That, in order to ensure the future long term viability of CoRE Limited, Cabinet delegate to the Executive Director of Place and Section 151 Officer (in consultation with the Cabinet Member for Green Enterprises and Clean City) the renegotiation of the revolving loan agreement between Stoke-on-Trent City Council and CoRE Limited. 2. That Cabinet agree that the Council can, by way of a Chief Officer Delegated Decision, enter into a loan guarantee agreement with the Building Research Establishment (BRE) to enable the repayment of £0.2m from CoRE Limited to the Council by the 31 st December 2014. 3. That Cabinet note that following difficult circumstances during the embryonic stages of the development project and start-up, encouraging progress is now being made by CoRE Limited in establishing itself as a commercially viable and sustainable business. 4. That Cabinet note business performance continues to be closely monitored by the Council’s CoRE Shadow Board.
Word for word from the decision Stoke-on-Trent published for this meeting.Source: moderngov.stoke.gov.uk
Cabinet Centre of Refurbishment Excellence (CoRE) Update Report
Date 18th December 2014 Report of Executive Director (Place) Contact officer(s) Trevor Whittaker (Green Enterprises) Paul Hodgkinson (Finance) Cabinet Member Councillor Andy Platt: Cabinet Member for Green Enterprises and Clean City. Type of Decision (Formerly Notice of Decisions Ref: 384) Wards Affected Broadway and Longton East
1. Purpose of Report 1.1 To provide the second of the bi-annual progress reports on the Centre of Refurbishment Excellence (CoRE) scheme as requested by Cabinet and confirmed in the Minutes of Cabinet Decisions of the 28th April 2010.
1.2To gain Cabinet approval to revise the revolving loan agreement with CoRE Limited to enable the business to concentrate on its growth potential and to safeguard the City Council’s investment both into the physical facility and on- going business.
1.3To make Cabinet aware of: The current financial performance of CoRE and the reasons for needing to revise the revolving loan agreement between the Council and CoRE.
The entering into of a loan guarantee agreement with the Building Research Establishment.
The status of the specific outcomes and outputs required by the external funders, in particular the European Regional Development Fund (ERDF) and Heritage Lottery Fund (HLF).
The current position with respect to the physical facility.
2. Recommendation(s) 2.1 That in order to ensure the future long term viability of CoRE Limited that
Report Page 1 Cabinet delegate to the Executive Director of Place and Section 151 Officer (in consultation with the Cabinet Member for Green Enterprises and Clean City) the renegotiation of the revolving loan agreement between Stoke-on-Trent City Council and CoRE Limited.
2.2That Cabinet agree that the Council can, by way of a Chief Officer Delegated Decision, enter into a loan guarantee agreement with the Building Research Establishment (BRE) to enable the repayment of £0.2m from CoRE Limited to the Council by the 31st December 2014.
2.3That Cabinet note that following difficult circumstances during the embryonic stages of the development project and start-up, encouraging progress is now being made by CoRE Limited in establishing itself as a commercially viable and sustainable business.
2.4That Cabinet note business performance continues to be closely monitored by the Council’s CoRE Shadow Board.
3. Options Considered 3.1 At its meeting on 25 October 2012, Cabinet considered a report addressing issues raised by the Department for Communities and Local Government (DCLG) pertaining to the financial sustainability of CoRE.
3.2Cabinet agreed a solution to support the establishment of CoRE Limited whilst ensuring compliance with both State Aid and European Regional Development Fund (ERDF) regulations. As part of the solution, Cabinet agreed: To provide match funding to the new CoRE company in the sum of £0.8m by way of an interest free loan to secure eligibility to draw down ERDF grant of £0.3m due to changes in the interpretation of eligible match funding by the National Audit Office. To delegate authority to the Director of City Renewal in consultation with the relevant Cabinet Member to negotiate and agree the terms of the loan and funding agreements with the new company.
3.3It should be noted that: The interest free revolving loan was agreed as a mechanism approved by DCLG to facilitate the drawdown of ERDF grant that was critical to the financial viability of CoRE Ltd in its operational phase. CoRE’s Business Plan was not dependent upon the Council facilitating its cash flow at that time given that it expected to generate alternative income streams from its business activities. The issue was that those income streams were not eligible as match to draw down ERDF grant.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.