Resolved
RESOLVED – That the be noted.
AI summaryAudit Committee noted external auditor's progress report confirming an unqualified opinion on 2024/25 accounts and proposed total fees of £407,802.
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Resolved
RESOLVED – That the be noted.
External Audit Progress Report Stockport Metropolitan Borough Council
March 2026 Contents
1. Audit progress 2. Audit fees and other services 3. National publications Audit progress 01 Audit progress
Purpose of this report This report provides the Audit Committee with information about progress in delivering our responsibilities as your external auditors.
Audit for the year ending 31 March 2025
Financial statements audit Members will be aware that we presented our Audit Completion Follow up Letter to the December 2025 Audit Committee meeting. The report identified the work that was outstanding at that time. We completed that outstanding work and did not identify any further matters to report to members. We issued an unqualified audit opinion on 12 December 2025. We also issued our Auditor’s Annual Report on the same date. Having completed the audit we have considered the impact of the work completed on the audit fees. Public Sector Audit Appointment Ltd (PSAA) determine the scale fee for the Council’s audit and publish this each November. The scale fee covers the work required as the Council’s appointed auditor under the NAO Code of Audit Practice. The scale fee for 2024/25 was set at £353,760. Work on additional audit risks and to respond to recent changes in accounting or auditing standards is not covered by the scale fee and is subject to additional audit fees. PSAA scrutinise our proposed additional fees and consider whether to approve them. We have agreed the proposed fees, set out in section 2 of this update report, with the Director of Finance. Value for money arrangements Our work on the Council’s value for money arrangements for 2024/25 is also complete. Our Auditor’s Annual Report for the 2024/25 audit, which contains our commentary on the arrangements the Council has in place to secure value for money in its use of resources, is being reported to the March Audit Committee meeting. We concluded the Council has proper arrangements in place for the year to 31 March 2025, and we did not identify any significant weaknesses in those arrangements.
Audit for the year ending 31 March 2026 We commenced our planning work for the 2025/26 financial statement audit in March 2026. We will discuss and agree the dates for our audit work with management as part of our planning procedures and will report the timetable in our Audit Strategy Memorandum. At this stage our intention is to carry out the Council’s audit in the summer period in order to complete the audit significantly earlier than for the 2024/25 audit year. Completing the Council’s audit earlier in 2025/26 is a key objective for us, and we will discuss the detailed plan with the finance team. The NAO’s revised Code of Audit Practice from 2024/25, requires auditors to issue their Auditor’s Annual Report, which includes commentary on the Council’s Value for Money arrangements, by 30 November each year. We plan to complete our work on the VFM arrangements and present this report to the Audit Committee in advance of 30 November 2026. Audit fees and other services 02 Audit fees and other services Fees for our work as the Council’s auditor 2024/25 Public Sector Audit Appointments (PSAA) determine the scale fee for the Council’s audit and publish this each November. The scale fee covers the work required as the Council’s appointed auditor under the NAO Code of Audit Practice. The scale fee for 2024/25 was set at £353,760. Having completed our work for 2024/25 we have set out our proposed fees below. The proposed fees have been agreed with the Director of Finance and will be scrutinised and considered by PSAA.
Area of work 2024/25 proposed fees 2023/24 actual fees
PSAA Scale fee £353,760 £326,438
Additional work in respect of Investment Property and Land & Building valuations £22,094 £16,200
Additional work relating to the Council’s pension asset ceiling £5,265 £7,500
Additional fees in respect of IFRS 16 (Leases) implementation £6,878 -
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Audit Progress ReportReport | 580 KB | DownloadRead as text |
Follow Audit Committee at Stockport and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 25 Mar 2026 | 2025/26 Statement of Accounts - Accounting PoliciesRESOLVED ( i ) That the report be noted (ii) That the Council’s proposed accounting policies as set out in Appendix O... | Noted | Open |
| 25 Mar 2026 | Update on the council's Annual Governance Action Plan 2025/26It was agreed that for future meetings, a report containing a timetable that officers work to, together with details ... | Agreed | Open |
| 25 Mar 2026 | Internal Audit Progress Report 4RESOLVED – That the report be noted. | Noted | Open |
| 25 Mar 2026 | wInternal Audit Plan and Charter 2026-27RESOLVED – ( i ) That the report be noted. (ii) That the 2026/27 internal Audit Plan and Charter be approved. | Noted | Open |
| 25 Mar 2026 | Corporate Risk Register - Q3 UpdateRESOLVED – That the report be noted. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.