Audit Committee, Wednesday 25 March 2026 at 6.00pm

Corporate Risk Register - Q3 Update

Noted Finance 2 papers

AI summaryStockport Audit Committee noted the Q3 2025/26 Corporate Risk Register, which covers 16 risk areas and reports a £63m forecast DSG deficit alongside significant SEND and finance pressures.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedReport acknowledged by Audit Committee
MoneyNot stated
What happens nextQuarterly updatesContinued monitoring of risk register
Who it affectsCouncil services and residentsRisks span all directorates

What was decided

The Audit Committee noted the Q3 2025/26 Corporate Risk Register update, presented in a fully overhauled format and content from the Director of Finance (Section 151 Officer). Report P1, P2

Why

The Committee needed to consider the corporate risk position of the council, including a requirement to set a balanced budget for 2026/27, manage a growing DSG deficit, and respond to significant financial pressures highlighted in the medium term. Report P17, P18, P117

What happens next

The risk register will continue to be reviewed quarterly, with ongoing monitoring via the quarterly Financial Monitoring Report, and any major changes will be reported to Members throughout the year to inform decision making. Report P18, P19, P20

The money

  • £12.012m MTFP requirement in 2027/28 Report P18
  • £23.323m MTFP requirement rising to in 2029/30 Report P18
  • £43m DSG deficit at end of 2024/25 financial year Report P117
  • £63m DSG deficit forecast for 2025/26 Report P117
  • c£20m Forecast DSG in year overspends Report P117
  • £4.490 million Stockport ICB efficiency target for 2025/26 Report P101
  • up to £15m Possible SEND high needs capital funding for Stockport from £3bn national allocation Report P64

Implications

  • Financial: MTFP shows a £12.012m requirement in 2027/28 rising to £23.323m in 2029/30, and the DSG deficit is forecast to reach £63m by end of 2025/26. Report P18, P117
  • Financial: Fairer funding review outcome is described as extremely disappointing and presents a significantly more challenging financial position over the medium term. Report P18, P19
  • Financial: Government will fund 90% of SEND deficits under a recent announcement, though details are still being understood, and the DSG override is due to end on 31.3.28. Report P118, P119
  • Legal: Failure to comply with the Civil Contingencies Act 2004 and statutory compliance duties for property and adult social care are monitored risks. Report P89, P113
  • Equalities: Failure to co-produce strategies with residents could damage relationships and trust with local communities, and lack of diversity in senior leadership is a workforce risk. Report P13, P14, P97, P98
  • Climate: Council declared a Climate Emergency in March 2019, with targets of Carbon Neutral by 2038 and Net Zero for operations by 2030; operational emissions have reduced by approximately a third since 2018/19 baseline. Report P77, P78
  • Risk: Cyber risks include social engineering, third party supplier vulnerabilities, ransomware, outdated software, insider threats, and emerging risks from AI technologies such as deepfakes. Report P25, P26, P28, P30, P34, P35, P37
  • Staffing: Workforce risks include difficulties recruiting and retaining staff, particularly in adult social care, and an ageing population requiring more care staff. Report P56, P95, P96, P97

Who and where

  • Council residents and service users across all directorates Report P1
  • Adults with care and support needs Report P50, P67, P70
  • Children with special educational needs and disabilities Report P64, P115, P117
  • Council staff and prospective employees Report P94, P95, P96
  • Suppliers and partners delivering services on behalf of the council Report P38, P42, P43
  • Local communities and voluntary sector organisations Report P13, P14, P15

Timeline

  • March 2019: Council declared a Climate Emergency Report P77
  • Q3 2025/26: 24/7 Security Monitoring and Response Service to be implemented Report P23, P24
  • December 2025: Level 7 apprenticeships cease Report P97
  • April 2026: Children's Wellbeing and Schools Bill and Partnership Programme to be delivered Report P68
  • 2030: Target for Net Zero emissions in Council operations Report P78
  • 2038: Target for Carbon Neutral status Report P78
  • 31.3.28: DSG override currently due to end Report P118, P119

Plain English for the jargon

  • MTFP: Medium Term Financial Plan
  • DSG: Dedicated Schools Grant
  • ASC: Adult Social Care
  • ICB: Integrated Care Board
  • DPA: Data Protection Act
  • FMR: Financial Monitoring Report
  • CAN: Climate and Nature Members Group
  • CLT: Corporate Leadership Team
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item9

Resolved

RESOLVED – That the report be noted.
Word for word from the decision Stockport published for this meeting. Source: democracy.stockport.gov.uk

