That Cabinet note that: 1. Progress is now being made by CoRE Limited, during this embryonic stage of the project and business, in establishing itself as a commercially viable and sustainable business in its own right. 2. A business plan now exists that is considered to be realistic, comprehensive and appropriately ambitious. 3. Business performance continues to be closely monitored by the CoRE Shadow Board. 4. That in order to help to secure the future long term viability of CoRE Limited the Council has extended its revolving loan to CoRE by way of a Chief Officer Delegated Decision to address a shortfall in short term cashflow predicted by above business plan.
Word for word from the decision Stoke-on-Trent published for this meeting.Source: moderngov.stoke.gov.uk
Cabinet Centre of Refurbishment Excellence (CoRE) Update Report
Date 26th June 2014 Report of Director of City Renewal (Place) Contact officer(s) Trevor Whittaker, Assistant Director (Green Enterprises) Cabinet Member Councillor Andy Platt: Cabinet Member for Green Enterprises and Clean City. Type of Decision (Formerly Key Decision 384) Wards Affected Broadway and Longton East
1. Purpose of Report 1.1 This is the first of the bi-annual progress reports on the Centre of Refurbishment Excellence (CoRE) scheme as requested by Cabinet and confirmed in the minutes of Cabinet decisions of the 28th April 2010.
1.2Its objective is to make Cabinet aware of: • The progress in implementing the approved recommendations contained in the 25th October 2012 Cabinet Report (please refer to the summary attached in Appendix 1). • Progress in completing the physical development works. • The status of the lease to CoRE Limited and sublease to the Colleges Academy Trust. • The progress in establishing the operations of CoRE Limited. • The current financial performance of CoRE. • That the business plan has been updated (“CoRE Business Plan 2014- 16”). • The status of those specific outcomes and outputs required by the external funders including ERDF and HLF in particular. • The latest position on the revolving loan arrangement between the City Council and CoRE Limited. • The project position in respect to State Aid.
2. Recommendation(s) 2.1 That Cabinet note that: 1. Progress is now being made by CoRE Limited, during this embryonic stage of the project and business, in establishing itself as a
Report Page 1 commercially viable and sustainable business in its own right. 2. A business plan now exists that is considered to be realistic, comprehensive and appropriately ambitious. 3. Business performance continues to be closely monitored by the CoRE Shadow Board. 4. That in order to help to secure the future long term viability of CoRE Limited the Council has extended its revolving loan to CoRE by way of a Chief Officer Delegated Decision to address a shortfall in short term cashflow predicted by above business plan, see section 3.7 below.
3. Options Considered 3.1 Not applicable – This is an update report as request by Cabinet.
Reason for Decision - how the proposal supports the Mandate for Change Make Stoke-on-Trent the place to bring business Support and develop existing business Work with people to promote independence and healthy lives Make Stoke-on-Trent a great city to live in An effective and confident council
Other Implications to be taken into consideration: Legal There are no legal implications arising directly from the contents of this report.
Financial Project Funding The funding for the scheme has been secured from a number of sources including the Department for Education (DfE), the European Regional Development Fund (ERDF), the Heritage Lottery Fund, the Coalfields Regeneration Trust and Stoke- on-Trent City Council (SOTCC), a full breakdown is identified in the table overleaf:
Report Page 2 Investment Type/Funding Approval Spend Predicted to Date Outturn £ £ £ Capital Land 650,000 650,000 650,000 Building & Construction Costs 9,625,616 9,292,663 9,625,616 Demolition & Clearance Costs 235,553 235,553 235,553 Professional Fees 1,919,900 1,919,900 1,919,900 Plant & Equipment 330,115 330,115 330,115 Sub Total 12,761,184 12,428,231 12,761,184
Financed By Stoke-on-Trent City Council – (Land) 650,000 650,000 650,000 Stoke-on-Trent City Council (Cabinet) 4,694,698 4,475,538 4,694,698 Stoke-on-Trent City Council (Delegated) 143,000 29,207 143,000 European Regional Development Fund 4,129,261 4,129,261 4,129,261 Heritage Lottery Fund 600,000 600,000 600,000 Department for Education 2,284,225 2,284,225 2,284,225 Coalfield Regeneration Trust 60,000 60,000 60,000 RENEW 200,000 200,000 200,000
Sub Total 12,761,184 12,428,231 12,761,184
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.