options and budget of £3,000 in relation to the sauna coals. 2. Delegate approval of the final solution in relation to the design of barrier to protect the turfed area to the Group Head of Community Wellbeing and Housing in consultation with the Chair and Vice Chair of Community Wellbeing and Housing Committee. 3. To approve preferred options and budget of £10,000 in relation to the barrier to protect the turfed area. Corporate Policy and Resources Committee (CPRC) 4. To note expenditure agreed by CWHC and to note the updated budget position for the construction of Eclipse leisure centre. Reason for To enable works to be completed as soon as possible and to note Recommendation the up to date budget position for phase 1 of the leisure centre project; and to ensure the centre is fully operational at the earliest opportunity.
1. Summary of the report
What is the situation Why we want to do something
• Whilst the Leisure Centre is fully compliant • Whilst fully compliant with planning with Building Regulations and has been obligations, officers were required to approved by planners, certain areas of the address Place’s concerns regarding certain Eclipse Leisure Centre have remained operational issues in order to complete the cordoned off since its opening on 15th Leisure Operator Contract (LOC) and avoid October over the operator’s concerns. a delay to the full opening of the new • These items are included as part of a centre. schedule of agreed works under the • Whilst the facilities remain closed or are leisure centre operating contract. The cordoned off costs are being incurred and Council is required to address the matter the operator can potentially seek damages of the sauna and the rooflight within 6 beyond the period in which the work can months of opening. be completed. The faster the issues can be • In addition, it has been suggested that resolved the lower the claim for additional barrier should be installed to compensation will be. deter people from walking on the grass at the front of the building.
This is what we want to do about it These are the next steps
• Undertake agreed works to satisfy Place’s Once approved: specific operational requirements and • Orders will be placed allow full use of the whole leisure centre. • The work will be undertaken • A number of options have been costed in • Restrictions lifted and facilities opened each case and the committee are asked to • Claims for compensation will be considered confirm which of the options they would like to be taken forward in each instance.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Follow Community Wellbeing and Housing Committee at Spelthorne and we tell you when its next papers are published, before the meeting rather than after it.
Disabled Facility Grant Policy UpdateThe Committee resolved to: 1. Note the outcome of investigations undertaken following the June 2026 Committee Meeting...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.