Eclipse Leisure Centre Additional Spend

Approved Committee 11 papers

Community Wellbeing and Housing Committee approved this item on Tuesday 7 January 2025. Below is the council's own wording, with the papers it was decided on.

Item8/25

Resolved

Option 1 carried (Non-Combustible Timber Upstand) The Committee voted on the options in relation to the grass protection barrier as follows: Option 1: 0 Option 2: 0 Option 3: 0 Option 4: 11 Option 4 carried with the amendment to explore alternative hedging options Committee resolved to: 1. Approve option one and a budget of £3000 in relation to the sauna coals. 2. Approve option 4, subject to exploring alternative hedging solutions and a budget of £10,000 in relation to the barrier to protect the turfed area. 3. Delegate approval of the final solution in relation to the design barrier to protect the turfed area to the Group Head Community Wellbeing in consultation with the Chair and Vice Chair of Community Wellbeing and Housing Committee. The Committee adjourned at 20:23 and readjourned at 20:33. Councillor Brennan left the meeting at 20:33.
Word for word from the decision Spelthorne published for this meeting. Source: democracy.spelthorne.gov.uk

Follow this further

Built from Spelthorne's papers

What the report saysPro

Report to Community Wellbeing and Housing Committee

Community Wellbeing & Housing Committee 7 January 2025 Corporate Policy and Resources Committee 20 January 2025

Title Eclipse Leisure Centre Additional Spend Purpose of the report To make a decision Report Author Kamal Mehmood – Strategic Lead for Leisure & Community Development Richard Mortimer – Asset Management Ward(s) Affected All Wards Exempt No Exemption Reason N/A Corporate Priority Services Recommendations Committee is asked to: Community Wellbeing Housing Committee (CWHC) 1. To approve preferred options and budget of £3,000 in relation to the sauna coals. 2. Delegate approval of the final solution in relation to the design of barrier to protect the turfed area to the Group Head of Community Wellbeing and Housing in consultation with the Chair and Vice Chair of Community Wellbeing and Housing Committee. 3. To approve preferred options and budget of £10,000 in relation to the barrier to protect the turfed area. Corporate Policy and Resources Committee (CPRC) 4. To note expenditure agreed by CWHC and to note the updated budget position for the construction of Eclipse leisure centre. Reason for To enable works to be completed as soon as possible and to note Recommendation the up to date budget position for phase 1 of the leisure centre project; and to ensure the centre is fully operational at the earliest opportunity.

1. Summary of the report

What is the situation Why we want to do something

• Whilst the Leisure Centre is fully compliant • Whilst fully compliant with planning with Building Regulations and has been obligations, officers were required to approved by planners, certain areas of the address Place’s concerns regarding certain Eclipse Leisure Centre have remained operational issues in order to complete the cordoned off since its opening on 15th Leisure Operator Contract (LOC) and avoid October over the operator’s concerns. a delay to the full opening of the new • These items are included as part of a centre. schedule of agreed works under the • Whilst the facilities remain closed or are leisure centre operating contract. The cordoned off costs are being incurred and Council is required to address the matter the operator can potentially seek damages of the sauna and the rooflight within 6 beyond the period in which the work can months of opening. be completed. The faster the issues can be • In addition, it has been suggested that resolved the lower the claim for additional barrier should be installed to compensation will be. deter people from walking on the grass at the front of the building.

This is what we want to do about it These are the next steps

• Undertake agreed works to satisfy Place’s Once approved: specific operational requirements and • Orders will be placed allow full use of the whole leisure centre. • The work will be undertaken • A number of options have been costed in • Restrictions lifted and facilities opened each case and the committee are asked to • Claims for compensation will be considered confirm which of the options they would like to be taken forward in each instance.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
List of contractual operational works /25Appendix A 291 KB Download
PDF
Final /25Appendix B 46 KB Download
PDF
/25Appendix C 10 KB Download
PDF
/25Appendix D 708 KB Download
PDF
Eclipse Leisure Centre Additional SpendReport 475 KB DownloadRead as text
PDF
Eclipse Leisure centre- updated cover report /25Report 461 KB Download
PDF
View as HTML (8/25/2) 44 KBReport 44 KB Copy on its way
PDF
View as HTML (8/25/3) 253 KBAppendix 253 KB Copy on its way
PDF
View as HTML (8/25/5) 17 KBAppendix 17 KB Copy on its way
PDF
View as HTML (8/25/6) 19 KBAppendix 19 KB Copy on its way
PDF
View item 8/25 as HTML 47 KBReport 47 KB Copy on its way

At this meeting

Whole meeting

Who was there

12 of 15 attended
SD
Councillor Sue DoranChair, present
OR
Councillor Olivia RybinskiVice-Chair, apologies, sent representative
MA
Councillor Michelle ArnoldCommittee Member, present
MA
Councillor Maureen AttewellCommittee Member, present
CB
Councillor Chris BatesonCommittee Member, present
MB
Councillor Mary Bing DongCommittee Member, apologies
LB
Councillor Lisa BrennanCommittee Member, present
SD
Councillor Sandra DunnCommittee Member, present
AG
Councillor Adam GaleCommittee Member, present
RG
Councillor Rebecca GeachCommittee Member, present
KG
Councillor Kathy GrantCommittee Member, present
AM
Councillor Anant MathurCommittee Member, present

All 15 on the meeting page

On this subject at Spelthorne

Search all
  1. Eclipse Leisure Centre Additional SpendThis decision
  2. Eclipse Leisure Centre Safeguarding Follow-upDecided
  3. Eclipse Leisure Centre Additional SpendDecided
  4. Eclipse Leisure Centre FinancingNoted
  5. Solar Canopies Over 'Eclipse' Leisure Centre Car ParkDecided
  6. Implementation of Solar Canopies Over the 'Eclipse' Leisure Centre Car ParkAgreed

More from Spelthorne Community Wellbeing and Housing Committee

All decisions
MeetingDecisionOutcome
29 Sep 2026 Review of Community Safety Partnership Plan & Priorities 2026The Committee resolved to receive the progress update contained in the report. Decided Open
29 Sep 2026 Leisure Operating Contract Review April 2025-March 2026The Committee resolved to receive Places for People Leisure ( PfP ) Annual Report for the period April 2025 to March ... Decided Open
29 Sep 2026 Procurement Framework for Nightly-Paid AccommodationThe Committee resolved not to make a recommendation to Council on this item and agreed that further details would be ... Agreed Open
29 Sep 2026 Community Grants Mapping Across Surrey Authorities: Section 24 Position and Decisions Required from Sovereign AuthoritiesThe Committee resolved to: 1. Approve the continuation of the Council’s existing Community Grant Programme (as approv... Approved Open
29 Sep 2026 Disabled Facility Grant Policy UpdateThe Committee resolved to: 1. Note the outcome of investigations undertaken following the June 2026 Committee Meeting... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies