CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Stockport Metropolitan Borough Council
Audit Committee, Wednesday 25 March 2026 at 6.00pm

Audit Progress Report

Noted Finance 1 paper

AI summaryAudit Committee noted external auditor's progress report confirming an unqualified opinion on 2024/25 accounts and proposed total fees of £407,802.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedAudit Committee noted the external auditor's progress report
Money£407,802 total proposed feesFor 2024/25, above the £353,760 scale fee
What happens next2025/26 audit planned for summer 2026Auditor's Annual Report due before 30 November 2026
Who it affectsNot stated

What was decided

The Committee noted the external auditor's progress report.

Forvis Mazars issued an unqualified opinion on the 2024/25 accounts and the Auditor's Annual Report on 12 December 2025. Report P6

The auditor and the Director of Finance agreed proposed total fees of £407,802 for 2024/25, to be considered by PSAA. Report P6, P17

Why

The 2024/25 financial statements audit and value for money work are complete, and the auditor found no significant weaknesses in arrangements. Report P6

The report sets out progress, fees and other services, and national publications for the Committee's awareness. Report P4, P3

No non-audit services were provided to the Council in the year. Report P18

What happens next

Planning for the 2025/26 financial statements audit commenced in March 2026, with fieldwork intended for summer 2026. Report P7

The auditor will report the timetable in the Audit Strategy Memorandum and aims to issue the Auditor's Annual Report before 30 November 2026. Report P7

PSAA will scrutinise and consider the proposed additional fees for 2024/25. Report P6, P7

The money

  • £353,760 PSAA scale fee for 2024/25 Report P9
  • £22,094 Additional work on Investment Property and Land and Buildings valuations, 2024/25 Report P10
  • £5,265 Additional work on pension asset ceiling, 2024/25 Report P11
  • £6,878 Additional fees for IFRS 16 Leases implementation, 2024/25 Report P12
  • £10,055 Additional work on group accounts under revised ISA 600, 2024/25 Report P13
  • £3,000 Additional work on valuation of MAHL shares and airport land, 2024/25 Report P15
  • £6,750 Additional work on prior period adjustments, 2024/25 Report P16
  • £407,802 Total proposed fees for 2024/25 Report P17

Options considered

  • Chosen: Note the external auditor's progress report. Recommended in the agenda to enable the Committee to be aware of audit progress, fees and publications.

Implications

  • Financial: Proposed total fees of £407,802 for 2024/25 exceed the £353,760 scale fee and are subject to PSAA scrutiny. Report P6, P7, P17
  • Legal: The NAO's revised Code of Audit Practice requires the Auditor's Annual Report to be issued by 30 November each year. Report P7
  • Risk: The 2024/25 audit closed significantly later than intended, and earlier completion in 2025/26 is a stated objective. Report P6, P7
  • Other: Auditor concluded the Council has proper value for money arrangements for the year to 31 March 2025, with no significant weaknesses identified. Report P6

Who and where

  • Stockport Metropolitan Borough Council as audited body Report P4, P6
  • Audit Committee members Report P4
  • Director of Finance, who agreed the proposed fees Report P6, P7
  • Public Sector Audit Appointments (PSAA), which scrutinises additional fees Report P6, P7

Timeline

  • 12 December 2025: Unqualified audit opinion and Auditor's Annual Report issued for 2024/25 Report P6
  • March 2026: Planning work commenced for the 2025/26 financial statements audit Report P7
  • Summer 2026: Intended timing of 2025/26 audit fieldwork Report P7
  • Before 30 November 2026: Auditor's Annual Report for 2025/26 to be presented to the Audit Committee Report P7

Plain English for the jargon

  • PSAA: Public Sector Audit Appointments, which sets and scrutinises local audit fees
  • NAO: National Audit Office, which issues the Code of Audit Practice
  • VFM: Value for Money, the auditor's assessment of arrangements to secure economical, efficient and effective use of resources
  • IFRS 16: Accounting standard on Leases, implemented in 2024/25
  • ISA 600: Auditing standard on group audits, revised for 2024/25
  • ISA 315 (Revised): Auditing standard on identifying and assessing risks of material misstatement
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item13

Resolved

RESOLVED – That the be noted.
Word for word from the decision Stockport published for this meeting. Source: democracy.stockport.gov.uk

Follow this further

Built from Stockport's papers

What the report saysPro

Report to Audit Committee

External Audit Progress Report Stockport Metropolitan Borough Council

March 2026 Contents

1. Audit progress 2. Audit fees and other services 3. National publications Audit progress 01 Audit progress

Purpose of this report This report provides the Audit Committee with information about progress in delivering our responsibilities as your external auditors.

Audit for the year ending 31 March 2025

Financial statements audit Members will be aware that we presented our Audit Completion Follow up Letter to the December 2025 Audit Committee meeting. The report identified the work that was outstanding at that time. We completed that outstanding work and did not identify any further matters to report to members. We issued an unqualified audit opinion on 12 December 2025. We also issued our Auditor’s Annual Report on the same date. Having completed the audit we have considered the impact of the work completed on the audit fees. Public Sector Audit Appointment Ltd (PSAA) determine the scale fee for the Council’s audit and publish this each November. The scale fee covers the work required as the Council’s appointed auditor under the NAO Code of Audit Practice. The scale fee for 2024/25 was set at £353,760. Work on additional audit risks and to respond to recent changes in accounting or auditing standards is not covered by the scale fee and is subject to additional audit fees. PSAA scrutinise our proposed additional fees and consider whether to approve them. We have agreed the proposed fees, set out in section 2 of this update report, with the Director of Finance. Value for money arrangements Our work on the Council’s value for money arrangements for 2024/25 is also complete. Our Auditor’s Annual Report for the 2024/25 audit, which contains our commentary on the arrangements the Council has in place to secure value for money in its use of resources, is being reported to the March Audit Committee meeting. We concluded the Council has proper arrangements in place for the year to 31 March 2025, and we did not identify any significant weaknesses in those arrangements.

Audit for the year ending 31 March 2026 We commenced our planning work for the 2025/26 financial statement audit in March 2026. We will discuss and agree the dates for our audit work with management as part of our planning procedures and will report the timetable in our Audit Strategy Memorandum. At this stage our intention is to carry out the Council’s audit in the summer period in order to complete the audit significantly earlier than for the 2024/25 audit year. Completing the Council’s audit earlier in 2025/26 is a key objective for us, and we will discuss the detailed plan with the finance team. The NAO’s revised Code of Audit Practice from 2024/25, requires auditors to issue their Auditor’s Annual Report, which includes commentary on the Council’s Value for Money arrangements, by 30 November each year. We plan to complete our work on the VFM arrangements and present this report to the Audit Committee in advance of 30 November 2026. Audit fees and other services 02 Audit fees and other services Fees for our work as the Council’s auditor 2024/25 Public Sector Audit Appointments (PSAA) determine the scale fee for the Council’s audit and publish this each November. The scale fee covers the work required as the Council’s appointed auditor under the NAO Code of Audit Practice. The scale fee for 2024/25 was set at £353,760. Having completed our work for 2024/25 we have set out our proposed fees below. The proposed fees have been agreed with the Director of Finance and will be scrutinised and considered by PSAA.

Area of work 2024/25 proposed fees 2023/24 actual fees

PSAA Scale fee £353,760 £326,438

Additional work in respect of Investment Property and Land & Building valuations £22,094 £16,200

Additional work relating to the Council’s pension asset ceiling £5,265 £7,500

Additional fees in respect of IFRS 16 (Leases) implementation £6,878 -

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Audit Progress ReportReport 580 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

8 of 9 attended
SG
Councillor Sue GlitheroChair, present
CM
Councillor Carole McCannVice-Chair, present
MJ
Councillor Mark JonesCommittee Member, present
HK
Councillor Huma KhanCommittee Member, present
PW
Councillor Paul WrightCommittee Member, present
AW
Councillor Alex WynneCommittee Member, apologies, sent representative
PM
Philip Mills Co-opted MemberCo-Optee, present
CH
Carol HargreavesSecretary, expected
CM
Councillor Colin MacAlisterCommittee Member, present

On this subject at Stockport

Search all
  1. Audit Progress ReportThis decision
  2. Internal Audit Progress Report 4Noted

More from Stockport Audit Committee

All decisions
MeetingDecisionOutcome
25 Mar 2026 2025/26 Statement of Accounts - Accounting PoliciesRESOLVED ( i ) That the report be noted (ii) That the Council’s proposed accounting policies as set out in Appendix O... Noted Open
25 Mar 2026 Update on the council's Annual Governance Action Plan 2025/26It was agreed that for future meetings, a report containing a timetable that officers work to, together with details ... Agreed Open
25 Mar 2026 Internal Audit Progress Report 4RESOLVED – That the report be noted. Noted Open
25 Mar 2026 wInternal Audit Plan and Charter 2026-27RESOLVED – ( i ) That the report be noted. (ii) That the 2026/27 internal Audit Plan and Charter be approved. Noted Open
25 Mar 2026 Corporate Risk Register - Q3 UpdateRESOLVED – That the report be noted. Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies