That Cabinet authorise the Director of Regeneration in consultation with the procurement team to seek tenders for the construction of the CoRE Education building, and to award a contract to the contractor which offers the most economically advantageous tender to the City Council, provided they are set within the limits outlined in this report.
Word for word from the decision Stoke-on-Trent published for this meeting.Source: moderngov.stoke.gov.uk
1. It is recommended that Cabinet authorise the Director of Regeneration in consultation with the procurement team to seek tenders for the construction of the CoRE Education building, and to award a contract to the contractor which offers the most economically advantageous tender to the City Council, provided they are set within the limits outlined in this report.
Report Summary:
1.1The main objectives of the CoRE project are to :-
1. Contribute to the regeneration of Longton by bringing back into economic use and enhancing the heritage features of the Enson Pottery Works, revitalising 5,938 sq.m of total space, attracting over 1000 business visitors per annum and creating additional jobs and business, by 2014.
2. Contribute towards the transformation of the Longton economy by levering additional private sector investment, leading to new additional activity as a result of CoRE in the locale, by 2014.
3. Create a CoRE visitor hub in approx space of 254 sq.m that provides for a good quality visitor experience, space for CoRE staff and a focal point for retrofit meetings and networks, by 2014.
4. To establish a high quality skills and learning facility (approx 1509 sq.m of space to BREEAM very good or excellent at current standards) accommodating Stoke- on-Trent College Diploma Centre delivery and the provision of wider knowledge and learning for all communities, by 2014.
1.2There has been positive determination of the planning application in September 2010 securing the development of the site. As such, the project is at a critical point to enable successful delivery.
Report Page 1 1.3. The report is brought to Cabinet to authorise delegated authority because of;
• The strategic importance of the scheme.
• The tight programme timescales required to deliver the Education building in line with funder requirements.
Supporting Information:
Background
2.1The new CoRE Project will demonstrate how high quality BREEAM Excellent ‘new build’ can co-exist and integrate with building refurbishment at the old Enson works pottery to create an exemplar blend of learning and refurbishment demonstration.
2.2The project will bring back into economic use a dilapidated building. There are two key specific uses from a revitalised site and environs. Firstly, a newly built skills and learning facility of 1509 sq.m (gross) and 1347sq.m (net) – (Education Building) located on three floors. This will permit Stoke-on-Trent College to deliver a Construction and Built Environment Diploma and other skills and learning providers to top up skills necessary for retrofit installation and maintenance.
2.3Secondly, a facility to host formal visits of groups of people. Introductory and concluding presentations will be made in the centre as will presentations and lectures on particular topics of contemporary interest. This part of the building will also provide a small suit of offices for CoRE’s staff. The visitor centre comprises 254 sq.m (gross) and 212 sq.m (net) of floor space.
Current Proposal
3.1The project is at a critical point to enable successful delivery. To ensure this happens in a timely manner, and align with the project programme it is necessary to prepare for the award of the Education building contract in January 2011.
3.2In light of the funding availability and the determination of the planning application it is programmed that Contract 1 - the demolition works will commence on site early in December 2010 with Contract 2 - the Education building works following in January 2011.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Councillor Mohammed Pervez Leader of the CouncilChair, present
RI
Councillor Ross Irving Deputy Leader of the Council and Cabinet Member for Community Safety, Partnerships and the Local Strategic PartnershipCabinet Member, apologies
HL
Councillor Hazel Lyth Cabinet Member for Adult Social Care and Health (Sport, Leisure and Culture)Cabinet Member, present
DG
Councillor Debra Gratton Cabinet Member for Children and Young People's ServicesCabinet Member, present
MS
Councillor Mervin Smith Cabinet Member for City Development (Regeneration)Cabinet Member, present
TR
Councillor Tom Reynolds Cabinet Member for Communication and Community EngagementCabinet Member, present
TF
Councillor Terence Follows Cabinet Member for Environment, Waste Management and Neighbourhood ServicesCabinet Member, present
BW
Councillor Brian Ward Cabinet Member for Housing, Planning and TransportationCabinet Member, present
KC
Councillor Kieran Clarke Cabinet Member for ResourcesCabinet Member, present
SH
Councillor Sarah Hill Cabinet Member for TransformationCabinet Member, present
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.