Resolved
The Executive considered a report in respect of 1 st and 2 nd Quarter Capital Programme Monitoring 2021/22 (General Fund and Housing Revenue Account). It was As contained in report. Other Options considered: As contained in report.
Executive (up to May 2024) decided this item on Wednesday 20 October 2021. Below is the council's own wording, with the papers it was decided on.
Resolved
The Executive considered a report in respect of 1 st and 2 nd Quarter Capital Programme Monitoring 2021/22 (General Fund and Housing Revenue Account). It was As contained in report. Other Options considered: As contained in report.
2.1That Executive approve the 2021/22 General Fund capital programme net decrease in expenditure of £59K as summarised in table one, para 4.1.1.
2.2That Executive approve the General Fund net increase of capital expenditure of £271K in 2022/23, also as summarised in table one, para 4.1.1.
2.3That Executive recommend to Council approval of the additional General Fund budget requirements as set out in table two, para 4.2.1, of £291K.
2.4That Members approve the net decrease of £4.4 Million in the capital expenditure for 2021/22 Housing Revenue Account, as summarised in table nine, para 4.4.1.
2.5That Members approve the corresponding net increase of £4.4 Million in the capital expenditure for 2022/23 Housing Revenue Account, also as summarised in table nine, para 4.4.1.
Executive 20 October 2021 Part I Release to Press 3 BACKGROUND
3.1The 2021/22 approved working budget for the capital programme is: General Fund £22.4 Million Housing Revenue Account £58.3 Million
4. REASONS FOR RECOMMENDED COURSE OF ACTION AND OTHER OPTIONS
4.12021/22 General Fund Capital Programme 4.1.1 The updated projected spend for 2021/22 General Fund capital programme (as detailed in Appendix A) is £22.3Million, a net decrease of £59K. The change in budget is shown by Business Unit in table one:
Table One 2021/22 £'000 2022/23 £'000 Working Working General Fund Q2 Revised Q2 Revised budget Variance budget Variance Capital Programme Budget Budget (Q4) (Q4) £ £ £ £ £ £ Stevenage Direct 3,465,352 3,505,352 40,000 3,284,620 3,244,620 (40,000) Services Housing Development 7,051,059 7,051,059 0 13,256,607 13,256,607 0 Finance & Estates 2,172,370 2,284,020 111,650 351,750 694,850 343,100 Digital & 899,430 896,830 (2,600) 104,220 106,820 2,600 Transformation Regeneration 7,779,480 7,779,480 0 2,474,000 2,474,000 0 Communities & 364,440 364,440 0 275,000 275,000 0 Neighbourhoods Planning & 384,350 417,900 33,550 305,000 270,000 (35,000) Regulatory Deferred Works 264,860 23,310 (241,550) 200,000 200,000 0 Reserve Total 22,381,341 29,322,391 (58,950) 20,251,197 20,521,897 270,700
Further analysis between working budget and the revised budget are shown below.
4.1.2 Stevenage Direct Services (SDS) –
4.1.2.1 Budget of £40K brought forward on the Play Area Improvement Programme. This was a councillor request following vandalism to Campshill Park play area.
4.1.2.2 There are likely to be future financial pressures to address the asbestos issue in a number of Council garages. An assessment of the costs will be included in later reports once the course of action is finalised.
4.1.3 Finance & Estates –
4.1.3.1 Cavendish Road Fire protection works £250K: there is currently a budget of £340K in the capital programme for fire protection works, (plus £63K spent
Executive 20 October 2021 Part I Release to Press in earlier years). To complete the works at Cavendish Road the costs are now anticipated to be £653K in total. This is because the work to scope the fire protection works including installing fire suppression for the waste bays, replacing the partition walls between the waste bays and installing drainage to deal with the water runoff has now been completed. It is recommended to fund the works £250K from the Deferred Works Reserve. Using the deferred works reserve (an existing budget), means it is within the amount delegated to the Executive..
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
1ST AND 2ND QUARTER CAPITAL PROGRAMME MONITORING REPORT 2021/22Report | 471 KB | DownloadRead as text |
PDF |
General Fund Q1&2 for Exec uploadAppendix A | 432 KB | Download |
PDF |
HRA Q1&2 for Exec uploadAppendix B | 256 KB | Download |
Follow Executive (up to May 2024) at Stevenage and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 13 Mar 2024 | Apologies for absence and declarations of interestApologies for absence were submitted on behalf of Councillors Richard Henry (Chair), Sandra Barr and [name removed]. ... | Decided | Open |
| 13 Mar 2024 | Minutes - 7 february 2024It was RESOLVED that the Minutes of the meeting of the Executive held on 7 February 2024 be approved as a correct rec... | Approved | Open |
| 13 Mar 2024 | Minutes of overview & scrutiny committee and select committeesThe Portfolio Holder for Environment and Performance thanked the Chair and Members of the Environment & Economy Selec... | Noted | Open |
| 13 Mar 2024 | Regeneration programme delivery updateThe Executive considered a report which provided an update on the projects within the Government’s Towns Fund program... | Agreed | Open |
| 13 Mar 2024 | Housing consumer standards - social housing (regulation) act 2023The Executive considered a report in respect of the Social Housing (Regulation) Act 2023, which introduced wide rangi... | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.