That the list of assets listed below be approved for disposal: 15 Trinity Street; Area Support Office ( Bucknall ); Area Support Office ( Longton ); Area Support Office ( Tunstall ); Burslem Day Centre; Burslem Local Centre; Burslem Town Hall ( Ceramica ) – potential alternative use; Commerce House; Customer Access (Dewsbury Road); 380 Chell Heath Road; Goodson Building; Gordon House; Hanley Central Library; Hanley Local Centre; Hanley Town Hall; Longton Local Centre; Meir Local Centre; Queensbury CEC; Regent Centre; Ringway House (Leased); Shelton Youth and Play Centre; Swann House; Swift House; The Lock Canal Arm 3; Tontine Building; Tunstall Library (proposed that the Library will move to Tunstall Town Hall); Unison Office (Former Stoke Library); Unit C Metro Business Park; Weston Coyney Training and Development Centre 2. That the Capital Investment Programme for 2014/15 to 2017/18 be recommended to City Council for approval
Word for word from the decision Stoke-on-Trent published for this meeting.Source: moderngov.stoke.gov.uk
1.1To present the Capital Investment Programme for 2014/15 to 2017/18 to be recommended to City Council for approval.
1.2The capital investment programme is linked to the Revenue Budget and Council Tax Setting 2014/15 presented at this meeting.
1.3To seek approval for asset disposals originally presented to Cabinet on 19 December and 23 October 2013.
Recommendations
2.1That the list of assets as identified in Appendix B is approved for disposal;
2.2That the Capital Investment Programme for 2014/15 to 2017/18 be recommended to City Council for approval
Options considered
3.1The Capital Programme continues to be ambitious, whilst remaining affordable. This includes an appropriate amount of over-programming in the context of the value and size of the investment proposed. To achieve this aim, existing projects and new opportunities will be subject to continuing challenge and review.
3.2The options explored for each scheme include ways of reducing costs; securing further external funding; re-phasing and sequencing; or indeed stopping the project altogether in the context of priority, strategic alignment, value for money and impact.
Report Page 1 Reason for Decision - how the proposal supports the Mandate for Change Make Stoke-on-Trent the place to bring business Support and develop existing business Work with people to promote independence and healthy lives Make Stoke-on-Trent a great city to live in An effective and confident council
Other Implications to be taken into consideration: Legal: The city council has to set a robust and legal budget before 11 March 2014, as set out in the Local Government Finance Act 1992. Financial: The financial implications are set out in the body of the report. Human Resources: N/A Equality Impact and Where applicable, projects within the original capital programme were Human Rights subject to an equality impact assessment. considerations: The impacts of any changes to projects as part of this update have been considered to assess whether the original EIA will be affected and where necessary appropriate action has been taken. Public Health: N/A Environmental No direct implications Impact Public Services No direct implications. The procurement for goods and services in (Social Value) Act delivering capital projects will consider the implications of the Public 2012 Services (Social Value) Act 2012.
Impact on No direct implications in this report. Each scheme when considered customers/partners will incorporate an impact assessment where appropriate.
Background papers and information sources: Capital Programme Update - City Council 17 October 2013
Enclosures: Appendix A Risk Register Appendix B Assets for Disposal
Report Page 2 Report Detail
Capital Programme Proposals 2014/15 – 2017/18 1. Background
1.1The current Capital Investment Programme was approved by City Council on 17 October 2013. This budget proposal for 2014/15 to 2017/18 is principally based on the October programme with a number of small adjustments reflecting approvals made to capital schemes since October and the capital outturn position as assessed at the end of quarter 3.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.