That the General Fund forecast outturn of £66.078m for 2013/14 as at month 9 (a predicted underspend of £0.725m) be noted. 2. That the Housing Revenue Account forecast surplus of £1.855m (an improvement of £2.847m against the budget) be noted. 3. That the forecast capital investment of £120.949m for the year, compared to the approved updated budget of £162.356m, be noted 4. That Directors and portfolio holders continue to implement action plans where pressures exist to reduce the impact of any overspends and provide the best possible platform for 2015/16. 5. That Directors continue to review the use of external support.
Word for word from the decision Stoke-on-Trent published for this meeting.Source: moderngov.stoke.gov.uk
Financial Performance Report as at the end of December 2013 Date 13 February 2014 Report of Interim Assistant Director - Financial Services Contact officer(s) Peter Lewis Interim Assistant Director - Financial Services Kerry Cartlidge Finance and Commercial Manager Cabinet Member Councillor Crowe - Finance, Procurement and Commissioning Type of Decision Information only Wards Affected No Ward Implications
1. Purpose of Report 1.1 To summarise the financial position of the General Fund, Housing Revenue Account and Capital Investment Programme as at the end of December 2013 and provide a forecast outturn for 2013/14. 1.2 At the end of the third quarter the General Fund forecast outturn for 2013/14 is a predicted underspend of £0.725m. The major directorate variances are summarised below. Management teams need to continue to work towards reducing the impact by continuing to implement cost saving measures wherever possible. • The main pressures in People Services relate to: increasing levels of complexity and need in Learning Disability Services (£2.276m); higher numbers of placements in Children in Care (£0.730m); and increased legal and agency costs in Vulnerable Children (£0.512m) • The pressures in City Renewal include: unachieved savings from the current and prior years (£1.400m); additional revenue costs incurred relating to the capital programme (£0.208m); income pressures (£0.468m); and increased waste disposal charges (£0.180m). The pressures are mainly being offset by non-departmental budget savings: • Within Non-Departmental Costs: there has been a delay in implementing a number of cross cutting savings (£3.235m); financing costs are projected to underspend (£2.750m); the costs of redundancy are estimated to be lower following the development of the budget savings proposals (£1.500m); and the increase in energy costs was lower than predicted (£1.054m).
Report Page 1 1.3 The quarter 3 Capital Investment Programme forecast outturn for 2013/14 is £120.949m representing a net £41.407m variance. £35.660m of the underspend is planned to be carried forward. 2. Recommendations 2.1 That the General Fund forecast outturn of £66.078m for 2013/14 as at month 9 (a predicted underspend of £0.725m) be noted. 2.2 That the Housing Revenue Account forecast surplus of £1.855m (an improvement of £2.847m against the budget) be noted. 2.3 That the forecast capital investment of £120.949m for the year, compared to the approved updated budget of £162.356m, be noted. 2.4 That Directors and portfolio holders continue to implement action plans where pressures exist to reduce the impact of any overspends and provide the best possible platform for 2015/16. 2.5 That Directors continue to review the use of external support.
3. Options Considered 3.1 There are no options associated with this report.
Reason for Decision - how the proposal supports the Mandate for Change Make Stoke-on-Trent the place to bring business Support and develop existing business Work with people to promote independence and healthy lives Make Stoke-on-Trent a great city to live in An effective and confident council
Other Implications to be taken into consideration: Legal None
Financial See report detail
Human Resources None
Equality Impact / None Human Rights considerations
Public Health None
Environmental None Impact
Report Page 2 Public Services None (Social Value) Act 2012
Impact on Customers/Partners Services are being delivered in accordance with the MTFS agreed in February 2013.
Background papers and information sources Capital Programme Update 2013/14–2015/16 – City Council 17 October 2013 Budget Setting Report 2013/14 – City Council 28 February 2013 HRA Rent Setting Report 2013/14 – City Council 24 January 2013
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.