CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Stevenage Borough Council
Executive (up to May 2024), Wednesday 5 September 2018 at 2.00pm

1ST QUARTER CAPITAL PROGRAMME MONITORING REPORT 2018/19 - GENERAL FUND AND HOUSING REVENUE ACCOUNT

Approved Executive 3 papers

Executive (up to May 2024) approved this item on Wednesday 5 September 2018. Below is the council's own wording, with the papers it was decided on.

Item8

Resolved

The Executive considered a report that provided an update on the Council’s 2018/19 and 2019/20 Capital Programme, and sought approval for revisions to the General Fund and Housing Revenue Account Capital Programme. In response to a query raised by the Leader, the Assistant Director (Finance & Estates) undertook to provide Executive Members with clarification regarding the Boiler upgrade/replacement schemes for St. Nicholas Community Centre and Springfield House. It was As contained in the report. Other Options considered: As contained in the report. As contained in the report. Other Options considered: As contained in the report.
Word for word from the decision Stevenage published for this meeting. Source: democracy.stevenage.gov.uk

Follow this further

Built from Stevenage's papers

What the report saysPro

Report to Executive (up to May 2024)

Recommendations

2.1That the 2018/19 General Fund capital programme net decrease in expenditure of £ 798,260 be approved as summarised in paragraph 4.1.1.

2.2That the virement from the deferred works Budget of £49,000 and for Multi Storey Car Park £12,140 as summarised in paragraph 4.1.5 and 4.1.6 be approved.

2.3The General Fund re profiling of capital expenditure to 2019/20 of £1,627,500 as summarised in table one, be approved.

2.4That Members note that there is no increase in the capital expenditure for 2019/20 Housing Revenue Account, as summarised in table two.

Background

3.1The 2018/19 capital programme was approved at the July Executive:  General Fund £32,805,510  Housing Revenue Account £23,227,800

Executive 5 September 2018 Part I Release to Press

3.2Subsequently Council approved an increase of £2,900,000 as detailed in 4.2.1, this brings the current working budget to £26,127,800.

4. REASONS FOR RECOMMENDED COURSE OF ACTION AND OTHER OPTIONS

4.12018/19 General Fund Capital Programme

4.1.1 The updated projection for 2018/19 General Fund capital programme (as detailed in Appendix A) is £32,007,250, a reduction of £798,260 due to:  Vehicle/plant replacement programme brought forward to 2018/19 from future years (+£567,740). Following an extensive review of the vehicle requirements for Stevenage Direct Services, the capital programme was reduced by £1.2million over the three year programme and incorporated into the capital report to the July Executive.  Regeneration schemes (- £1,366,000) re-profiled to match the wider SG1 phasing of works (see also para 4.1.2).

Changes to General Fund Capital Budget Increase Increase (Decrease) to (Decrease) to Capital Programme Change to 2018/19 Working Budget & 2019/20 2018/19 2019/20 Projected Budget Working Projected Budget Budget £ £ Slippage Vehicle replacements – revised delivery programme 567,740 261,500 Town Square Improvements (1,000,000) 1,000,000 Leisure Centre GD1 (400,000) 400,000 Old Town Parking Permit Implementation (11,000) 11,000 Multi Storey Car Park 45,000 (45,000) Total Slippage (798,260) 1,627,500 Springfield House - Boiler Upgrade 14,000 Town Centre Toilets 15,000 Deferred Works Reserve (49,000) Multi Storey Car Park 12,140 Surface Car Parks (12,140) Total Virements Between Projects 0 0

Total Change in Working Budget and Projected Budgets (798,260) 1,627,500

Slippage:

4.1.2 Regeneration- Included in the works re-profiled to 2019/20 (£1,627,500) are regeneration projects for Town Centre improvements (£1,000,000) and Leisure Centre (£400,000). These schemes have been re-profiled to map the wider SG1 scheme and the work Mace, the Council’s SG1 developer, are undertaking. Improvement works to the multi storey car park originally scheduled for 2019/20 have been brought forward to 2018/19.

Executive 5 September 2018 Part I Release to Press 4.1.3 IT/Digital (Connected to our Customers (CTOC)) Programme – The capital programme has been amended to realign schemes between the IT improvement programme and the Connected to our Customers (CTOC)/Digital Agenda. The total schemes moved between Connected to our Customers (CTOC)/Digital programme and IT improvement budget amount to £324,600. There is a potential risk of slippage of Connected to our Customers (CTOC) budgets (£224,000). This has not been included in Appendix A but may be reported later on in the year when there’s more clarity around the timing of delivery.

Reductions in Expenditure:

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
1ST QUARTER CAPITAL PROGRAMME MONITORING REPORT 2018/19: GENERAL FUND AND HOUSING REVENUE ACCOUNTReport 155 KB DownloadRead as text
PDF
Item 8: Appendix A: Capital Strategy (Q1)Appendix 200 KB Download
PDF
Item 8: Appendix B: Capital Strategy (Q1)Appendix 157 KB Download

At this meeting

Whole meeting

Who was there

8 of 8 attended
ST
Sharon Taylor OBE CCChair, present
JL
Mrs Joan LloydCommittee Member, present
RB
Rob BroomCommittee Member, present
JG
John GardnerCommittee Member, present
RH
Richard HenryCommittee Member, present
JH
Jackie HollywellCommittee Member, present
RR
Ralph RaynorCommittee Member, present
JT
Jeannette ThomasCommittee Member, present

On this subject at Stevenage

Search all
  1. 1ST QUARTER CAPITAL PROGRAMME MONITORING REPORT 2018/19 - GENERAL FUND AND HOUSING REVENUE ACCOUNTThis decision
  2. 1st quarter revenue and capital monitoring report 2026/27 – general fund and hraApproved
  3. Second quarter monitoring report for general fund, housing revenue account and capital monitoringNoted
  4. First quarter revenue and capital monitoring report 2025/26 - general fund and hraApproved
  5. Third quarter revenue budget monitoring 2024/25 (including third quarter capital budget monitoring 2024/25)Decided
  6. Second quarter revenue budget monitoring 2024/25 (including second quarter capital budget monitoring 2024/25)Approved

More from Stevenage Executive (up to May 2024)

All decisions
MeetingDecisionOutcome
13 Mar 2024 Apologies for absence and declarations of interestApologies for absence were submitted on behalf of Councillors Richard Henry (Chair), Sandra Barr and [name removed]. ... Decided Open
13 Mar 2024 Minutes - 7 february 2024It was RESOLVED that the Minutes of the meeting of the Executive held on 7 February 2024 be approved as a correct rec... Approved Open
13 Mar 2024 Minutes of overview & scrutiny committee and select committeesThe Portfolio Holder for Environment and Performance thanked the Chair and Members of the Environment & Economy Selec... Noted Open
13 Mar 2024 Regeneration programme delivery updateThe Executive considered a report which provided an update on the projects within the Government’s Towns Fund program... Agreed Open
13 Mar 2024 Housing consumer standards - social housing (regulation) act 2023The Executive considered a report in respect of the Social Housing (Regulation) Act 2023, which introduced wide rangi... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies