The Cabinet received a report setting out the second quarter monitoring for the 2024/25 General Fund, Housing Revenue Account, and Capital and seeking approval for changes to 2024/25 working budgets. Members were advised that timing differences had resulted in some of the figures within the HRA appearing relatively high. These would be re-phased in the HRA Capital Programme with the funding allocated to be spent in later years. It was
Word for word from the decision Stevenage published for this meeting.Source: democracy.stevenage.gov.uk
2.1That the 2024/25 second quarter projected net decrease in General Fund expenditure of £292,080 be approved.
2.2That Members note the proposed movement on reserves as detailed in paragraph 4.2.1
2.3That Members approve the a revenue contribution to capital for garages of £104,870 to fund works within the Capital Garage Improvement Programme (paragraph 4.1.2).
Executive – 13 November 2024 Part I
Housing Revenue Account
2.4That the 2024/25 second quarter net decrease in HRA expenditure of £4,129,020 be approved.
Capital Programme
2.6That the General Fund capital budget re-phasing of £13Million from 2024/25 to future years be approved. 2.7. That the Housing Revenue Account capital budget re-phasing of £3.4Million from 2024/25 and £6Million from 2025/26 to future years be approved. 2.8. That the budget of £94.6K for remedial works, funded by developers’ contributions and £599K for the new spur road as part of Swingate works, funded by One Public Estate be noted (paragraphs 4.8.1 and 4.8.2). 2.9. That the General Fund capital budget virements in paragraph 4.9 be approved.
3. BACKGROUND - GENERAL FUND
3.1Since the General Fund net budget of £12,788,410 was approved at February Council, Members have approved net budget changes of £81,820 as detailed in the chart below:
Executive – 13 November 2024 Part I
4. REASONS FOR RECOMMENDED COURSE OF ACTION AND OTHER OPTIONS
4.1General Fund – Budget Review
4.1.1 Following the second quarter review of the General Fund budgets officers have identified a projected decrease in the forecast budget for the year of £292,080.
4.1.2 The primary reasons for the underspend are detailed below, with a full analysis of less significant variances available in Appendix A:
• Revenue Garages £55K - The latest forecast shows an additional £179K in rental income for garages this year, against an original budget of £3.835 million which was reduced by £86K for impact on asbestos garage. In the Quarter 1 report (to September Cabinet), an extra £75K in income was reported. The Chief Finance Officer approved a budget virement of £50K during October for additional garage repair works. Quarter 2 is reporting additional £55K of income. This surplus is attributed to improved occupancy rates, with only 7.5% of garages vacant at the end of September.
• Contribution to Capital (RCCO) Garages £105K – The latest forecast for capital repair works, including doors, facias, and soffits, shows an additional £105K pressure. These repairs are essential to keep the garages usable, but the number of repairs needed has increased due to the age of the garages, higher occupancy rates, and weather conditions over the past year.
• External Audit Fees £23K – The Council has been notified that External Audit Fees for 2024/25 will increase (following consultation) by the Public Sector Audit Appointments (PSAA) to cover additional audit work required under revised auditing standards and a contractual inflationary increase for 2024/25. This is on top of the 2% increase included in the 2024/25 Original budget.
Executive – 13 November 2024 Part I
• Other variances £64K – A breakdown of these smaller variances can be found in Appendix A.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.