Stockport Metropolitan Borough Council
Audit Committee, Wednesday 25 March 2026 at 6.00pm

Update on the council's Annual Governance Action Plan 2025/26

Agreed Finance 3 papers

AI summaryStockport Audit Committee notes progress on 2025/26 governance action plan covering transformation, the medium-term financial plan, health reforms, arm's length bodies and decision publication, and asks for a future timetable of governance reports.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeAgreedCommittee also agreed to receive a future timetable of governance reports
Money£12.012m to £23.323m shortfallMTFP gap 2026/27 rising to 2029/30; balanced budget set 26 February 2026
What happens nextFuture timetable report to be providedWill set out when reports go through the governance cycle
Who it affectsCouncil services, residents, partner bodiesCovers transformation, finance, NHS, arm's length companies and decision publication

What was decided

The committee noted the March 2026 update on the council's Annual Governance Action Plan covering progress against five governance areas for 2025/26. Report P1, P2

The committee agreed that future meetings will receive a report containing a timetable officers work to, details of reports going through the governance cycle, and a timeline of forthcoming information and linked reports and meetings.

Why

The council's Annual Governance Statement 2024/25 identified five areas needing action during 2025/26, and the report set out progress on each to give the Audit Committee oversight. Report P1, P2, P3

Officers reported that the financial position is increasingly difficult, the Integrated Care Board reported a significant year-end deficit, and arm's length bodies including Stockport Homes required governance changes, all of which the committee needed to be aware of. Report P5, P6, P7, P8, P10, P11, P14

What happens next

The digital register of interests for officers will be finalised in early course, having been delayed by resources being directed elsewhere, alongside conflicts of interest guidance and annual training records for board members. Report P12, P13

A new AI Ethics Board, co-chaired by two members of the Senior Leadership team, will be established under the oversight of the Senior Information Risk Owner Board. Report P4

Future Audit Committee meetings will receive a governance timetable report, and further updates on arm's length bodies and shared services governance changes will be brought back to the committee. Report P16

The money

  • £12.012m Medium-Term Financial Plan shortfall in 2026/27 Report P5
  • £23.323m Medium-Term Financial Plan shortfall rising to in 2029/30 Report P5

Options considered

  • Chosen: Note the Annual Governance Action Plan progress report. Standard oversight of progress against the 2024/25 statement action plan Report P1, P2
  • Chosen: Receive a future governance timetable report at each meeting. To give the committee clearer sight of when governance items are scheduled

Implications

  • Financial: Council faces a £12.012m shortfall in 2026/27 rising to £23.323m in 2029/30, with funding not keeping pace with rising service demand; a balanced budget was approved on 26 February 2026. Report P5, P6, P7, P8
  • Risk: Without a robust financial approach the council could be pushed closer to needing exceptional financial support from government. Report P8
  • Legal: Officers and members serving on boards of arm's length companies must navigate different legal and cultural frameworks, with potential conflicts of interest between duties to the council and to the company. Report P13, P14
  • Governance: Independent review of Stockport Homes and two shared services reports are likely to require further governance changes, with updates to be brought back to the Audit Committee. Report P14, P16
  • Other: AI implementation is an emerging governance risk and an Ethics Board is being established to oversee its use in service delivery. Report P4
  • Staffing: ICB restructuring is causing unavoidable cuts to staffing resources, with potential knock-on effects on the quality of governance and decision making for shared services including SEND, Safeguarding and Continuing Healthcare. Report P10, P11

Who and where

  • Stockport residents and businesses facing rising cost of living and increasing demand for council services Report P5, P6, P7
  • Council service areas under financial pressure including Social Care, Greenspace, Highways and Homelessness Report P7
  • Stockport Integrated Care Board, subject to NHS England reforms and a place-level oversight process Report P10, P11
  • Arm's length bodies including Stockport Homes Group, TLC and other council-owned companies Report P13, P14, P15
  • Council officers and members serving on boards of arm's length companies Report P12, P13

Timeline

  • July 2025: Departure of TLC's former Chief Executive; Director of Place Management continues as Executive Chair Report P15
  • 10 December 2025: Annual Governance Statement 2024/25 dated, setting out the action plan for 2025/26 Report P2
  • 26 February 2026: Balanced budget for 2026/27 approved at Budget Council Meeting Report P8
  • 2026 to 2030: Council's digital strategy being refreshed to cover this period Report P4
  • 2026/27 to 2028/29: First multi-year local government finance settlement covering these financial years Report P5

Plain English for the jargon

  • MTFP: Medium-Term Financial Plan, the council's multi-year budget and savings planning document
  • PPRRs and CPRR: Project and Programme Progress Reviews and the Corporate Programme Review process used to monitor savings delivery
  • SIRO: Senior Information Risk Owner, the senior officer responsible for information risk
  • ICB: Integrated Care Board, the NHS body responsible for commissioning health services in an area
  • EFS: Exceptional Financial Support, additional government funding available to councils in severe financial difficulty
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item6

Resolved

It was agreed that for future meetings, a report containing a timetable that officers work to, together with details of reports that go to the governance cycle, alongside a timeline as to when council will be receiving further information and links to those reports and meetings would be provided. RESOLVED – That the report be noted.
Word for word from the decision Stockport published for this meeting. Source: democracy.stockport.gov.uk

Follow this further

Built from Stockport's papers

What the report saysPro

Report to Audit Committee

ANNUAL GOVERNANCE ACTION PLAN – March 2026 UPDATE ON GOVERNANCE AREAS TO BE ADDRESSED DURING 2025/26 (AS PER THE ANNUAL GOVERNANCE STATEMENT 2024/25) 1. The council’s Annual Governance Statement (2024/25) identified the following areas/actions to be addressed as part of its Annual Governance Action Plan that will need to be addressed during 2025/2026.