Follow this further

Built from Stockport's papers

What the report saysPro

Report to Audit Committee

Corporate Risk Register Q3 2025/26

Corporate Risk Register 2025/26 Q3

Pre – Post mitigation mitigation Risk Area Owner Existing Controls Emerging risks & opportunities (Inherent) (Residual) (CD / HoS) score score

1. Change Corporate Management Leadership Team (Holly Rae/Gill Lawton) Specific risks:

Ineffective employee All colleague survey provides engagement/involvement insight, feedback and in new delivery models experience around change. affects colleague buy in and delivery objectives. HR/OD business partner roles (working alongside L3 x I2 Transformation team) are key to supporting management to L2 x I1 Low deliver change. Low Medium Corporate Risk Register Q3 2025/26

Limited resource in the  Utilising IT to streamline Transformation function project management. requires prioritisation of resource and projects to  Updates on the deliver those with transformation maximum benefits. programme are published L4 x I3 within the Cabinet’s L3 x I2 response to the MTFP. Medium/ This includes Low/Mediu High identification of proposals m to support a balanced budget.  Joint Transformation Steering Group.

Insufficient management  Outcomes frameworks information business and related monitoring in intelligence to properly place for key strategic model proposed changes partnerships and their and impacts. delivery plans.

L3 x I2  Monthly performance Low/Medi item discussed at CLT um which includes PPRR, Spotlights (e.g. L2 x I2 workforce) and corporate Low measures.

 Dashboard and reports have been created, or are being produced, to assist with monitoring outcomes, alongside Corporate Risk Register Q3 2025/26

existing reporting frameworks (e.g. PPRR).

 Work underway between BI and HR to improve access to and analysis of presentation of workforce data which will support improved manager insight.

Services unable to  Programme Governance provide the required level in place for key enabling of input into strategic programmes (e.g. Live cross cutting L3 x I2 Well, Digital and Fair & programmes. Inclusive). L2 x I2 Low Medium  (See Risk 14- Low Recruitment and Retention).

Failure to co-produce  One Stockport: One strategies and Future launched in 2023 approaches to inclusion is the latest phase of our with residents, making it Borough Plan. Priorities difficult to build in the plan have been relationships and trust mapped to strategic L2 x I3 with local communities. partnerships. Low  Stockport Council have Medium invested in community and neighbourhood Corporate Risk Register Q3 2025/26

networks with the ambition that these L3 x I3 support stronger Medium community voice and High power, local coordination and relationships between the council and its communities.

 Strategic investment in Sector 3, our local infrastructure organisation (LIO).

2. Financial Headline risk Failure to deliver MTFP (savings targets and balanced budget).

Specific risks The council’s approved MTFP shows The financial landscape  Ongoing updates of the L3 x I3 a requirement of £12.012m in 2027/28 is extremely challenging MTFP based on latest Medium rising to £23.323m in 2029/30, having due to inflationary costs information/data that High set a balanced budget for 2026/27. and ever-increasing impact on the Corporate Risk Register Q3 2025/26

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Corporate Risk Register: Q3 UpdateReport 1.1 MB DownloadRead as text
PDF
Corporate Risk Register: Q3 UpdateReport 292 KB Download

At this meeting

Whole meeting

Who was there

8 of 9 attended
SG
Councillor Sue GlitheroChair, present
CM
Councillor Carole McCannVice-Chair, present
MJ
Councillor Mark JonesCommittee Member, present
HK
Councillor Huma KhanCommittee Member, present
PW
Councillor Paul WrightCommittee Member, present
AW
Councillor Alex WynneCommittee Member, apologies, sent representative
PM
Philip Mills Co-opted MemberCo-Optee, present
CH
Carol HargreavesSecretary, expected
CM
Councillor Colin MacAlisterCommittee Member, present

More from Stockport Audit Committee

All decisions
MeetingDecisionOutcome
25 Mar 2026 2025/26 Statement of Accounts - Accounting PoliciesRESOLVED ( i ) That the report be noted (ii) That the Council’s proposed accounting policies as set out in Appendix O... Noted Open
25 Mar 2026 Update on the council's Annual Governance Action Plan 2025/26It was agreed that for future meetings, a report containing a timetable that officers work to, together with details ... Agreed Open
25 Mar 2026 Internal Audit Progress Report 4RESOLVED – That the report be noted. Noted Open
25 Mar 2026 wInternal Audit Plan and Charter 2026-27RESOLVED – ( i ) That the report be noted. (ii) That the 2026/27 internal Audit Plan and Charter be approved. Noted Open
25 Mar 2026 Anti-Fraud, Bribery and Corruption Policy 2026/27RESOLVED – That the revised Anti-Fraud, Bribery and Corruption Policy/Strategy be approved. Approved Open