That approval is given to remodel and modernise the council’s seven sheltered housing schemes (Option 2). 2. That approval is given, subject to securing Homes and Community Agency (HCA) grant funding, for the Director of People Services, in consultation with the Cabinet Member for Housing, Neighbourhoods & Community Safety, to include the delivery of 20 new build units of accommodation within the sheltered housing remodelling and modernisation programme (Option 3).
Word for word from the decision Stoke-on-Trent published for this meeting.Source: moderngov.stoke.gov.uk
Date 25 July 2013 Report of Director - People Services Directorate Contact officer(s) Val Bourne – Assistant Director, Housing Services Tanya Gibson – Strategic Manager, Housing Enabling Cheryl Tharp - Project Development & Delivery Officer, Housing Enabling Cabinet Member Councillor Janine Bridges - Cabinet Member for Housing, Neighbourhoods and Community Safety Type of Decision Key Decision (Notice of Decisions Ref: 447) Wards Affected Meir South, Tunstall, Abbey Hulton & Townsend, Ford Green & Smallthorne, Etruria & Hanley, Hollybush & Longton West, Fenton West & Mount Pleasant
1. Purpose of Report 1.1 To present the outcome of the work undertaken by Michael Dyson Associates (MDA) which provides detailed designs and costs associated with a proposed remodelling and new build programme for the council’s seven sheltered housing schemes and based on this, to seek approval to deliver an investment programme (subject to grant funding) as outlined in option 3 below. 1.2 The costing exercise undertaken by MDA follows on from a series of sustainability exercises, the most recent of which was a detailed options appraisal undertaken by Ark Housing Consultancy in 2011. This commission concluded that the sheltered schemes would not be sustainable without intervention and proposed a remodelling programme which would deliver a more modern portfolio of accommodation by eradicating all bedsits, creating larger one and two bedroom units and ensuring that all dwellings would include en-suite bathing facilities. 1.3 Given the scale and estimated investment costs, Ark recommended that the council undertake a detailed design and costing exercise to provide more accurate costs against which to base its investment proposals, the outcome of which forms the basis of this report.
Report Page 1 2. Recommendations 2.1 That approval is given to remodel and modernise the council’s seven sheltered housing schemes (Option 2). 2.2 That approval is given, subject to securing Homes and Community Agency (HCA) grant funding, for the Director of People Services, in consultation with the Cabinet Member for Housing, Neighbourhoods & Community Safety, to include the delivery of 20 new build units of accommodation within the sheltered housing remodelling and modernisation programme (Option 3). 3. Options Considered 3.1 In May 2012, the council commissioned Michael Dyson Associates (MDA) to undertake a detailed design and costing exercise based upon earlier remodelling proposals developed by Ark. MDA’s brief was to design and cost the remodelling of the sheltered schemes based on the recommendations of Ark’s report; it also included the following additional works:
• An in-depth schedule of work relating to fire safety; • Full Disability Discrimination Act Audit; • Full stock condition survey of all schemes; • An option appraisal to determine the possibility of adding extensions and/or new build units to the schemes.
Based on the outcome of this commission, three options have been considered.
3.2Option 1 – Status Quo (No remodelling, compliance work completed) No remodelling - leave units in existing layout. Complete fire safety, Disability Discrimination Act (DDA) works and continue with current 30-year programme of planned maintenance works. 3.3 Option 2 – Remodel and Modernise Remodel all seven schemes as per the MDA design and costing exercise including Fire Safety and Disability Discrimination Act (DDA) works and bring forward key elements of future programmed work to deliver a more fully modernised and sustainable scheme. 3.4 Option 3 – Remodel/Modernise and New Build Remodel all seven schemes as per Option 2 and, subject to the council receiving grant funding from the Homes and Communities Agency (the decision on which should be known in July 2013), deliver 20 replacement units of accommodation through new build provision (17 flats and 3 bungalows) across three of the seven sites.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.