2. The first two columns of the Action Plan below are taken from the council’s Annual Governance Statement (2024/25) dated 10 December 2025. The third column has been added to this report as an update to the audit committee on the progress made during 2025/26.

No. Governance Area and Lead Officer Action proposed during 2025/26 Progress Update – 2025/26

1 Transformation – Assistant Director for Strategy, Our transformation programme is aligned to the Regular joint reviews are Transformation and Digital ambition set out in our One Future strategy and undertaken by the service’s our MTFP. Our resource will be focused on leadership and the Corporate delivering transformation that will make the Leadership Team to consider Our transformation programme is closely aligned to biggest impact for the organisation in ensuring prioritisation and any re- our MTFP so that we can transformation services that we remain financially sustainable. prioritisation required of the whilst ensuring we remain financially sustainable. council’s transformation programme. This ensures the This will be clearly aligned to delivery of our programme is flexible and The challenge to reduce spend across the council plan ambitions, particularly around adaptable and responds to organisation remains a key pressure this year with ensuring we are delivering efficient and effective changing needs. It also ensures significant savings needing to be found through services. that resource is directed in the right places, at the right time, No. Governance Area and Lead Officer Action proposed during 2025/26 Progress Update – 2025/26

transforming the way we work, in order to achieve a delivering the best value for balanced budget. money, best return on investment We will ensure robust governance and effective and most benefit to our residents. It will be crucial to ensure we have robust and clear prioritisation of transformation resource to prioritisation of transformation resource aligned to ensure we are focusing on the areas that will The council’s digital strategy is deliver the key transformation programmes. deliver the biggest return on investment for the being refreshed for 2026 to 2030 organisation. and supports and enables the delivery of our Council Plan A new area of potential risk in relation to governance priorities. is emerging, as referred to above, in relation to AI We will ensure that any proposals for the use of With regards to AI, the SIRO and how its implementation may affect decision AI will be considered from a governance and Board (Senior Information Risk making. ethical position to ensure that the use of such Owner) is overseeing the will result in a continued robust and transparent establishment of an Ethics Board approach to governance. which will be co-chaired by two members of the Senior Leadership team, to ensure that the use of AI by the council in relation to the provision of services, is understood by our residents. 2. Delivering the Medium-Term Financial Plan We will undertake the following activities in The council’s approved MTFP (MTFP) - Director of Finance 2025/26 to ensure the MTFP activities receive shows a requirement of £12.012m appropriate oversight and governance: in 2026/27 rising to £23.323m in 2029/30, having set a balanced The council’s financial position over the medium term budget for 2026/27. is increasingly challenging. Councils across the  Ongoing updates of MTFP based on country are facing significant and urgent funding latest information/data that could impact No. Governance Area and Lead Officer Action proposed during 2025/26 Progress Update – 2025/26

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Enc. 1 for Update on the council's Annual Governance Action Plan 2025/26Report 338 KB DownloadRead as text
PDF
Supplement to Audit Committee Report 18 March 2026 VBReport 266 KB Download
PDF
Update on the council's Annual Governance Action Plan 2025/26Report 128 KB Download

At this meeting

Whole meeting

Who was there

8 of 9 attended
SG
Councillor Sue GlitheroChair, present
CM
Councillor Carole McCannVice-Chair, present
MJ
Councillor Mark JonesCommittee Member, present
HK
Councillor Huma KhanCommittee Member, present
PW
Councillor Paul WrightCommittee Member, present
AW
Councillor Alex WynneCommittee Member, apologies, sent representative
PM
Philip Mills Co-opted MemberCo-Optee, present
CH
Carol HargreavesSecretary, expected
CM
Councillor Colin MacAlisterCommittee Member, present

More from Stockport Audit Committee

All decisions
MeetingDecisionOutcome
25 Mar 2026 2025/26 Statement of Accounts - Accounting PoliciesRESOLVED ( i ) That the report be noted (ii) That the Council’s proposed accounting policies as set out in Appendix O... Noted Open
25 Mar 2026 Internal Audit Progress Report 4RESOLVED – That the report be noted. Noted Open
25 Mar 2026 wInternal Audit Plan and Charter 2026-27RESOLVED – ( i ) That the report be noted. (ii) That the 2026/27 internal Audit Plan and Charter be approved. Noted Open
25 Mar 2026 Corporate Risk Register - Q3 UpdateRESOLVED – That the report be noted. Noted Open
25 Mar 2026 Anti-Fraud, Bribery and Corruption Policy 2026/27RESOLVED – That the revised Anti-Fraud, Bribery and Corruption Policy/Strategy be approved. Approved Open